Advanced Planning uses master data and transaction data from SAP S/4HANA In which data objects can you set the Advanced Planning flag?
Note: There are 2 correct answers to this question.
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
What will happen in the MRP run if you have created a new MRP-relevant material that
supports both in-house production and external procurement?
What does forecasting in the demand planning cycle include?
Note: There are 3 correct answers to this question
Which business processes are affected by settings in the order-type-dependent parameters?
Note: There are 2 correct answers to this question.
What does the material type influence?
Note: There are 2 correct answers to this question.
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing?
Note: There are 2 Correct answers to this question?
You can you use capacity availability checks for production orders, which settings have to be made for this?
Note: There are 2 Correct answers to this question?
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.
what is the impact of this decision?
Note: there are 2 correct answers to this question
You want to create a production order. What methods can you use?
Note: There are 2 correct answers to this question.
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question
You Have a scheduling agreement with a vendor, you want classic MRP to automatically create
schedule lines in case of material shortage, what must you do?
Note: there are 2 correct answers to this question.
What could be the reason for multiple commitments, where several operations have the same scheduled dates on a work center after dispatching?
Note: There are 2 correct answers to this question.
How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.
which actions does the system perform by default when you save a confirmation for a finished
product in repetitive manufacturing?
Note: There are 3 Correct answers to this question.
What data can you maintain in the subitems of a bill of material (BOM)?
Note: There are 2 correct answers to this question.