You are the business analyst for your organization. Management has asked you to create a plan that will define the proposed structure and schedule for communicating the business analysis activities to the appropriate stakeholders. What plan does management want you to create?
Shelly is the business analyst for her organization and she's working with Thomas to review the business requirements. They are discussing the identified requirements, how the requirements will transition to the operations, and the longevity of the solution. Thomas is concerned that theidentified requirements may not map to the desired future state of the organization. What business analysis task is Shelly facilitating in this scenario?
Sam is preparing for the task of prioritizing requirements and he'll need five inputs to accomplish the task. Which one of the following is not an input that Sam will use to prioritize requirements?
There are five tasks and six inputs to requirements management and communication. As a business analyst, you'll need to gather all of the following inputs for this knowledge area except for which one?
Which element of the process of assessing the capability gaps is best described as gathering as much enterprise architecture information as is available about the current state of the organization and the areas affected by the business need?
You are the business analyst for a large software development project. There are several issues that must be resolved by certain dates or the problem will prevent the project from advancing. What technique can you use to track problems with the requirements?
What element of the plan business analysis process affects the business analysis duties that need to be performed?
You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record these communication requirements based on your stakeholder analysis?
All of the following are examples of elicitation techniques that are used as part of the business analyst elicitation task except for which one?
You are the business analyst for your organization and you're creating the requirements package. In this documentation, to what level should you document the requirements for your stakeholders?
Beth is the business analyst for her organization and she's creating a data dictionary for her organization. All of the following information should be included in the data dictionary for an endeavor Beth is leading except for which one?
When a business analyst performs requirements tracing, he may need to trace the requirements backward through their lineage and may need to trace the requirements forward through their relationship to other requirements. What is the backwards tracing activity called in requirements traceability?
You are a business analyst for your organization and you're working with the stakeholders to identify the primary inputs to the business analysis approach. Which of the following are primary inputs of planning the business analysis approach?
Each correct answer represents a complete solution.
You are currently working on creating the activity list for an initiative in your organization. What characteristic must be assigned to each task in your task list?
You are the business analyst for your organization. You are currently identifying opportunities for a customer to improve their business processes. The customer wants to streamline their business efforts either through new technologies, better processes, or a combination of both. The customer demands, however, that the solution should not cost more than $300,000 to implement and support for one year. What does the $300,000 represent?
Which approach to business analysis activities deals with rapid delivery of the business value?
A business analyst has determined that a project should be worth $2,750,000 in four years if her company decides to pursue the project. Assuming the rate of return on the investment is six percent, what is the minimum amount of funds the organization should invest in this project?
You are a business analyst for your organization and you're working with Mary. Mary wants to know what you need to complete the process of planning the business analysis approach if you're already the business analyst for your organization. This approach helps to find out the following except for which one?
You are a business analyst in an organization that has recently embraced business analysis as part of its initiative for new projects. In this organization, there is not an organizational standard for tailoring business analysis duties and expectations. Which one of the following best describes the action you should take to begin business analysis?
A business analyst (BA) has elicited non-functional information for a system's replacement. In reviewing the elicitation results, the BA finds the number of concurrent users is a large portion of the target user group, which seems high. How should the BA proceed?
When a business analyst completes the task of organizing requirements, he is completing two key objectives. What are the two objectives?
You are the business analyst for your organization and you've identified a business need. In order to satisfy this business need, you believe that your organization will need to hire three electrical engineers, purchase equipment, and likely provide training to existing resources. What process is being described in this scenario?
You are the business analyst for your organization. Management has asked you to define and document the requirements of an endeavor so that the requirements may be reused again in the organization. Why would an organization want to re-use requirements?
The creative thinking process has three values to determine the effectiveness of the process. Which one of the following is not a measurement of effective creative thinking?
You are the business analyst for your organization and you're working to identify all of the stakeholders within your organization and outside
your organization to ensure that you've captured the correct requirements for a project. Which one of the following techniques can be best suited for identifying stakeholders?
A business analyst (BA) has determined that “Product Box”, a collaboration game, will provide a fun way to engage the stakeholders when working on prioritizing the list of features. What should the BA do?
