Winter Special Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 713PS592

CAPM Certified Associate in Project Management (CAPM) Questions and Answers

Questions 4

What estimating technique is used when there is limited information?

Options:

A.

Analogous estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Three-point estimating

Buy Now
Questions 5

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?

Options:

A.

Project Cost Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Schedule Management

Buy Now
Questions 6

Which of the following is example of communication tools and techniques?

Options:

A.

Conflict management

B.

Stakeholder mapping

C.

Advertising plan

D.

Developing team

Buy Now
Questions 7

Which of the following is used as an input to prepare a cost management plan?

Options:

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Buy Now
Questions 8

Which items are components of a project management plan?

Options:

A.

Change management plan, process improvement plan, and scope management plan

B.

Agreements, procurement management plan, and work performance information

C.

Schedule management plan, project schedule, and resource calendars

D.

Scope baseline, project statement of work, and requirements traceability matrix

Buy Now
Questions 9

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

Options:

A.

Schedule network analysis

B.

Reserve analysis

C.

Alternative analysis

D.

Variance analysis

Buy Now
Questions 10

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

Options:

A.

-8000

B.

-2000

C.

2000

D.

8000

Buy Now
Questions 11

A weighting system is a tool for which area of Conduct Procurements?

Options:

A.

Plan contracting

B.

Requesting seller responses

C.

Selecting seller's

D.

Planning purchase and acquisition

Buy Now
Questions 12

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Buy Now
Questions 13

An output of the Manage Stakeholder Engagement process is:

Options:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Buy Now
Questions 14

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

Options:

A.

Customers.

B.

Business partners.

C.

Sellers.

D.

Functional managers.

Buy Now
Questions 15

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

Options:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

Buy Now
Questions 16

Which grid shows which resources are tied to work packages?

Options:

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Project assignment chart

D.

Personnel assignment matrix

Buy Now
Questions 17

The Perform Quality Assurance process occurs in which Process Group?

Options:

A.

Executing

B.

Monitoring and Controlling

C.

Initiating

D.

Planning

Buy Now
Questions 18

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

Options:

A.

Force/direct

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Collaborate/problem solve

Buy Now
Questions 19

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

Options:

A.

mitigate

B.

accept

C.

transfer

D.

avoid

Buy Now
Questions 20

An input to Conduct Procurements is:

Options:

A.

Independent estimates.

B.

Selected sellers.

C.

Seller proposals.

D.

Resource calendars.

Buy Now
Questions 21

Which process in Project Time Management includes reserve analysis as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Buy Now
Questions 22

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

Options:

A.

Inspection

B.

Quality audits

C.

Design of experiments

D.

Root cause analysis

Buy Now
Questions 23

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03

B.

0.06

C.

0.10

D.

0.50

Buy Now
Questions 24

Which type of graphic is displayed below?

CAPM Question 24

Options:

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

Buy Now
Questions 25

The purpose of the Project Communications Management Knowledge Area is to:

Options:

A.

Monitor and control communications throughout the entire project life cycle.

B.

Maintain an optimal flow of information among all project participants.

C.

Develop an appropriate approach for project communications.

D.

Ensure timely and appropriate collection of project information.

Buy Now
Questions 26

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

Options:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Buy Now
Questions 27

The following is a network diagram for a project.

CAPM Question 27

How many possible paths are identified for this project?

Options:

A.

3

B.

4

C.

6

D.

7

Buy Now
Questions 28

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

Options:

A.

lead

B.

lag

C.

mandatory dependency

D.

internal dependency

Buy Now
Questions 29

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Buy Now
Questions 30

At the start of a typical project life cycle, costs are:

Options:

A.

low, peak as work is carried out, and drop as the project nears the end.

B.

low, become steady as work is carried out, and increase as the project nears the end.

C.

high, drop as work is carried out, and increase as the project nears the end.

D.

high, become low as work is carried out, and drop as the project nears the end.

Buy Now
Questions 31

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

Options:

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

Buy Now
Questions 32

The following is a network diagram for a project.

CAPM Question 32

The total float for the project is how many days?

Options:

A.

5

B.

9

C.

12

D.

14

Buy Now
Questions 33

Progressively elaborating high-level information into detailed plans is performed by the:

Options:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

Buy Now
Questions 34

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

Options:

A.

Influencing

B.

Motivation

C.

Negotiation

D.

Trust building

Buy Now
Questions 35

When the business objectives of an organization change, project goals need to be:

Options:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Buy Now
Questions 36

The following is a network diagram for a project.

CAPM Question 36

The shortest non-critical path for the project is how many days in duration?

Options:

A.

10

B.

12

C.

14

D.

16

Buy Now
Questions 37

Which element does a project charter contain?

Options:

A.

Management reserves

B.

Work breakdown structure

C.

Stakeholder list

D.

Stakeholder register

Buy Now
Questions 38

Project management processes ensure the:

Options:

A.

alignment with organizational strategy

B.

efficient means to achieve the project objectives

C.

performance of the project team

D.

effective flow of the project throughout its life cycle

Buy Now
Questions 39

The primary benefit of the Plan Schedule Management process is that it:

Options:

A.

provides guidance to identify time or schedule challenges within the project.

B.

tightly links processes to create a seamless project schedule.

C.

guides how the project schedule will be managed throughout the project.

D.

creates an overview of all activities broken down into manageable subsections.

Buy Now
Questions 40

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Buy Now
Questions 41

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

Options:

A.

Close Procurements.

B.

Control Procurements.

C.

Plan Procurements.

D.

Conduct Procurements.

Buy Now
Questions 42

Which stakeholder approves a project's result?

Options:

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Buy Now
Questions 43

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Options:

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

Buy Now
Questions 44

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

Options:

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Buy Now
Questions 45

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

Options:

A.

Collect Requirements

B.

Plan Scope Management

C.

Define Scope

D.

Define Activities

Buy Now
Questions 46

Which enterprise environmental factors may influence Plan Schedule Management?

Options:

A.

Cultural views regarding time schedules and professional and ethical behaviors

B.

Historical information and change control procedures

C.

Risk control procedures and the probability and impact matrix

D.

Resource availability and organizational culture and structure

Buy Now
Questions 47

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Options:

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

Buy Now
Questions 48

Which is an enterprise environmental factor?

