Summer Special Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 713PS592

C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Questions 4

How can a material availability check be triggered automatically for a production order?

Note: There are 2 correct answers to this question.

Options:

A.

By capacity planning

B.

By mass processing

C.

By order release

D.

By order confirmation

Buy Now
Questions 5

Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?

Note: There are 2 correct answers to this question

Options:

A.

Total replenishment lead time

B.

Operation duration

C.

Planned delivery time

D.

In-house production time

Buy Now
Questions 6

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

Options:

A.

Scheduling agreement schedule line

B.

Purchase Order

C.

Planned Order

D.

Production Order

Buy Now
Questions 7

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 Correct answers to this question.

Options:

A.

Increase the capacity supply in a time-phased interval.

B.

Determine a time period with available capacity on the planning board.

C.

Execute an infinite production planning run for the critical resources.

D.

Reduce the planning Window.

E.

Form optimum sequence to reduce setup times.

Buy Now
Questions 8

How can you support a GMP (Good Manufacturing Practice)-compliant production process?

Note: There are 3 correct answers to this question.

Options:

A.

Approved resources

B.

Digital signature

C.

Batch record

D.

GMP-compliant flag

E.

Recipe approval

Buy Now
Questions 9

What is the purpose of a reporting point confirmation in repetitive manufacturing?

Note: There are 2 Correct answers to this question?

Options:

A.

To determine the work in progress along the production line

B.

To provide timely updates of inventory management for the staged components

C.

To reduce the total production lead time for a long production line

D.

To stage different components for a production line simultaneously

Buy Now
Questions 10

What does a line hierarchy in repetitive manufacturing represent?

Options:

A.

A production line with more than one work center

B.

A production line with prioritized work centers

C.

A production line with a parallel sequence in the routing

D.

A production line with an alternative sequence in the routing

Buy Now
Questions 11

You need to model goods receipt processing time in detailed scheduling. Which modeling options do you have?

Note: There are 3 correct answers to this question.

Options:

A.

Model a separate resource in the production data structure.

B.

Model a handling resource in the location master.

C.

Model a transportation lane and carrier selection in the location master.

D.

Model a separate inbound resource in the location master.

E.

Model a goods receipt time in the material master.

Buy Now
Questions 12

Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.

what is the impact of this decision?

Note: there are 2 correct answers to this question

Options:

A.

Storage Location MRP areas are required for sales-orders-specific stock.

B.

Net requirement calculation is carried out for every sales order individually.

C.

Both the reduction of make-to-order stock and requirements occur on delivery

D.

Sales orders have to be ATP-confirmed (available-to-promise) to saved.

E.

Production orders are created with sales order reference.

Buy Now
Questions 13

Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.

Options:

A.

The same batch management level is used

B.

The same base unit of measure is used.

C.

The quantity and value updates are the same

D.

The same account category is used

Buy Now
Questions 14

Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

Options:

A.

Create an object selection variant for priority-category-related alerts.

B.

Assign the alert profile to the overall profile.

C.

Create an object selection variant for production-planning-related alerts.

D.

Assign the overall profile to the authorization profile.

Buy Now
Questions 15

Which standard item categories can you select inside a bill of material (BOM)?

Note: There are 2 correct answers to this question

Options:

A.

Work item

B.

Variable-size item

C.

Non-stock item

D.

WBS item

Buy Now
Questions 16

If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?

Options:

A.

Fill up to the maximum stock level.

B.

Fill up to the safety stock level.

C.

Fill up based on the lot size procedure.

D.

Fill up to the reorder stock level.

Buy Now
Questions 17

You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

Options:

A.

Planning with final assembly (40)

B.

Production by lot size (30)

C.

Planning at assembly level (70)

D.

Make-to-order production (20)

Buy Now
Questions 18

Which materials have a negative quantity in a bill of material or in a recipe?

Note: There are 3 correct answers to this question

Options:

A.

Continuous flow materials

B.

Bulk materials

C.

By-products

D.

Co-products

E.

Waste products

Buy Now
Questions 19

Which of the following questions do you have to answer before you start creating a bill of material (BOM)?

Options:

A.

Is the material type allowed in the BOM?

B.

Which base unit of measure does the material have?

C.

What status does the BOM have?

D.

In which storage location is the BOM required?

Buy Now
Questions 20

which SAP application can be used for forecasting in Supply Chain Planning?

Note: there are 2 correct answers to this question.

Options:

A.

Integration Business Planning (IBP)

B.

Capacity Requirement Planning (CRP)

C.

Supply Chain Management (SCM)

D.

Material Requirement Planning (MRP)

Buy Now
Questions 21

You are trying to create a production order and NO valid production version can be selected. What could be the reasons?

Note: There are 2 correct answers to this question.

Options:

A.

NO bills of material (BOMs) are assigned to the production versions.

B.

All production versions for the material are locked.

C.

The order lot size is NOT within the validity range of a production version.

D.

NO production lines are assigned to the production versions..

Buy Now
Questions 22

You want to schedule an operation finitely, without removing other operations. Which scheduling strategy do you select?

Options:

A.

Insert operation

B.

Squeeze in

C.

Schedule in working time only

D.

Find Slot

Buy Now
Questions 23

Generic Parent » Generic 1 pt

What is the purpose of collective orders?

Options:

A.

To manage production orders for an entire finished product on multiple levels

B.

To combine order management of co-products and by-products with the main product

C.

To post production costs on a cost collector instead of the production order

D.

To post any component withdrawal as single backflush with order confirmation

Buy Now
Questions 24

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

Options:

A.

Kanban

B.

Material requirements planning

C.

Backflushing

D.

Production order release

Buy Now
Exam Code: C_TS422_2023
Exam Name: SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing
Last Update: Sep 15, 2024
Questions: 80

PDF + Testing Engine

$66.4  $165.99

Testing Engine

$46  $114.99
buy now C_TS422_2023 testing engine

PDF (Q&A)

$42  $104.99
buy now C_TS422_2023 pdf