You are the business analyst for your organization and you're working with Adam on business analysis processes. Adam allows the business analysis activities and resources to exist in support of the organization. Of the following, what type of business analysis stakeholder is Adam?
Audrey is the business analyst for her organization and she's doing an assessment of the organization's readiness to implement the solution. In her assessment, she's finding that there are conflicting stakeholder groups for and against the proposed solution. Some of the stakeholders have more power over the solution than others. What diagram can Audrey create to visualize the people that are for and against the solution?
A business analyst must consider the business value a solution brings in relation to the cost of implementing the desired solution. Suppliers will often be limited in the amount of requirements they can implement based on the allocated resources. If there are not enough resources to implement all of the solutions, what can the business analyst create to justify the additional funds for the implementation?
Beth is a business analyst for her organization and she's completing the tasks in the requirements management and communication knowledge area. As a result of these tasks, she'll create several things for her organization. Which one of the following, however, is not one of the outputs of the requirements management and communication tasks?
Jason is creating a business case for his organization and management has asked him to assess the appropriate risks in the business case regarding the solution. Which one of the following risks is not a concern for Jason when defining the business case and associated risks?
Complete this sentence in regard to the level of abstraction. Requirements need to sayneeds to be done, notto do it.
The business need is considered to be the most critical step in the business analysis effort. Why is the definition of the business need considered the most critical step?
By which of the following is the performance of all requirements management and communication activities governed?
Which one of the following terms is not a business analysis planning and monitoring approach?
You are the business analyst for your organization and you've been working with several stakeholders to
gather requirements for approval.
The requirements have been approved with the exception of a conflict on one requirement. What must you and the stakeholders do in regard to this conflict before the business analysis endeavor may continue?
You are the business analyst for your organization and you are working with Bill on creating a model. Bill is a little confused about all the different things a model can do for the stakeholders. You explain to Bill that a model can do all of the following except for which one?
You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system. You would like to plan the communications that need to be made during the project lifecycle. Which of the following would be a critical tool/technique to help in your communications planning?
Which stakeholder in the solution assessment task will provide information on technical constraints that could limit the solutions that may be implemented?
You are the business analyst for your organization and you're using a plan-driven approach to business analysis processes. In this environment, what types of communications are most likely required to be used in regard to requirements?
Complete this sentence. If a requirement cannot be verified, it cannot be successfully.
All of the following are inputs to the task assess organizational readiness except for which one?
High quality requirements have certain characteristics which distinguish them from low-quality requirements. Which characteristic of requirements demands that all requirements in a set or model support its overall purpose and scope?
You are the business analyst in your organization and you're working to organize the requirements for the business units in your company. Which technique is best suited for structuring requirements around the needs of each stakeholder group?
The project plan called for deliverables to be handed over at the end of the project. Although the client's business team was satisfied, the client's technical team was extremely resistant to this approach. What could the business analyst (BA) do to mitigate the technical team’s resistance?
You are the business analyst for your organization and you're working with several stakeholders to identify, manage, and approve requirements. Your organization requires using a plan-driven approach to business analysis and changing management. In this approach, who is most likely to approve changes to requirements?
You are the business analyst for your organization and are working on organizing the identified requirements for a new solution. Nancy, your assistant in this process, says that these requirements aren't very complex. You agree but add that it's this thing that makes the overall solution complex. What thing adds to the level of complexity among requirements?
There are three inputs needed to determine the solution approach process. What are these inputs?
When a business analyst assists in the planning of the solution implementation, she must always consider the constraints for implementation. Which one of the following cannot be considered as an implementation constraint?
All of the following statements are true regarding a brainstorming session during requirements elicitation except for which one?
Which approach is best to take when a business analyst is assessing the solution options for a business need when there are relatively few criteria involved?
Henry is meeting with Janet, the business analyst of the organization. They are discussing an opportunity to create a new service their company can provide, though the startup of the service would take time and an investment. Henry wants Janet to explore the possibility of this new venture. What activity is Henry asking Janet to complete?
Which of the following is used to define and document the business analysis approach?
A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?
Which of the following are not appropriate for a plan-driven business analysis approach? Each correct answer represents a complete solution.