Options:

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

Buy Now
Questions 49

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

Options:

A.

management

B.

response

C.

tolerance

D.

appetite

Buy Now
Questions 50

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

Options:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Buy Now
Questions 51

A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

Options:

A.

cultural differences of team members

B.

possibility of communication misunderstandings

C.

costs associated with travel

D.

costs associated with technology

Buy Now
Questions 52

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

Options:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Buy Now
Questions 53

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

Options:

A.

organizational skills

B.

technical skills

C.

communication skills

D.

hard skills

Buy Now
Questions 54

Perform Integrated Change Control is the process of:

Options:

A.

Reviewing, approving, and managing all change requests

B.

Facilitating change management, manuals, or automation tools

C.

Comparing actual results with planned results in order to expand or change a project

D.

Documenting changes according to the change control system by the change control board

Buy Now
Questions 55

A tool and technique used in the Develop Project Charter process is:

Options:

A.

change control tools

B.

expert judgment

C.

meetings

D.

analytical techniques

Buy Now
Questions 56

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

Options:

A.

Uniform

B.

Continuous

C.

Discrete

D.

Linear

Buy Now
Questions 57

For a stakeholder with low interest and high power, the project manager should:

Options:

A.

Monitor the stakeholder.

B.

Manage the stakeholder closely.

C.

Keep the stakeholder satisfied.

D.

Keep the stakeholder informed.

Buy Now
Questions 58

The purpose of inspection in Perform Quality Control is to keep errors:

Options:

A.

in line with a measured degree of conformity.

B.

out of the hands of the customer.

C.

in a specified range of acceptable results.

D.

out of the process.

Buy Now
Questions 59

Which of the following Project Communication Management processes uses performance reports as an input?

Options:

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Buy Now
Questions 60

What is the primary benefit of meeting quality requirements?

Options:

A.

Quality metrics

B.

Less rework

C.

Quality control measurements

D.

Benchmarking

Buy Now
Questions 61

Which is the correct formula for calculating expected activity cost for three-point estimating?

Options:

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Buy Now
Questions 62

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Buy Now
Questions 63

The key benefit of the Monitoring and Controlling Process Group is the ability to:

Options:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

Buy Now
Questions 64

Quality metrics are an output of which process?

Options:

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 65

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

Options:

A.

Project Time Management

B.

Project Cost Management

C.

Project Scope Management

D.

Project Human Resource Management

Buy Now
Questions 66

"Tailoring" is defined as the:

Options:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.

B.

act of creating a project team with the specialized skills required to produce a required product or service.

C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

Buy Now
Questions 67

The project scope statement and resource calendars are inputs to which Project Time Management process?

Options:

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Buy Now
Questions 68

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

Options:

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Buy Now
Questions 69

Which of the following characteristics are found in a functional organizational structure?

Options:

A.

Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

B.

Limited project manager authority, limited resource availability, and a part-time project manager's role

C.

Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role

D.

High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Buy Now
Questions 70

How many Project Management Process Groups are there?

Options:

A.

3

B.

4

C.

5

D.

6

Buy Now
Questions 71

Which is a communication method used in the Report Performance process?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Stakeholder analysis

D.

Status review meetings

Buy Now
Questions 72

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

Buy Now
Questions 73

In which process might a project manager use risk reassessment as a tool and technique?

Options:

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Buy Now
Questions 74

Which of the following is an output of Direct and Manage Project Execution?

Options:

A.

Project management plan

B.

Change request status updates

C.

Organizational process assets updates

D.

Work performance information

Buy Now
Questions 75

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

Options:

A.

Determine Budget.

B.

Baseline Budget.

C.

Control Costs.

D.

Estimate Costs.

Buy Now
Questions 76

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

Options:

A.

enterprise environmental factors.

B.

organizational process assets.

C.

project management plan,

D.

project funding requirements.

Buy Now
Questions 77

Which of the following correctly explains the term "progressive elaboration'?

Options:

A.

Changing project specifications continuously

B.

Elaborate tracking of the project progress

C.

Elaborate tracking of the project specifications with a change control system

D.

Project specifications becoming more explicit and detailed as the project progresses

Buy Now
Questions 78

In Project Cost Management, which input is exclusive to the Determine Budget process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Buy Now
Questions 79

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

Options:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Buy Now
Questions 80

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Buy Now
Questions 81

Which process involves identifying and documenting the logical relationships between project activities?

Options:

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

Buy Now
Questions 82

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Buy Now
Questions 83

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Requested changes

B.

Approved change requests

C.

Work performance information

D.

Implemented defect repair

Buy Now
Questions 84

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

Options:

A.

Resource breakdown structure

B.

Staffing management plan

C.

Project organizational chart

D.

Scope management plan

Buy Now
Questions 85

What is the name of a graphic display of project team members and their reporting relationships?

Options:

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

Buy Now
Questions 86

What is the total float of the critical path?

Options:

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Buy Now
Questions 87

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Buy Now
Questions 88

The product scope description is used to:

Options:

A.

Gain stakeholders' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Buy Now
Questions 89

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

Options:

A.

Push communication

B.

Pull communication

C.

Interactive communication

D.

Stakeholder communication

Buy Now
Questions 90

Which statement is related to the project manager's sphere of influence at the organizational level?

Options:

A.

A project manager interacts with other project managers to detect common interests and impacts between their projects.

B.

A project manager facilitates communication between the suppliers and contractors on the project.

C.

A project manager considers the current industry trends and evaluates how they can impact or be applied to the project.

D.

A project manager may inform other professionals about the value of project management.

Buy Now
Questions 91

How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?

Options:

A.

Look at the quality metrics.

B.

Validate the scope.

C.

Review the quality checklist.

D.

Conduct a quality audit.

Buy Now
Questions 92

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

Options:

A.

Monitor project stakeholder relationships using engaging strategies and plans

B.

Send all project documents to stakeholders each time they are modified

C.

Schedule monthly meetings with the stakeholders, including team members

D.

Engage only with the project sponsors

Buy Now
Questions 93

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

Options:

A.

Internal enterprise environmental factor

B.

Risk register database

C.

External enterprise environmental factor

D.

