Black Friday Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Better-Business-Cases-Practitioner Better Business Cases Practitioner Exam Questions and Answers

Questions 4

Which 2 observations correctly evaluate risks that could affect the affordability of this project?

Options:

A.

Without the sale of Pittville High School, the project is no longer viable.

B.

The project would still be viable if equipment costs were to double after Year 3.

C.

If the other income were to be withdrawn for any reason, LEA Funding alone could fund the running costs of the scheme after Year 3.

D.

The project would no longer be affordable if funding were to increase by 5%.

E.

Income from the hire of the Sport Facilities must continue to increase every year for the scheme to be viable.

Buy Now
Questions 5

The Consortium has appointed its own assurance on the Western Area Learning

Improvement Programme.

Which action should be completed by this role?

Options:

A.

Establish the Pittville project spending objectives.

B.

Confirm the requirements for 16 to 18-year-old learners can be met.

C.

Manage the risks retained by the public sector.

D.

Arrange and schedule the resources required to develop the new learning campus.

Buy Now
Questions 6

Which is an appropriately defined SMART spending objective for more choice of subjects?

Options:

A.

To increase the number of education courses from 55 to 65, preferably more.

B.

To increase the number of education courses offered to 16 to 18-year-olds within three years.

C.

To provide at least 65 different education courses for 16 to 18-year-olds within three years.

D.

To increase the achievement of qualifications by a minimum of 15% within three years.

Buy Now
Questions 7

Using the Scenario, answer the following question about the Strategic Case section of the

Strategic Outline Case (SOC) for the Pittville project.

Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each

line identify the appropriate option, from options A to E, that applies. Each option can be used once,

more than once or not at all.

Better-Business-Cases-Practitioner Question 7

Better-Business-Cases-Practitioner Question 7

Better-Business-Cases-Practitioner Question 7

Options:

Buy Now
Questions 8

There is a need to meet regulations that address the needs of those with Learning Difficulties and Disabilities

Should this item be recorded as a dependency within the Strategic Outline Case?

Options:

A.

No, because the regulations are an externally imposed parameter or constraint.

B.

No, because dependencies should NOT be recorded within the Strategic Outline Case.

C.

Yes, because any actions or developments required by others should be considered if the success of the project is dependent upon them.

D.

Yes, because success of the project is dependent upon compliance with these regulations.

Buy Now
Questions 9

The Director of Pittville University has resigned during the procurement process. As a result, the Deputy Director is now acting as Director. The other schools have now withdrawn their objections to Pittville University running the new campus. It is thought that

the delivery approach could be revised so that Pittville University manages all 16-18-year-olds education and further cost reductions could be achieved. There is no option in the OBC that provides this delivery approach with the service solution of a new

campus.

Should the preferred option be reviewed in the FBC? (Select one)

Options:

A.

No, because the lack of a Director of Pittville University would not affect a delivery approach involving Pittville University.

B.

No, because the preferred option should remain unchanged once selected at OBC.

C.

Yes, because the FBC must demonstrate that the preferred option offers better VFM than the other available options.

D.

Yes, because the FBC should consider the organization's strategy for managing contractual change.

Buy Now
Questions 10

Service Solution 2: 'New development on Pittville University site and close and transfer all further

education units in the Pittville area resulting in financial affordability'.

Which 2 statements are correct about this entry in the Options Framework?

Options:

A.

This is a Service Scope option NOT a Service Solution option.

B.

Delivers against one or more of the critical success factors.

C.

Supports one or more of the Spending Objectives.

D.

Will represent a benchmark for Value For Money throughout the appraisal process.

E.

This is the LEA's preference and therefore the preferred option.

Buy Now
Questions 11

An extract of an entry in the benefits register includes the following information:

1. Benefit type: Cash-releasing

2. Description: A net overall saving in the cost of cleaning

3. Target improvement: Reduce overall costs of cleaning contracts by 10% per annum

4. Responsible officer: Pittville University Procurement Manager.

Which 2 statements apply to these entries?

Options:

A.

Amend entry 1, because the benefit type should be 'financial but non-cash-releasing'.

B.

No change to entry 1, because the benefit is cash-releasing and should be measured in financial terms.

C.

Amend entry 3, because the improvement is unknown.

D.

No change to entry 3, because the benefits register should indicate the level of improvement expected.

E.

Amend entry 4, because the SRO should be the responsible officer for all benefits.