You are the business analyst for your organization and your manager has asked you to prepare an analysis of each proposed solution. Your manager wants you to determine whether and how eachoption can provide an expected business benefit to meet the stated business need. What is your manager asking you to create?
Which of the following documents graphically depicts the project team members and displays their interrelationship for a specific project?
A business analyst in her organization has identified all of the terminology of the solution, the acronyms the organization will use, and the nomenclature of her department where the endeavor will take place. Where should all of this information actually be stored?
Henry is a business analyst in his organization and he's asked an expert to help him determine the best business analysis duties to implement. Why would Henry ask an expert to help him define the business analysis duties?
You are the business analyst for your organization and you're working with your stakeholders to assess the organization's readiness for the solution. As part of this assessment, you'll perform a cultural assessment. What is the purpose of this assessment?
Bob and Susan are business analysts for their organization. They are examining two materials that could be used in an upcoming project.
They are testing the materials and measuring the results of each test to compare the materials to each other. This process will help Bob and Susan determine which material is best for their upcoming project. What type of process are Bob and Susan completing with these materials?
In order to plan business analysis activities, you will need four inputs. Which one of the following inputs is not valid for this task?
A business analyst wants to use benchmarking, but the project manager recommends against the approach. There are, as the project manager points out, several disadvantages to benchmarking. Which one of the following is not a disadvantage to benchmarking?
As a business analyst, you must identify activities in your business analysis approach. Which one of the following is useful for identifying activities?
A new contract requires a thorough level of documentation to be developed and maintained with planned phases of reviews and authorized sign offs. Which approach fits this contract?
A business analyst (BA) has elicited the following requirement; "The solution must ensure the portal response times are under 2 seconds." What requirement classification schema does this requirement belong to?
A new regulation results in organizations needing to change online contractual wording. A business analyst (BA) has elicited the requirements and documented them in a change control request Where will the BA find out which stakeholder has the authority to approve, deny, or defer the change request?
The Chief Executive Officer (CEO) of a company presents a new corporate strategy that will introduce a new system to the organization. The CEO has expressed a concern about the impact to the staff once the strategy has been implemented. What must the business analyst (BA) do to address concerns of the CEO?
A business analyst (BA) is designing solutions for a set of requirements and finds that there is an opportunity to improve the operations of the business. Which of the following is an opportunity for improvement the BA could recommend?
An organization's board of directors has funded a new mobile application to support external customers. The business case was developed with emphasis on objectives to broaden the organization's brand and increase customer engagement. The business analyst (BA) is reviewing a group of user stories with the product owner. One of these user stories is: "As a customer service representative, I need to enter my time on the mobile application so that I can leave work to pick up my sick daughter from school". The product owner wants to take advantage of this opportunity to provide the staff a way to enter their time away from the office and create an interface to the Payroll application. How must the BA evaluate alignment with the existing scope?
The claims intake workflow of an insurance company is being standardized across all branch offices. The business analyst (BA) assigned to this project has interviewed users individually in all the offices and plans to schedule a workshop with all the users. What should the BA do to prepare for the workshop?
A business analyst (BA) is working on a project for a media company. The BA has verified, validated, and prioritized the requirements based on business benefits. During the development phase, the team discovered that the current viewer will no longer be supported by the provider. The technical team needs to either upgrade to the newer version with different technology or find an alternate viewer. Given this new information, what is the next step for the BA?
A deployed loan product was funded with the expectation of prepayment risk reduction. Initially key performance indicators would be to take similar loan prepayment rates over the previous 10-year period and compare it with the new product. After implementation, the business analyst (BA) determines that the decade old housing market is vastly different. Which of the following should the BA consider for validity of performance measures?
A business owner has identified a high priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to perform an impact analysis of this change. Which factor will the BA need to consider?
A business analyst (BA) is facilitating a meeting with subject matter experts (SMEs) in which the SMEs are answering questions about the major business processes and associated activities the business performs. The BA will create a deliverable from this discussion that will assist in defining scope. What technique is the BA using?
An organization has hired a consulting firm to implement and customize a software solution they purchased. The firm has raised concerns regarding the effort required to develop a solution that meets all requirements. On what basis should the requirements be prioritized in this context?