Organizational process asset

Buy Now
Questions 94

Which of the following are outputs from the process of creating a work breakdown structure (WBS)?

Options:

A.

Project scope statement and accepted deliverables

B.

Scope baseline and project documents update

C.

Accepted deliverables and enterprise environmental factors

D.

Scope baseline and work performance information

Buy Now
Questions 95

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

Options:

A.

What-if scenario analysis

B.

Simulation

C.

Alternatives analysis

D.

Reserve analysis

Buy Now
Questions 96

A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?

Options:

A.

Informal

B.

Unofficial

C.

Formal

D.

Hierarchical

Buy Now
Questions 97

Which of the following strategic considerations often results in project authorization?

Options:

A.

Customer requests and/or issue resolution

B.

Stakeholder expectations and/or strategic opportunity (business need)

C.

Technological advancement and/or senior executive request

D.

Market demand and/or legal requirements

Buy Now
Questions 98

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

Options:

A.

training, testing, and warranty work.

B.

equipment, rework, and scrap.

C.

training, document processes, and inspections.

D.

inspections, rework, and warranty work.

Buy Now
Questions 99

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Buy Now
Questions 100

As the project progresses, which of the following is routinely collected from the project activities?

Options:

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Buy Now
Questions 101

Which characteristic do projects and operational work share in common?

Options:

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

Buy Now
Questions 102

Which tool or technique is used in Close Procurements?

Options:

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Buy Now
Questions 103

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

Options:

A.

Plan Risk Responses

B.

Manage Stakeholder Expectations

C.

Define Scope

D.

Report Performance

Buy Now
Questions 104

Labor, materials, equipment, and supplies are examples of:

Options:

A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

Buy Now
Questions 105

Which of the following factors is lowest at the start of the project?

Options:

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Buy Now
Questions 106

Which Process Group contains those processes performed to define a new project?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Buy Now
Questions 107

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

Options:

A.

Portfolio

B.

Process

C.

Project

D.

Program

Buy Now
Questions 108

Testing falls into which of the following categories of cost of quality?

Options:

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

Buy Now
Questions 109

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Buy Now
Questions 110

When sequencing activities, what does the common acronym FF stand for?

Options:

A.

Fixed Fee

B.

Free Float

C.

Fixed Finish

D.

Finish-to-Finish

Buy Now
Questions 111

Which process should be conducted from the project inception through completion?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Buy Now
Questions 112

Which of the following are outputs of Develop Project Team?

Options:

A.

Human resources plan changes and project staff assignment updates

B.

Project management plan updates and enterprise environmental factor updates

C.

Resource calendars and project management plan updates

D.

Team performance assessments and enterprise environmental factor updates

Buy Now
Questions 113

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

Options:

A.

Authority

B.

Role

C.

Competency

D.

Responsibility

Buy Now
Questions 114

Which of the following project documents is an input to the Control Scope process?

Options:

A.

Vendor risk assessment diagram

B.

Risk register

C.

Requirements traceability matrix

D.

Area of responsibility summary

Buy Now
Questions 115

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Buy Now
Questions 116

An example of a group decision-making technique is:

Options:

A.

nominal group technique

B.

majority

C.

affinity diagram

D.

multi-criteria decision analysis

Buy Now
Questions 117

Success is measured by benefits realization for a:

Options:

A.

strategic plan

B.

project

C.

portfolio

D.

program

Buy Now
Questions 118

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Options:

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Buy Now
Questions 119

The component of the risk management plan that documents how risk activities will be recorded is called:

Options:

A.

tracking

B.

scoping

C.

timing

D.

defining

Buy Now
Questions 120

Completion of the product scope is measured against the product:

Options:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

Buy Now
Questions 121

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

Options:

A.

scope creep.

B.

a change request.

C.

work performance information.

D.

deliverables.

Buy Now
Questions 122

Which of the following is a tool and technique used in the Develop Schedule process?

Options:

A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Buy Now
Questions 123

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Buy Now
Questions 124

Which of the following is an example of schedule compression?

Options:

A.

Activity sequencing

B.

Resource leveling

C.

Lead and lag adjusting

D.

Crashing

Buy Now
Questions 125

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

Options:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

Buy Now
Questions 126

Which tool should a project manager consider to deal with multiple sources of risk?

Options:

A.

An updated risk register

B.

Risk breakdown structure

C.

Issue log

D.

Stakeholder register

Buy Now
Questions 127

A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?

Options:

A.

Identify Stakeholders

B.

Plan Stakeholder Engagement

C.

Manage Stakeholder Engagement

D.

Monitor Slakeholder Engagement

Buy Now
Questions 128

What scenario describes when a project must be created due to market demand?

Options:

A.

A public company authorizes a project to create a new service for electric car sharing to reduce pollution.

B.

A car company authorizes a project to build more fuel-efficient cars in response to gasoline shortages.

C.

Researchers develop an autonomous car. with several new features to be commercialized in the future.

D.

Stakeholders request that raw matenais be changed due to locally high costs.

Buy Now
Questions 129

With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?

Options:

A.

Suppliers

B.

Customers

C.

Governing bodies

D.

Project team

Buy Now
Questions 130

What is the best tool to calculate the critical path on a project?

Options:

A.

Critical chain method

B.

Graphical evaluation and review technique (GERT) diagram

C.

Gantt chart

D.

Project network diagram

Buy Now
Questions 131

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

Options:

A.

Least cost

B.

Qualifications only

C.

Sole source

D.

Fixed budget

Buy Now
Questions 132

What purpose does the hierarchical locus of stakeholder communications serve?

Options:

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media, and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Buy Now
Questions 133

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

Options:

A.

Project charter, business documents, and project management plan

B.

Agreements, scope baseline, and project management plan

C.

Project charter, business case, and project management plan

D.

Work performance data, enterprise environmental factors, and project management plan

Buy Now
Questions 134

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

Options:

A.

Develop Schedule

B.

Control Schedule

C.

Estimate Activity Durations

D.

Define Activities

Buy Now
Questions 135

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

Options:

A.

Initiating Process Group

B.

Planning Process Group

C.

Executing Process Group

D.

Monitoring and Controlling Process Group

Buy Now
Questions 136

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

Options:

A.

0.88

B.

1.12

C.

