Summer Special Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 713PS592

AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Questions and Answers

Questions 4

The Web Content Manager has provided the Web Developer with a mock up

of the 'Contact Us' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads 'Delete' instead of 'Cancel'.

What action should the Web Content Manager take?

Options:

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Buy Now
Questions 5

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

'all members of the project understand and accept the DSDM approach'.

What action should the Project Manager take?

Options:

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Buy Now
Questions 6

Answer the following questions about the contents of the DSDM

products.

Each of the following questions includes true statements about the project

but only two statements are appropriate entries for the DSDM product

identified.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 statements represent appropriate entries for the Business Case?

Options:

A.

A list of high-level functional and non-functional requirements that the

project should meet written as User Stories.

B.

Coffee shops that sell Fairtrade products and alcohol from local breweries

out perform other coffee shops in the market.

C.

The Sales Manager has been asked to produce a report within the next

two days showing the number of generic insurance policies sold to coffee

shops over the past three years.

D.

The Sales Manager has calculated that the new coffee shop insurance

product will increase revenues by 10% each week.

E.

Market research shows that the number of coffee shop patrons taking

legal action against retailers has increased by 200% over the past two

years.

Buy Now
Questions 7

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Buy Now
Questions 8

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.

Buy Now
Questions 9

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Buy Now
Questions 10

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

AgilePM-Practitioner Question 10

Options:

Buy Now
Questions 11

The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the

agreement of the team.

Which Agile principle MOST influences this course of action?

Options:

A.

Deliver on time.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Buy Now
Questions 12

The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open

Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.

At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.

However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video

tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of

storage space on the company server and require minimal maintenance.

The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.

Remember to limit your answers to the number of selections requested in each question.

Which 2 individuals should the Facilitator invite to participate in the Workshop?

Options:

A.

Chief Executive (Steering Group)

B.

Representative for Earth Excavations (Solution Developer)

C.

Representative for Timber Tigers (Solution Developer)

D.

IT Operations Manager (Solution Development Team)

E.

Marketing Director (Business Visionary)

Buy Now
Questions 13

A three-month timeframe has been specified to catch the seasonal sales window.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Buy Now
Questions 14

Which 2 statements explain why the Architecture Angels' Marketing Director would be an appropriate Business Visionary?

Options:

A.

Is a friend of the Architecture Angels' Chief Executive.

B.

Is fully committed to changing the company's strategic direction to include hotel renovation.

C.

Is one of the original four founders of the company.

D.

As a Director, will ensure that the project is NOT driven by the cost-consciousness of the Finance Director in the role of Business Sponsor.

E.

Has a passion for old buildings and can see the potential for business opportunity.

Buy Now
Questions 15

Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?

Options:

A.

Accustomed to bringing in contract staff for short periods of time.

B.

Closely manages the building team so that they consistently produce high-quality work.

C.

Is able to represent the team in all daily meetings.

D.

An experienced builder who is good at turning a brief into a practical design.

E.

Is empowered by Timber Tigers' management to make decisions on the building work.

Buy Now
Questions 16

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

At the beginning of Solution Development Timebox A, the Timebox is being

planned in detail. Although Foundations was conducted at a high level, the

Prioritised Requirements List was baselined. Now the Solution Development

Team is setting detailed acceptance criteria against each requirement.

Is this an appropriate approach to setting detailed acceptance criteria?

Options:

A.

Yes, because acceptance criteria can only be understood at a high level during Foundations and will always need further investigation.

B.

Yes, because the Solution Development Team members will be setting acceptance criteria for the first time during Solution Development Timebox A.

C.

No, because the Solution Development Team should NOT be involved in setting acceptance criteria.

D.

No, because acceptance criteria should be set in detail against each requirement during Foundations.

Buy Now
Questions 17

The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in

the gardens could be enjoyed.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Deliver on time.

C.

Collaborate.

D.

Never compromise quality.

Buy Now
Questions 18

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because only Must Have requirements should be fully understood.

B.

Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.

C.

No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.

D.

No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.

Buy Now
Questions 19

The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are

four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and

to know who should be where. Some of the contractors have started to turn up late to the site.

Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The

Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.

Answer the following questions about motivating the contractor teams according to Agile Project Management.

How should the Project Manager encourage the resources to operate more successfully?

Options:

A.

Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan.

B.

Hold a separate Daily Stand-up meeting for contractors only.

C.

Provide a detailed plan of activity for each contractor team.

D.

Schedule the electrical and plumbing teams so that they work on different Timeboxes.

Buy Now
Questions 20

The Timebox to deliver the online reservation system through the Hoy Hall website has experienced a major issue. During Timebox C a test was completed to

simulate an attack on the financial element of the online reservation system, with the intention of finding security weaknesses. It was found that it was

potentially possible to gain access to the system, its functionality and data. Further work is therefore needed to meet the information security elements of a

customer financial transaction.

Answer the following question about the actions to be taken by each role.

Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system. Column 2 lists the key roles. For each action in Column 1,

select from Column 2 the role that should carry out the action.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1

    Advise how the legislation on the transfer of data will affect the requirements

and the system.

    Agree the changes needed to the corporate technical architecture with the

Architecture Angels IT support team.

    Ensure the information security vulnerability is communicated to the AA Head

Office IT Director.

    Evaluate the impact of proposed security controls on the business and decide

on the most suitable solution.

    Reprioritise the requirements on the Prioritised Requirements List associated

with the security issue.

Column 2

    Project Manager

    Business Sponsor

    Business Visionary

    Technical Coordinator

    Business Analyst

    Team Leader

    Business Ambassador

    Solution Developer

AgilePM-Practitioner Question 20

AgilePM-Practitioner Question 20

Options:

Buy Now
Questions 21

Which 2 statements explain why the Architecture Angels' Operations Director would be an appropriate Business Advisor?

Options:

A.

Is in charge of providing appropriate scenarios to check the security systems.

B.

Is one of the original four founders of the company.

C.

Can provide input about problems experienced by the people who run the hotels.

D.

Has specialist knowledge about the targets for staff performance.

E.

Has been involved with monitoring the progress of previous company projects.

Buy Now
Questions 22

Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.

Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully

meet Hoy Hall requirements, after deployment.

2. Developing a fully functioning in-house system, developed and hosted by Architecture

Angels IT Operations team.

3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's

specification.

4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,

until a suitable system can be implemented at the site.

5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.

Column 2

    Maintainability is a required attribute of the initial delivered solution

    Deliver first, re-engineer later

    Short-term, tactical solution

AgilePM-Practitioner Question 22

Options:

Buy Now
Questions 23

A difference of opinion on the outcome of an earlier project has created a

'them and us' culture between the Sales Department and the Operations

Department.

What action should the Project Manager take to resolve this?

Options:

A.

Allow the different skillsets to work independently of one another so as

not to create further conflict.

B.

Brief the team and the Business Visionary on the use of an Agile Project

Management approach and the requirement to collaborate.

C.

Appoint only those members of staff who are prepared to work

collaboratively.

D.

Circulate a copy of the Business Case to all members of the Solution

Development Team and project-level roles and invite feedback.

Buy Now
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: Sep 14, 2024
Questions: 78

PDF + Testing Engine

$66.4  $165.99

Testing Engine

$46  $114.99
buy now AgilePM-Practitioner testing engine

PDF (Q&A)

$42  $104.99
buy now AgilePM-Practitioner pdf