Buy Now
Questions 12

The Financial Appraisal includes an estimated 60% taxation costs that are NOT reclaimable.

Is this an appropriate application of the Five Case Model for the project?

Options:

A.

No, because taxation costs should be excluded from the Financial Appraisal.

B.

No, because it is the Economic Case that should include inflation and taxation costs.

C.

Yes, because the Financial Appraisal should demonstrate value for money.

D.

Yes, because both resource and non-resource costs and benefits should be factored into the analysis.

Buy Now
Questions 13

The rationalization of courses will increase the utilization of teaching staff from 75% to 90% and improve

teacher/pupil ratios.

During which activity should the project manager capture this information?

Options:

A.

Agree strategic context.

B.

Determine spending objectives, existing arrangements and business needs.

C.

Determine potential business scope and key service requirements.

D.

Determine benefits, risks, constraints and dependencies.

Buy Now
Questions 14

The current establishment of support staff will be able to absorb 30% growth in numbers of 16 - 18-year-old learners.

This information has been:

1. Entered in the benefits register

2. Classed as a cash-releasing benefit.

Which 2 statements apply to these entries?

Options:

A.

Amend entry 1, because benefits should be described only in the Economic Case.

B.

No change to entry 1, because non cash-releasing benefits should be entered in the benefits register.

C.

Amend entry 2, because the benefit class should be 'non-cash-releasing'.

D.

No change to entry 2, because an increase in productivity is classified as cash-releasing.

E.

No change to entry 2, because a growth in learner numbers will result in additional revenue.

Buy Now
Questions 15

Pittville University insist that the business scope of the Pittville project should be based on the

development of a new campus on the site of the Old Fire Station Headquarters.

Is this an appropriate application of the Five Case Model for this project?

Options:

A.

No, because Pittville University should NOT be involved in the development of the Strategic Case.

B.

No, because the business scope should determine the affected business areas, functionality and organization.

C.

Yes, because the Old Fire Station Headquarters site has good access from most parts of Pittville.

D.

Yes, because the business scope of the Pittville project should be based on a short list of options.

Buy Now
Questions 16

Which 2 observations correctly evaluate the affordability of the Pittville project?

Options:

A.

The Financial Appraisal shows that this scheme is unaffordable.

B.

At the end of Year 6, E6 million of the initial spending costs will have been recovered.

C.

The surplus Income forecast in Year 1 is sufficient to cover the deficit forecast in Year 2.

D.

The revenue budget should show how long it will take for the surplus income to cover the initial cost of building the new campus.

E.

If expenditure and income continue at the same rate, each subsequent year should return a surplus of Ā£1 million.

Buy Now
Questions 17

Answer the following question about the Programme Business Case.

The following questions include only true statements, but only 2 statements are

appropriate entries for that heading in the Strategic Case section.

Remember to select 2 answers to each question.

Which 2 statements should be recorded under the Organization overview heading?

Options:

A.

The Consortium has been formed to plan the transformation of education and learning for 14-19- year-olds throughout the Western Area.

B.

Formal meetings have been held over the past nine months to establish the goals to be achieved.

C.

Pittville is the commercial, retail and cultural centre of Topland, with a population of circa22,000.

D.

There are problems accessing learning in some parts of the region.

E.

There is a shortage of higher education establishments in the region.

Buy Now
Questions 18

Providing better facilities, improving learning provision and offering a wider choice of education courses.

Which of the key objectives for spend are these objectives based on?

Options:

A.

Economy.

B.

Efficiency.

C.

Effectiveness.

D.

Compliance.

Buy Now
Questions 19

Which action should be completed by the Pittville Project Manager?

Options:

A.

Produce regular progress reports for the Senior Responsible Owner of the

project.

B.

Appoint the Senior Responsible Owner for the project.

C.

Approve the specification for the new learning campus.

D.

Approve the continuation of the project at the end of each delivery stage.

Buy Now
Questions 20

Springbank School has been hugely oversubscribed so has decided to expand its further education unit. It is working formally with

Battledown School to reduce course duplication and to potentially offer a greater range of education courses. The Governors from

Springbank School feel that these scheduled changes need to be reflected in the Pittville project FBC, even though Springbank

was not a shortlisted option.

Should the FBC be updated with the Springbank changes?

Options:

A.

No, because the FBC should NOT be updated for best and final offers.

B.

No, because this new scheme should be considered in the next iteration of the programme business case.

C.

Yes, because the public sector comparator (PSC) should be updated.

D.