0.58

D.

1.58

Buy Now
Questions 137

What are the key tools for managing project knowledge?

Options:

A.

Expert judgment and data gathering

B.

Networking and storytelling

C.

Data analysis and decision making

D.

Prototypes and product analysis

Buy Now
Questions 138

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take into account for risk management in this environment?

Options:

A.

Occasionally identify, evaluate, and classify risks.

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Buy Now
Questions 139

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

Options:

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

Buy Now
Questions 140

Which of the following are components of the technical project management skill?

Options:

A.

Ability to explain business aspects of the project, business strategy, goals and objectives, and business value.

B.

Ability to deal with people, to be collaborative, and to apply persuasion and negotiation.

C.

Ability to focus on relationships with people, inspire trust, and implement decisions and actions that support the business strategy.

D.

Ability to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors.

Buy Now
Questions 141

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

Options:

A.

List of identified risks, potential risk owners, list of potential risk response

B.

List of identified risks, list of causes, list of risk categories

C.

Short risk titles, list of potential risk owners, list of impacts on objectives

D.

List of activities affected, list of potential risk responses, list of causes

Buy Now
Questions 142

In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

Options:

A.

Hold a face-to-face meeting with the project manager and warn them.

B.

Point the director to a link where they can take a look at the reports.

C.

Invite stakeholders to attend monthly progress review meetings.

D.

Ask the project manager to update the monthly status report distribution list.

Buy Now
Questions 143

Which conflict resolution technique produces the most lasting results?

Options:

A.

Withdraw/avoid

B.

Smooth/accommodate

C.

Compromise/reconcile

D.

Collaborate/problem solve

Buy Now
Questions 144

What is the project manager's responsibility in Project Integration Management?

Options:

A.

Ensuring that requirements-related work is clarified in the project management plan

B.

Investing sufficient effort in acquiring, managing, motivating, and empowering the project team

C.

Combining the results in all other knowledge areas, and overseeing the project as a whole

D.

Developing a strategy to ensure effective stakeholder communication

Buy Now
Questions 145

Which of the following are outputs of the Define Scope process in Project Scope Management?

Options:

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project scope statement and project documents updates

D.

Scope baseline and project documents updates

Buy Now
Questions 146

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

Options:

A.

improvement

B.

program

C.

result

D.

portfolio

Buy Now
Questions 147

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

Options:

A.

a Knowledge Area

B.

a Process Group

C.

program management

D.

portfolio management

Buy Now
Questions 148

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

Options:

A.

Information management systems

B.

Work performance reports

C.

Stakeholder analysis

D.

Data gathering and representation

Buy Now
Questions 149

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

Options:

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

Buy Now
Questions 150

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

Options:

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Buy Now
Questions 151

Which of the following is contained within the communications management plan?

Options:

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Buy Now
Questions 152

The process of formalizing acceptance of the completed project deliverables is known as:

Options:

A.

Validate Scope.

B.

Close Project or Phase.

C.

Control Quality.

D.

Verify Scope.

Buy Now
Questions 153

Which process is included in the Project Integration Management Knowledge Area?

Options:

A.

Manage Project Team

B.

Collect Requirements

C.

Sequence Activities

D.

Direct and Manage Project Work

Buy Now
Questions 154

Which tools or techniques will a project manager use for Develop Project Team?

Options:

A.

Negotiation

B.

Roles and responsibilities

C.

Recognition and rewards

D.

Prizing and promoting

Buy Now
Questions 155

Which document includes the project scope, major deliverables, assumptions, and constraints?

Options:

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Buy Now
Questions 156

Portfolio Management is management of:

Options:

A.

a project by dividing the project into more manageable sub-projects.

B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.

C.

all projects undertaken by a company.

D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Buy Now
Questions 157

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Options:

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Buy Now
Questions 158

Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

Options:

A.

Program

B.

Functional

C.

Project

D.

Portfolio

Buy Now
Questions 159

Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?

Options:

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Buy Now
Questions 160

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

Options:

A.

Organizational process assets

B.

A work breakdown structure

C.

The project management plan

D.

Enterprise environmental factors

Buy Now
Questions 161

What is the difference between the critical path and the critical chain?

Options:

A.

Scope changes

B.

Resource limitations

C.

Risk analysis

D.

Quality audits

Buy Now
Questions 162

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

Options:

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

Buy Now
Questions 163

Which of the following is TRUE about most project life cycles?

Options:

A.

Staffing level is highest at the start.

B.

The stakeholders' influence is highest at the start.

C.

The level of uncertainty is lowest at the start.

D.

The cost of changes is highest at the start.

Buy Now
Questions 164

During which process group is the quality policy determined?

Options:

A.

Initiating

B.

Executing

C.

Planning

D.

Controlling

Buy Now
Questions 165

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options:

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Buy Now
Questions 166

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Buy Now
Questions 167

What is one of the objectives of Project Risk Management?

Options:

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Buy Now
Questions 168

Which of the following statements correctly characterizes pull communication?

Options:

A.

It includes letters, memos, reports, emails, and faxes.

B.

It requires recipients to access communication content at their own discretion.

C.

It is the most efficient way to ensure a common understanding among all participants.

D.

It is primarily used when the volume of information to be transferred is minimal.

Buy Now
Questions 169

Which is one of the major outputs of Sequence Activities?

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS) update

C.

Project schedule network diagram

D.

Mandatory dependencies list

Buy Now
Questions 170

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

Options:

A.

start-to-start (SS)

B.

start-to-finish (SF)

C.

finish-to-start (FS)

D.

finish-to-finish (FF)

Buy Now
Questions 171

Plan Risk Management is the process of defining how to:

Options:

A.

Communicate identified risks to the project stakeholders.

B.

Conduct risk management activities for a project.

C.

Analyze the impact a specific risk may have on the project.

D.

Address unexpected risks that may occur during a project.

Buy Now
Questions 172

At which point of the project is the uncertainty the highest and the risk of failing the greatest?

Options:

A.

Final phase of the project

B.

Start of the project

C.

End of the project

D.

Midpoint of the project

Buy Now
Questions 173

Which of the following techniques is used during Control Scope?

Options:

A.

Cost-benefit analysis

B.

Variance analysis

C.

