Black Friday Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

C_TS422_2021 SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Questions 4

What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?

Options:

A.

Material Requirements Planning (MRP)

B.

Capacity Requirements Planning (CRP)

C.

Supply Network Planning (SNP)

D.

Demand Planning (DP)

Buy Now
Questions 5

If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?

Options:

A.

Fill up based on the lot size procedure

B.

Fill up to the maximum stock level

C.

Fill up to the safety stoc level

D.

Fill up to the reorder stock level

Buy Now
Questions 6

Which mhetods are available for goods issue posting of material components for process orders?

Options:

A.

Transfer order

B.

Picking list

C.

Blackflushing

D.

Kanban

Buy Now
Questions 7

What type of time element can be reduced by strategy settings while dispatching?

Options:

A.

Transportation time

B.

Wait time

C.

Queue time

D.

Setup time

Buy Now
Questions 8

You use planning strategy Finite Scheduling - with Reverse adn want to allow scheduling in the past. How can you achive this?

Options:

A.

Specify a negative offset time in the strategy profile.

B.

Specify a positive planning horizon in the strategy profile.

C.

Specify a negative lanning horizon in the strategy profile.

D.

Specify a positive offset time in the strategy profile.

Buy Now
Questions 9

You have a schedule agreement whit a vendor. You want classic MRP to automatically create schedule lines in case of material

shortage.

What must you do?

Options:

A.

Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.

B.

Set the creation indicator for purchase requisitions on initial screen of MRP run

C.

Add the agreement to the source list and mark it for MRP revalance.

D.

Add the agreement to the quota arrangement and mark it for MRP revalance.

Buy Now
Questions 10

What are the consequences when you assgn a planned order to a production line manually, using the planning table in repetitive manufacturing?

Options:

A.

The planed order's component availability is checked.

B.

The planed order is converted to production order.

C.

The planned order's components are copied to the picking list.

D.

The planed order generates capacity requirements

Buy Now
Questions 11

Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?

Options:

A.

Planning with final assembly (40)

B.

Make-to-order production (20)

C.

Make-to-stock production (10)

D.

Planning without final assembly (50)

Buy Now
Questions 12

Which of the following elements does MRP take into account during net requirement calculation?

Options:

A.

Purchase orders

B.

Lot size

C.

Maximum stock level

D.

Safety stock

Buy Now
Exam Code: C_TS422_2021
Exam Name: SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing
Last Update: Nov 23, 2024
Questions: 82

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now C_TS422_2021 testing engine

PDF (Q&A)

$36.75  $104.99
buy now C_TS422_2021 pdf