A project manager (PM) is planning the project timelines along with a business analyst (BA) and they come across the task of requirement allocation. The PM wants to know what the dependencies are before the requirement allocation task is initiated and seeks the BA's advice. Which of the following is a dependency that the BA will highlight as a predecessor for requirement allocation?
After a walk-through of the requirements specification with the business users, the group determines that five requirements are now mandatory due to new government regulations. What should the business analyst (BA) do following the meeting?
The Chief Information Officer (CIO) of a large financial services firm with many technology applications was formally reviewing all ongoing projects and noticed that the requirements were complex and difficult to follow. The CIO asks the business analyst (6A) what would improve the stakeholder's ability to understand the requirements. Which of the following will improve the requirements quality?
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?
A software company wants to make a gradual change from its traditional way of developing requirements to a more adaptive approach. A business analyst (BA) is hired to quantify the probability that the solution will meet the company’s needs and assess the relevant risks. Which element of risk assessment does the BA need to consider?
A deployed loan product was funded with the expectation of prepayment risk reduction. Initially, key performance indicators (KPIs) would be to take similar loan prepayment rates over the previous 10-year period and compare them with the new product. After implementation, the business analyst (BA) finds that the decade-old housing market is vastly different. Which of the following should the BA consider for validity of performance measures?
A business analyst (BA) is preparing an analysis approach to replace a 12-year-old air traffic control system. The BA aims to define the solution definition before implementation, capture theinformation in standardized templates, and ensure that all activities are identified first and then divided into tasks. Which approach provides the appropriate level of formality for this project?
The Chief Information Officer (CIO) of a large financial services firm with many technology applications was formally reviewing all ongoing projects and noticed that the requirements were complex and difficult to follow. The CIO asks the business analyst (BA) what would improve the stakeholder's ability to understand the requirements. Which of the following will improve the requirements quality?
A business analyst (BA) is working on a project to implement a commercial off-the-shelf (COTS) application for tracking customers. In an observation session with a domain subject matter expert (SME), the BA notes that the SME keeps separate records for the customers who are also vendors. The BA knows that the new software has a module for vendor management that would integrate the vendor and customer records. Which type of opportunity has the BA identified?
A key stakeholder has requested an extensive range of performance measures for a replacement workflow system. A business analyst (BA) has decided to work closely with the stakeholder to validate the performance measures requested. The BA will be ensuring that the performance measures:
The business analyst (BA) is investigating techniques that would be appropriate for determining how and who uses data across the identified processes. Which technique should the BA select?
Two stakeholders are arguing over which model to use for requirements. One insists that using an activity diagram is superior, while the other prefers a state diagram. How should the business analyst (BA) resolve the conflict?
In a project meeting, stakeholders presented conflicting views on how the business analysis process should be conducted, leading to the sponsor becoming very upset. If a similar situation arises in the future, what can the business analyst (BA) do to avoid the situation?
An organization's Business Analysis Center of Excellence (BACoE) has deployed several business analysts (BAs) to provide business analysis to a cross-functional initiative. After the first phase of the project, the BACoE seeks to determine the effectiveness of the businessanalysis work. Which of the following techniques could be used to elicit feedback from all affected stakeholders?
A long-established company selling ice cream is entering its crucial sales period leading up to summer. Based on the company's risk tolerance, a business analyst (BA) has advised against replacing the most popular flavors with new untested flavors. What is the company's attitude toward risk, as assessed by the BA?
A business analyst (BA) is tasked with performing a gap analysis between two existing systems to combine into a single system or run just one system. Which of the following modeling formats will show the requirements for both systems side by side?
A facilities management company has an ambitious growth plan of doubling the revenue of their office waste recycling service over the next 12 months. The business analyst (BA) plans to define the objectives and align them with the enterprise’s vision, mission, and goals. What element of 'SMART' goals would this objective refer to?
A business analyst (BA) is supporting an organization in its product launch. The BA wants to identify assumptions about the benefits resulting from the new product. What does identifying assumptions help the BA manage?