Reserve analysis

D.

Stakeholder analysis

Buy Now
Questions 174

Which of the following is a narrative description of products, services, or results to be delivered by a project?

Options:

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Buy Now
Questions 175

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Buy Now
Questions 176

Which type of managers do composite organizations involve?

Options:

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Buy Now
Questions 177

What is the number of stakeholders, if the project has 28 potential communication channels?

Options:

A.

7

B.

8

C.

14

D.

16

Buy Now
Questions 178

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

Options:

A.

Pareto

B.

Ishikawa

C.

Shewhart-Deming

D.

Delphi

Buy Now
Questions 179

Projects are undertaken by an organization to support the:

Options:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

Buy Now
Questions 180

Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

Options:

A.

Build vs. buy

B.

Expert judgment

C.

Alternatives identification

D.

Product analysis

Buy Now
Questions 181

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

Options:

A.

budget at completion (BAC)

B.

earned value management (EVM)

C.

to-complete performance index

D.

cost performance index

Buy Now
Questions 182

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

Options:

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

Buy Now
Questions 183

An output of the Develop Project Team process is:

Options:

A.

change requests

B.

team performance assessments

C.

project staff assignments

D.

project documents updates

Buy Now
Questions 184

Which of the following is a tool and technique for Estimate Activity Durations?

Options:

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

Buy Now
Questions 185

An input of the Plan Procurement Management process is:

Options:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Buy Now
Questions 186

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

Options:

A.

Push

B.

Pull

C.

Interactive

D.

Iterative

Buy Now
Questions 187

Perform Quality Control is accomplished by:

Options:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Buy Now
Questions 188

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Options:

A.

Customer request

B.

Market demand

C.

Technological advance

D.

Strategic opportunity

Buy Now
Questions 189

Which of the following involves making information available to project stakeholders in a timely manner?

Options:

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Buy Now
Questions 190

Which is a tool or technique used in Define Scope?

Options:

A.

Templates, forms, and standards

B.

Change requests

C.

Product analysis

D.

Project assumptions

Buy Now
Questions 191

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Buy Now
Questions 192

The initial development of a Project Scope Management plan uses which technique?

Options:

A.

Alternatives identification

B.

Scope decomposition

C.

Expert judgment

D.

Product analysis

Buy Now
Questions 193

Which statement is true about the project management body of knowledge?

Options:

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Buy Now
Questions 194

The process of identifying specific actions to be performed to produce project deliverables is:

Options:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Buy Now
Questions 195

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Buy Now
Questions 196

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Buy Now
Questions 197

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Buy Now
Questions 198

Which activity may occur at project or phase closure?

Options:

A.

Acceptance of deliverables

B.

Change requests

C.

Project management plan updates

D.

Benchmarking

Buy Now
Questions 199

Funding limit reconciliation is a tool and technique used in which process?

Options:

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Buy Now
Questions 200

During project selection, which factor is most important?

Options:

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Buy Now
Questions 201

Who is responsible for initiating a project?

Options:

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Buy Now
Questions 202

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Buy Now
Questions 203

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 204

After Define Activities and Sequence Activities, the next process is:

Options:

A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.

Buy Now
Questions 205

Which is one of the determining factors used to calculate CPI?

Options:

A.

EV

B.

SPI

C.

PV

D.

ETC

Buy Now
Questions 206

Which input will be used when tasked with developing the human resource plan?

Options:

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Buy Now
Questions 207

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

Options:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Buy Now
Questions 208

An input to the Estimate Activity Resources process is:

Options:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

Buy Now
Questions 209

The staffing management plan is part of the:

Options:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Buy Now
Questions 210

Which of the following is a project constraint?

Options:

A.

Twenty-five percent staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to volatile political environment.

D.

The product is needed in 250 days.

Buy Now
Questions 211

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (T&M).

Buy Now
Questions 212

Which type of dependency is contractually required or inherent in the nature of the work?

Options:

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Buy Now
Questions 213

Which of the following is a tool and technique used to monitor risk?

Options:

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Buy Now
Questions 214

The process for performing variance analysis may vary, depending on:

Options:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

Buy Now
Questions 215

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Buy Now
Questions 216

Prototype development may be used as a tool for which of the following risk response strategies?

Options:

A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Buy Now
Questions 217

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Options:

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Buy Now
Questions 218

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

Options:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Buy Now
Questions 219

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Buy Now
Questions 220

The diagram below is an example of a:

CAPM Question 220

Options:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Buy Now
Questions 221

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Buy Now
Questions 222

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

Options:

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Buy Now
Questions 223

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

Options:

A.

Control Scope

B.

Collect Requirements

C.

Create WBS

D.

Define Scope

Buy Now
Questions 224

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Options:

A.

Two

B.

Four

C.

Five

D.

Twelve

Buy Now
Questions 225

A tool and technique used during the Define Scope process is:

Options:

A.

facilitated workshops.

B.

observations.

C.

questionnaires and surveys.

D.

group creativity techniques.

Buy Now
Questions 226

Which of the following is an output of Define Scope?

Options:

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule

Buy Now
Questions 227

Resource calendars are included in the:

Options:

A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

Buy Now
Questions 228

An input to the Collect Requirements process is the:

Options:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Buy Now
Questions 229

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

Options:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Buy Now
Questions 230

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

Options:

A.

quality.

B.

value.

C.

technical performance.

D.

status.

Buy Now
Questions 231

Risk exists the moment that a project is:

Options:

A.

planned.

B.

conceived.

C.

chartered.

D.

executed.

Buy Now
Questions 232

Projects are separated into phases or subprojects; these phases include:

Options:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

Buy Now
Questions 233

Risk responses reflect an organization's perceived balance between:

Options:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Buy Now
Questions 234

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

Options:

A.

Acquisition

B.

Negotiation

C.

Virtual team

D.

Pre-assignment

Buy Now
Questions 235

Which technique is utilized in the Control Schedule process?

Options:

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Buy Now
Questions 236

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

Options:

A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

Buy Now
Questions 237

Which is an output of the Collect Requirements process?

Options:

A.

Requirements traceability matrix

B.

Project scope statement

C.

WBS dictionary

D.

Work performance measurements

Buy Now
Questions 238

What are the identified risks for doing excessive decomposition in a WBS?

