Easter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Questions 4

What does a line hierarchy in repetitive manufacturing represent?

Options:

A.

A production line with more than one work center

B.

A production line with an alternative sequence in the routing

C.

A production line with a parallel sequence in the routing

D.

A production line with prioritized alternative work centers

Buy Now
Questions 5

You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers to this question.

Options:

A.

Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

B.

Add the agreement to the source list mark it for MRP relevance.

C.

Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.

D.

Add the agreement to the quota arrangement mark it for MRP relevance.

Buy Now
Questions 6

What are the advantages of collective orders? Note: There are 2 correct answers to this question.

Options:

A.

To perform availability checks across the entire collective order

B.

To coordinate orders in the planning board for a collective order

C.

To show the flow of batches across the entire collective order

D.

To post confirmations for the entire collective order

Buy Now
Questions 7

Which business processes are affected by settings in the order type-dependent parameters? Note: There are 2 correct answers to this question.

Options:

A.

Schedule production orders.

B.

Check material availability.

C.

Select master data.

D.

Define integration with cost accounting.

Buy Now
Questions 8

You are a consultant on an SAP S/4HANA Cloud Greenfield project. Which of the following aspects should you focus on to achieve and maintain clean core data quality? Note: There are 2 correct answers to this question.

Options:

A.

Efficiency

B.

Accuracy

C.

Timeliness

D.

Stability

Buy Now
Questions 9

What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

Options:

A.

Order type

B.

Requirements profile

C.

Requirements type

D.

Planning strategy

Buy Now
Questions 10

What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.

Options:

A.

One-off events

B.

Past production planning quantities

C.

Past quotation quantities

D.

Market intelligence

E.

Past sales order quantities

Buy Now
Questions 11

You are trying to create a production order, but NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.

Options:

A.

The order lot size is NOT within the validity range of a production version.

B.

NO production lines are assigned to the production versions.

C.

All production versions for the material are locked.

D.

NO bills of material (BOMs) are assigned to the production versions.

Buy Now
Questions 12

Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.

Options:

A.

Production orders

B.

Planned orders (firmed)

C.

Planned orders (unfirmed)

D.

ATP quantities

Buy Now
Questions 13

How can you set up a material as a phantom assembly? Note: There are 2 correct answers to this question.

Options:

A.

Select a special procurement type inside the material master.

B.

Use a special item category in your material BOM (bill of material).

C.

Select a special MRP type inside the material master.

D.

Define the special procurement type inside the material BOM (bill of material).

Buy Now
Questions 14

Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.

Options:

A.

Procurement type

B.

Material type

C.

MRP type

D.

MRP group

Buy Now
Questions 15

What is a work center hierarchy?

Options:

A.

A group of alternative work centers for production structured in hierarchy levels by priorities

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel

Buy Now
Questions 16

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

Options:

A.

Backflushing

B.

Kanban

C.

Material requirements planning

D.

Production order release

Buy Now
Questions 17

Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

Options:

A.

Wait time

B.

Float before production

C.

Processing time

D.

Pick time

E.

Setup time

Buy Now
Questions 18

Where does the system check master data selection settings during the creation of planned orders or production orders? Note: There are 3 correct answers to this question.

Options:

A.

In the production version

B.

In the work centers

C.

In the bill of material (BOM)

D.

In the MRP controller

E.

In the routing

Buy Now
Questions 19

Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?

Options:

A.

Assembly processing with production orders (82)

B.

Planning with final assembly (40)

C.

Planning without final assembly (50)

D.

Make-to-stock production (10)

Buy Now
Questions 20

What are the key features of using a low-level code? Note: There are 2 correct answers to this question.

Options:

A.

To determine the priority of alternative components inside ATP

B.

To determine how costs are rolled up by product costing

C.

To determine the sequence in which materials are planned in MRP

D.

To determine the use of sub-items inside material BOM (bill of material)

Buy Now
Questions 21

Which standard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

Variable-size item

B.

Work item

C.

Preliminary item

D.

WBS item

Buy Now
Questions 22

Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Assign planned orders manually in the planning table.

B.

Run MRP with quota arrangement.

C.

Run MRP with automatic selection of production version.

D.

Run PP/DS heuristics for repetitive manufacturing.

Buy Now
Questions 23

Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Options:

A.

Use a resource group.

B.

Use a planning group.

C.

Use a propagation range.

D.

Use a planning area.

Buy Now
Questions 24

In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

Options:

A.

MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.

B.

MRP creates the capacity requirements without considering existing load on the work centers.

C.

MRP creates the capacity requirements at the earliest possible time.

D.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

Buy Now
Exam Code: C_TS422_2023
Exam Name: SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing
Last Update: Apr 19, 2025
Questions: 80

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now C_TS422_2023 testing engine

PDF (Q&A)

$36.75  $104.99
buy now C_TS422_2023 pdf