Yes, because the preferred way forward for the Pittville project must offer better Value For Money than the other options.

Buy Now
Questions 21

Two of the options in the OBC have been revised, as shown in the table above.

Should Option B be ranked as the preferred option?

Options:

A.

No, because the benefits are greater for Option A.

B.

No, because the public sector test discount rate has been applied.

C.

Yes, because option B has positive liquidity.

D.

Yes, because Option B has the higher NPSV.

Buy Now
Questions 22

Using the Scenario, answer the following questions about the Commercial Case for the Pittville project.

The following questions include only true statements about the project, but only two statements are appropriate entries for the

suggested heading of the Commercial Case.

Remember to select 2 answers to each question.

Which 2 statements should be recorded under the Required services heading?

Options:

A.

20% of the contract price is to be paid up front for materials.

B.

To increase the rate of 16-18-year-olds participating in education and training by at least 15% within the next three years.

C.

The major users of the finished campus will be 16-18 year old learners.

D.

The selected contractor will be responsible for taking measures to reduce any potential errors in the construction phase.

E.

All intellectual property rights are to be maintained by the Local Education Authority.

Buy Now
Questions 23

Using the Scenario, answer the following questions.

What should be prepared to demonstrate how the Pittville project will fit with other initiatives, such as the development of Work Based Learning throughout the Western Area?

Options:

A.

Strategic Outline Case.

B.

Strategic Assessment

C.

Business strategies.

D.

SWOT analysis.

Buy Now
Questions 24

Scoping Solution 2: '20% increase in rate of participation, 75-85 education courses, 15-20%

improvement in qualification success rate'.

Which 2 statements are correct about this entry in the Options Framework?

Options:

A.

Should be rejected as over-ambitious.

B.

Delivers against one or more of the critical success factors.

C.

Will represent a benchmark for Value For Money throughout the appraisal process.

D.

Supports one or more of the Spending Objectives.

E.

Incorrectly identified as a Scoping Solution.

Buy Now
Questions 25

Which statement should be recorded under the Post Project Evaluation heading?

Options:

A.

The Western Area Learning Improvement Programme Director is responsible for delivering the benefits of the Pittville project.

B.

The monitoring of anticipated benefits is to be assessed every year, for a ten-year period.

C.

The rate of 16-18 year olds in education and training to be increased by at least 15% within three years.

D.

New roles will be identified, advertised and assigned before the start of the second academic year of the implementation.

Buy Now
Questions 26

Answer the following question about the Outline Business Case.

The following questions include only true statements about the Pittville project.

However only one statement is an appropriate entry for that heading in the

Management Case section.

Which statement should be recorded under the Programme and Project Management heading?

Options:

A.

Projected inflation will mean that costs will be 6% higher when the campus is operational.

B.

Temporary accommodation will be put on the site of the Old Fire Station Headquarters at least 3 months before the development of the new campus takes place.

C.

Opportunities will be created for teachers to be involved in delivering new courses.

D.

The chosen service provider must have experience in the construction of publicly used buildings.

Buy Now
Questions 27

Using the Scenario, answer the following questions about the Financial Appraisal of the option to build a new campus on

the site of the Old Fire Station Headquarters.

Decide whether the action taken represents an appropriate application of the Five Case Model for this project and select the response

that supports your decision.

The cost of inflation is estimated to be 2% per annum.

Should the project manager use this information when preparing the Financial Appraisal for this scheme?

Options:

A.

No, because the Financial Appraisal should include constant or real prices.

B.

No, because the Financial Appraisal should exclude the cost of general inflation and depreciation.

C.

Yes, because the Financial Appraisal should include the cost of inflation.

D.

Yes, because inflation will reduce the cost of the scheme over time.

Buy Now
Questions 28

Which statement should be recorded under the Risk Management heading?

Options:

A.

The sports facilities at the new campus are to be hired out to external organizations and groups.

B.

A project management special advisor has been appointed from a consultancy specializing in the PRINCE2 methodology.

C.

Schools and universities affected by the Pittville project are to escalate any risks to the Project Manager.

D.

The redefinition of jobs is to be communicated to teaching unions before any communications with staff can be issued.

Buy Now
Exam Name: Better Business Cases Practitioner Exam
Last Update: Nov 16, 2024
Questions: 95

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now Better-Business-Cases-Practitioner testing engine

PDF (Q&A)

$36.75  $104.99
buy now Better-Business-Cases-Practitioner pdf