Options:

A.

Insufficient project funding and disqualification of sellers

B.

Insufficient project funding and ineffective use of resources

C.

Disqualification of sellers and non-productive management efforts

D.

Non-productive management effort and inefficient use of resources

Buy Now
Questions 239

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Options:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Buy Now
Questions 240

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

Options:

A.

$800

B.

$1000

C.

$1250

D.

$1800

Buy Now
Questions 241

The project manager released a report A few stakeholders express the view that report should

have been directed to them

Which of the 5Cs of written communications does the project manager need to address?

Options:

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Buy Now
Questions 242

A project manager should consider the impact of project..............manager following

A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?

Options:

A.

Project Cost Management

B.

Project Integration Management

C.

Project Resources Management

D.

Project Scope Management

Buy Now
Questions 243

The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?

Options:

A.

Organizational structure type, Key stakeholders, and protect funds

B.

Rules. policies and norms

C.

Project management software, resources availability and risk checklist

D.

Governance elements, team policies, and organizational goals

Buy Now
Questions 244

At what stages of project should the identify Stakeholder process be performed?

Options:

A.

When beginning each phase of the project

B.

At the beginning of the project only

C.

Only when the project manager is concerned about stakeholder satisfaction

D.

When the project charter is produced, at the beginning of each phase, and when significant changes occur

Buy Now
Questions 245

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take to account for risk management n this environment’

Options:

A.

Occasionally identify evaluate, and classify risks

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Buy Now
Questions 246

What is a tailoring consideration for Project Scope Management'?

Options:

A.

Life cycle approach

B.

Continuous improvement

C.

Validation and control

D.

Project complexity

Buy Now
Questions 247

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

Options:

A.

Engage customer earlier

B.

Conduct quality audits

C.

Validate Scope

D.

Validate quality requirements

Buy Now
Questions 248

A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release.

What should the project manager do next to engage the new stakeholder?

Options:

A.

Add the stakeholder to the communications management plan.

B.

Conduct a one-on-one interview with the stakeholder.

C.

Invite the stakeholder to the sprint-planning meeting.

D.

Send the stakeholder a questionnaire.

Buy Now
Questions 249

When planning communications management what input identifies key stakeholders?

Options:

A.

Work performance information

B.

Project schedule

C.

Project charter

D.

Work performance reports

Buy Now
Questions 250

Match the process with its corresponding Process Group:

CAPM Question 250

Options:

Buy Now
Questions 251

A project manager is performing a specific process and has..........is being referred to?

A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?

Options:

A.

Control Quality

B.

Validate Scope

C.

Validate Quality

D.

Control Scope

Buy Now
Questions 252

In which of the risk management processes is the processes is the project charter used as an input?

Options:

A.

Palm Risk Responses

B.

Implement Risk Responses

C.

Plan Risk Management

D.

Perform Quantitative Risk Responses

Buy Now
Questions 253

Two members of the team are having a conflict..............or partially resolve the problem

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

Options:

A.

Withdraw/Avoid

B.

Smooth/Accommodate

C.

Compromise/Reconcile

D.

Collaborate/Problem Solve

Buy Now
Questions 254

Which project management process is used by the project manager to ensure that stakeholders receive timely and relevant information?

Options:

A.

Plan Communications Management

B.

Manage Communications

C.

Monitor Communications

D.

Develop Project Management Plan

Buy Now
Questions 255

A project team is closing out a phase and updating the organizational knowledge base What organizational process asset (OPA) will the team update?

Options:

A.

Traceability matrix

B Lessons learned

B.

Change control procedures

D Resource availability

Buy Now
Questions 256

How can you describe the role of the project.... of influence concept?

Options:

A.

The proiect manager proactivnly interacfS with other project managers creating a positive influence Km fulfilling project needs, working with other managers and sponsor to address internal political and strategic issues and ensunng that the project managemenl plan aligns with the portfolio or program plan

B.

The project manager leads the team, performs communication roles between stakeholders, and uses interpersonal sills to balance conflicting goals

C.

The proiect manager stays informed about current technology developments lakes into account new quality management standards, and uses relevant technical support tools

D.

The proiect manager participates in project management trainings, contributes to the organization professional community sharing knowledge, and maintains subied matter expertise

Buy Now
Questions 257

Which process determines the correctness of deliverables?

Options:

A.

Verify Deliverables

B.

Validate Deliverables

C.

Review Deliverables

D.

Analyze Deliverables

Buy Now
Questions 258

For what project management process is work performance information an output?

Options:

A.

Implement Risk Responses

B.

Plan Stakeholder Engagement

C.

Monitor Stakeholder Engagement

D.

Plan Quality Management

Buy Now
Questions 259

What is the purpose of the protect management process groups?

Options:

A.

To define a new project

B.

To track and monitor processes easily

C.

To logically group processes to achieve specific project objectives

D.

To link specific process inputs and outputs

Buy Now
Questions 260

What tools or techniques are necessary to create the project management plan?

Options:

A.

Meetings and data analysis

B.

Expert judgment and data gathering

C.

Interpersonal skills and change control

D.

Data analysis and expert judgment

Buy Now
Questions 261

A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?

Options:

A.

Detailed estimation

B.

Lightweight estimation

C.

Parametric estimation

D.

A mix of them

Buy Now
Questions 262

Which process uses expert judgment to manage project resources?

Options:

A.

Plan Resource Management

B.

Estimate Activity Resources

C.

Manage Team

D.

Both A and B

Buy Now
Questions 263

What is a characteristic of the relationship among projects, programs, and portfolios?

Options:

A.

A portfolio is a group of programs, and a program is a large project

B.

Portfolios often engage with the same stakeholders as the programs and projects in the portfolio.

C.

Programs focus on the internal interdependencies within each project in a portfolio

D.

Portfolios focus on program results and project deliveries

Buy Now
Questions 264

What kind of skills should a project manager use when attempting to achieve consensus by balancing the conflicting and competing goals of project stakeholders?

Options:

A.

Interpersonal skills and the ability to manage people

B.

Strategic and business management skills

C.

Technical and business management skills

D.

Business analysis skills and expertise

Buy Now
Questions 265

What characteristic of servant leadership supports resource management in an agile environment?

