Winter Special Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 713PS592

C_TS412_2021 SAP Certified Application Associate - SAP S/4HANA Project Systems Questions and Answers

Questions 4

The various work packages in the project are described as individual______________. Choose the correct answer.

Options:

A.

WBS elements

B.

Project definitions

C.

Tasks

D.

Activities

Buy Now
Questions 5

Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

Options:

A.

Material master

B.

Network activity

C.

WBS element

D.

BOM item

Buy Now
Questions 6

Resources

Which of the following transactions can you use to post actual cost for external processing.

Note : there are 2 correct answer for this question.

Options:

A.

Approval of a service entry sheet

B.

Posting a goods receipt

C.

Creating a service entry sheet

D.

Approval of a good receipt.

E.

Creating a purchase order.

Buy Now
Questions 7

Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

Options:

A.

Individual overview capacity requirements

B.

Capacity load work center view

C.

Extended capacity evaluation

D.

Structure overview

Buy Now
Questions 8

In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

Options:

A.

The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)

B.

The purchase order is updated automatically to match the new quantity while saving the project.

C.

A workflow can be triggered to inform the purchasing group.

D.

The system automatically creates a new purchase requisition with the difference to the original quantity

Buy Now
Questions 9

You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question

Options:

A.

The formula for costing in the work center is incorrect

B.

The activity output price for the activity type and cost center assigned to the work center is not maintained.

C.

The duration is missing in the activity

D.

The Determine Costs indicator in the network header rules out planned cost calculation

E.

Integrated planning for the network is active

Buy Now
Questions 10

In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

Options:

A.

Scheduling and capacity category

B.

Scheduling and distribution key

C.

Control key of an activity

D.

Capacity planner group in the network header

Buy Now
Questions 11

You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

Options:

A.

The person responsible for the work center

B.

The person responsible for the superior WBS element

C.

The MRP controller for the network

D.

The person responsible for the network activity

Buy Now
Questions 12

You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?

Note : there are 2 correct answers for this question.

Options:

A.

The procurement type in the material master is set to in-house Production.

B.

The item category of the materials is set tstock item.

C.

The material have no material number.

D.

The item category of the materials is set tnon-stock item.

Buy Now
Questions 13

Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct answers to this question.

Options:

A.

Reservations

B.

Sales order items

C.

Purchase order items

D.

Internal orders

Buy Now
Questions 14

You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

Options:

A.

You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"

B.

You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"

C.

You can always maintain the actual start and finish date of a WBS element

D.

You can only maintain the actual start of a WBS element if the finish date is not maintained

Buy Now
Questions 15

What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.

Options:

A.

Ensure user status must always be set manually

B.

Allow business processes forbidden by SAP system status

C.

Restrict setting user status for individual users

D.

Utilize priorities for setting the user status

Buy Now
Questions 16

A service company uses project management and they complain that the system does not prevent

their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

Options:

A.

Activate availability control for the WBS elements. Define the tolerance limits on each WBS element

B.

Activate availability control in the assigned budget profile. Define the tolerance limits in customizing

C.

Activate commitment management in the project definition Enter the budget in the master data of the top WBS element

D.

Activate availability control for projects in the controlling area. Enter the plan data for each WBS element

Buy Now
Exam Code: C_TS412_2021
Exam Name: SAP Certified Application Associate - SAP S/4HANA Project Systems
Last Update: Dec 11, 2024
Questions: 110

PDF + Testing Engine

$66  $164.99

Testing Engine

$50  $124.99
buy now C_TS412_2021 testing engine

PDF (Q&A)

$42  $104.99
buy now C_TS412_2021 pdf