Options:

A.

Lecturing

B.

Construing

C.

Measuring

D.

Coaching

Buy Now
Questions 266

During what project management process does the project team begin identifying risks?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 267

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

Options:

A.

Add more risk categories

B.

Identify, analyze, and manage risk during each iteration of the project

C.

Add new values to the probability and impact matrix

D.

Increase the reserves because of the high variability environment

Buy Now
Questions 268

Which is a key skill set in PMI’s Talent Triangle?

Options:

A.

Project excellence and scope management

B.

Strategic and business management

C.

Scope management and business management

D.

Financial management and people management

Buy Now
Questions 269

Which project documents can determine the budget?

Options:

A.

Procurement documents, contracts, requirements documentation, and basis of estimates

B.

Basis of estimates, cost estimates, project schedule, and risk register

C.

Business case, project charter, statement of work, and cost estimates

D.

Scope baseline, resource management plan, activity list, and assumption log

Buy Now
Questions 270

A project manager is reviewing a past project with similar.... team choosing for tailoring?

A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?

Options:

A.

Policy compliance and auditing

B.

Standards and compliance

C.

Review of lessons learned

D.

Test and inspection planning

Buy Now
Questions 271

Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?

Options:

A.

Resource breakdown structure

B.

Physical resources assignment

C.

Team building activities

D.

Integrated Change Control

Buy Now
Questions 272

Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

Options:

A.

Plan Procurement

B.

Manage Procurement

C.

Conduct Procurements

D.

Perform Procurement

Buy Now
Questions 273

What does the creation of a project management plan accomplish?

Options:

A.

Defines the basis of all project work and how it will be performed

B.

Acknowledges the existence of a project and defines its high-level information

C.

Authorizes the project manager to apply organizational resources to project activities

D.

Provides the project manager with organizational standards, policies, processes, and procedures

Buy Now
Questions 274

Which process is engaged when a project team member makes a change to project budget with project manager's approval

Options:

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Buy Now
Questions 275

Match the praxes manager's sphere of influence with the associated primary role:

CAPM Question 275

Options:

Buy Now
Questions 276

Which of the following is least influenced by a project manager, according to the project manager's sphere of influence?

Options:

A.

Sponsors

B.

Project team

C.

Steering committees

D.

Stakeholders

Buy Now
Questions 277

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

Options:

A.

A self-organizing approach to increase team focus and maximize collaboration

B.

A virtual team to minimize feeling of isolation and gaps on sharing knowledge

C.

A distributed team to improve tracking progress, productivity, and performance

D.

A norming approach that requires team members to adjust their behavior and work together

Buy Now
Questions 278

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?

Options:

A.

Schedule Variance (SV) = 2

B.

Cost Performance Index (CPI) = 0.80

C.

Schedule Performance Index (SPI) = 1.93

D.

Cost Variance (CV) = 7

Buy Now
Questions 279

On which type of project.... only after the final iteration?

On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?

Options:

A.

Incremental life cycle

B.

Predictive life cycle

C.

Iterative life cycle

D.

Adaptive life cycle

Buy Now
Questions 280

Select three processes that are associated with Project Schedule Management.

Options:

A.

Define Activities

B.

Plan Resource Management

C.

Estimate Activity Durations

D.

Develop Schedule

E.

Acquire Resources

Buy Now
Questions 281

What document gathers all of the lessons learned at the end of a phase or project

Options:

A.

Lessons learned register

B.

Lessons learned list

C.

Lessons learned project asset

D.

Lessons learned repository

Buy Now
Questions 282

A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.

Options:

A.

Risks should be considered when selecting the content of each iteration.

B.

Risks should be tailored for each iteration.

C.

Risks should be identified, analyzed, and managed during each iteration.

D.

Risks should be documented prior to each iteration.

E.

Risks should be reviewed only once during each iteration.

Buy Now
Questions 283

Which of the following set of items belongs to the communications management plan?

Options:

A.

Escalation processes and meeting management

B.

Project schedule and glossary of common terminology

C.

Escalation processes and stakeholder communication requirements

D.

Interactive communication model and information to be communicated

Buy Now
Questions 284

Match each tool or technique with its corresponding Project Cost Management process.

CAPM Question 284

Options:

Buy Now
Questions 285

Project reporting is a tool that is most closely associated with which process?

Options:

A.

Communicate Plan

B.

Manage Communications

C.

Report Performance

D.

Control Communications

Buy Now
Questions 286

Which two processes should be used to influence costs in the early stages of a project?

Options:

A.

Estimate Costs and Determine Budget

B.

Plan Cost Management and Estimate Activity Durations

C.

Control Quality and Control Costs

D.

Plan Stakeholder Engagement and Plan Communications Management

Buy Now
Questions 287

A project manager is preparing to meet with three crucial project stakeholders on a new project Which tools and techniques can the project manager use to capture stakeholder interest?

Options:

A.

Review stakeholder register and meeting

B.

Data analysis and communication skills

C.

Data gathering and data analysis

D.

Communication skills and cultural awareness

Buy Now
Questions 288

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

Options:

A.

Approved change requests

B.

Verified deliverables

C.

Lessons learned

D.

Work performance data

Buy Now
Questions 289

During which process of Project Cost Management does a project manager produce the cost baseline?

Options:

A.

Estimate Costs

B.

Control Schedule

C.

Determine Budget

D.

Develop Project Charter

Buy Now
Questions 290

What process is included in Project Schedule Management?

Options:

A.

Estimate Activity Durations

B.

Create Work Breakdown Structure (WBS)

C.

Direct and Manage Project Work

D.

Estimate Activity Resources

Buy Now
Questions 291

A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?

Options:

A.

Earned value (EV) / actual cost (AC)

B.

Estimate at completion (EAC) - AC

C.

Budget at completion (BAC) / cost performance index (CPI)

D.

EV - planned value (PV)

Buy Now
Questions 292

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Options:

A.

Acquire Resources

B.

Control Resources

C.

Manage Team

D.

Develop Team

Buy Now
Questions 293

When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.

Options:

A.

Develop Schedule

B.

Define Activities

C.

Define Scope

D.

Collect Requirements

Buy Now
Questions 294

A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?

Options:

A.

Withdraw/avoid

B.

Smooth /accommodate

C.

Collaborate/problem solve

D.

Compromise/ reconcile

Buy Now
Questions 295

When should Project Risk Management be conducted?

Options:

A.

Project Planning

B.

Monitoring and Controlling

C.

Quality Planning

D.

Throughout the project lifecycle

Buy Now
Questions 296

Creating the project scope statement is part of which process?

Options:

A.

Manage Scope

B.

Collect Requirements

C.

Define Scope

D.

Validate Scope

Buy Now
Questions 297

The project manager is creating the communications management plan Which group of inputs Is required to begin?

Options:

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

Buy Now
Questions 298

The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?

Options:

A.

Take control of all decisions and product planning.

B.

Build a team that can respond to changes within a collaborative, decision-making environment.

C.

Promote a team with a narrow specialization within a hierarchical environment.

D.

Delegate project decisions to the product owner and sponsor.

Buy Now
Questions 299

Which is the tool or technique that is used to obtain the list of activities from the work packages?

Options:

A.

Data analysis

B.

Leads and lags

C.

Precedence diagramming method

D.

Decomposition

Buy Now
Questions 300

Which is a list of organizational systems that may have an impact on a project?

Options:

A.

Internal policies, company procedures, and organizational resources

B.

Company culture, purchasing system, and project management information system

C.

Organizational structure, governance framework, and management elements

D.

Organizational process assets, enterprise environmental factors, and corporate knowledge

Buy Now
Questions 301

What is the first step in the Stakeholder Management process?

Options:

A.

Plan Stakeholder Engagement

B.

Identify Stakeholders

C.

Manage Stakeholder Responsibility

D.

Monitor Stakeholder Activity

Buy Now
Questions 302

Which process is engaged when a proiect learn inember makes a change to project budget with the project manager's approval?

Options:

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Buy Now
Questions 303

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

Options:

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Close Project or Phase

D.

Perform Integrated Change Control

Buy Now
Questions 304

Which of these is true of project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Buy Now
Questions 305

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

Options:

A.

Work performance data

B.

Project documents

C.

Scope baseline

D.

Requirements documentation

Buy Now
Questions 306

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Buy Now
Questions 307

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

Options:

A.

Cost management plan.

B.

Work performance information.

C.

Quality management plan.

D.

Work breakdown structure.

Buy Now
Questions 308

Which item is an example of personnel assessment?

Options:

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Buy Now
Questions 309

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Buy Now
Questions 310

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Buy Now
Questions 311

Which Process Group and Knowledge Area include the Sequence Activities process?

Options:

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Buy Now
Questions 312

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Options:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Buy Now
Questions 313

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Buy Now
Questions 314

Which tool or technique is used to manage change requests and the resulting decisions?

Options:

A.

Change control tools

B.

Expert judgment

C.

Delphi technique

D.

Change log

Buy Now
Questions 315

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Buy Now
Questions 316

In a project, total float measures the:

Options:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Buy Now
Questions 317

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Buy Now
Questions 318

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

Options:

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Buy Now
Questions 319

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50

B.

$100

C.

$125

D.

$175

Buy Now
Questions 320

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

Options:

A.

Enhance

B.

Share

C.

Exploit

D.

Accept

Buy Now
Questions 321

Which cost is associated with nonconformance?

Options:

A.

Liabilities

B.

Inspections

C.

Training

D.

Equipment

Buy Now
Questions 322

An input to the Plan Cost Management process is:

Options:

A.

Cost estimates.

B.

Resource calendars,

C.

The project charter,

D.

The risk register.

Buy Now
Questions 323

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Options:

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Buy Now
Questions 324

Change requests are processed for review and disposition according to which process?

Options:

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Buy Now
Questions 325

Which tool or technique is used in the Develop Project Management Plan process?

Options:

A.

Pareto diagram

B.

Performance reporting

C.

SWOT analysis

D.

Expert judgment

Buy Now
Questions 326

The Plan Stakeholder Management process belongs to which Process Group?

Options:

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Buy Now
Questions 327

Which document defines how a project is executed, monitored and controlled, and closed?

Options:

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Buy Now
Questions 328

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

Options:

A.

Continuous improvement.

B.

Predictive planning.

C.

Progressive elaboration.

D.

Quality assurance.

Buy Now
Questions 329

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

Options:

A.

Direct and Manage Project Work

B.

Develop Project Management Plan

C.

Plan Quality Management

D.

Monitor and Control Project Work

Buy Now
Questions 330

In the Plan Stakeholder Management process, expert judgment is used to:

Options:

A.

Provide information needed to plan appropriate ways to engage project stakeholders.

B.

Ensure comprehensive identification and listing of new stakeholders.

C.

Analyze the information needed to develop the project scope statement.

D.

Decide the level of engagement of the stakeholders at each required stage.

Buy Now
Questions 331

A tool or technique used in the Control Procurements process is:

Options:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Buy Now
Questions 332

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

Options:

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Buy Now
Questions 333

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

Options:

A.

Identify Risks

B.

Control Risks

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 334

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

Options:

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Buy Now
Questions 335

The process of prioritizing risks for further analysis or action is known as:

Options:

A.

Plan Risk Management.

B.

Plan Risk Responses.

C.

Perform Qualitative Risk Analysis.

D.

Perform Quantitative Risk Analysis.

Buy Now
Questions 336

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Options:

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Buy Now
Questions 337

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Change requests.

C.

Accepted deliverables.

D.

Variance analysis.

Buy Now
Questions 338

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Options:

A.

Requirements documentation

B.

Requirements traceability matrix

C.

Project management plan updates

D.

Project documents updates

Buy Now
Questions 339

Which tool or technique is an examination of industry and specific vendor capabilities?

Options:

A.

Independent estimates

B.

Market research

C.

Analytical techniques

D.

Bidder conferences

Buy Now
Questions 340

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

Options:

A.

Procurement documents

B.

Communications plan

C.

Project charter

D.

Stakeholder register

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Nov 28, 2024
Questions: 1135

PDF + Testing Engine

$66  $164.99

Testing Engine

$50  $124.99
buy now CAPM testing engine

PDF (Q&A)

$42  $104.99
buy now CAPM pdf