The director of a furniture store manages a group of skilled carpenters who make furniture from locally available materials. The director decides to automate its inventory processes so that the carpenters can place orders for raw materials themselves. A business analyst (BA) is engaged to define the requirements and propose options for commercial off-the-shelf (COTS) inventory management solutions. After meeting with the director, the BA needs to schedule a workshop with the carpenters to:
A project is being initiated to enhance an online product because sales have declined for over a year. The company leaders are confident that all of the skills needed to improve the product exist within the company. By enhancing the product, sales will increase, and new customers will emerge. A business analyst (BA) will help the enhancement project by first:
During planning, elicitation, and sign-off of requirements, the stakeholders felt that their opinions were not heard and information was not frequently shared. What major competency was lacking in this process?
The product backlog refinement meeting for a project is complete, but two stakeholders do not agree on the priority of several product backlog items. What should the business analyst (BA) do to help move the project forward?
A lead business analyst (BA) has received negative feedback on the deliverables produced by BAs in the organization. A major concern was ambiguous requirements. What technique will help ensure business analysis information is clear and understandable?
The claims intake workflow of an insurance company is being standardized across all branch offices. The business analyst (BA) assigned to this project has interviewed users individually in all the offices and plans to schedule a workshop with all the users. What should the BA do to prepare for the workshop?
Before selecting a design solution, a company wants to ensure that stakeholder, solution, and transition requirements align with the business requirements and also that the design satisfies the requirements. What process is the business analyst (BA) completing?
A business analyst (BA) is defining a stakeholder approval approach for the requirement deliverables. The project involves implementing new government regulatory requirements with significant risk to the organization in case of non-compliance. According to the BABOK® Guide, what will the BA need to do?
A business analyst (BA) is working on a project that has a release date that cannot be changed. The BA engaged with stakeholders and completed the business requirements elicitation task. Upon review with the rest of the project team, it is determined that not all requirements can be implemented by the set deadline. What must the BA do to ensure maximum business value?
A business analyst (BA) working with a large insurance corporation interviewed an industry thought leader who predicted that many of the regulations currently imposed by the government will change very soon. The BA carefully documented all these inputs from the thought leader because it will impact many of the strategic initiatives of the insurance company. What specific element of requirement validation is being executed by the BA?
A system owner calls the project team to inquire about a recent change in one of the requirements, and insists that the change was never requested. What should the project team do to investigate the issue?
A business analyst (BA) is conducting a workshop with the purpose of analyzing a business process. Stakeholders of different business units are in attendance. Each stakeholder is able to explain their unit's contribution to the process, however, there is no end to end process owner who can provide a consolidated view. Which technique should the BA use to compare the stakeholder's inputs against each other in order to check for consistency and omissions?
A business analyst (BA) has completed documenting requirements and to save time, recommends sharing the requirements document with the development team to fast-track development immediately. What issue may arise by doing so?
A business analyst (BA) is creating a business process model (BPM) showing how the organization will handle errors reported on its website. The BA held a workshop with stakeholders about how the process might work. The BA was also given an instruction manual about a similar error-handling situation, but was advised that some minor aspects are not applicable to the new process. How can the BA use the manual?
An organization's Business Analysis Center of Excellence (BACoE) has deployed several business analysts (BAs) to provide business analysis to a cross-functional initiative. After the first phase of the project, the BACoE seeks to determine the effectiveness of the business analysis work. Which of the following techniques could be used to elicit feedback from all affected stakeholders?
During a requirements elicitation workshop, a stakeholder raises an issue that is outside of the project's scope. The business analyst (BA) facilitating the workshop should:
A business analyst (BA) is developing the requirements for an inventory management system. Some current accounting processes are automated but other departments like purchasing, marketing, sales and distribution departments work in isolation and have a manual process. They extensively use spreadsheets to maintain the transactions and at the end of the day the department managers manually verify and reconcile transactions before supplying the information to the accounting department. In order to verify and validate the elicited requirements, the BA will need to prepare a:
A passport agency has recently deployed an online system where customers can apply for, amend, and renew passports. The expected volumes have not been realized and as a result, the agency has not achieved the projected savings. A business analyst (BA) has been asked to investigate the potential causes of this shortfall by understanding the trends, patterns. and volumes at a detailed level. What method of requirements elicitation should the BA start with?
A business analyst (BA) is assessing risks on a project addressing the implementation of a new web portal. Which of the following would the BA classify as a project risk?
The business analyst (BA) has prepared a requirements package and it is now ready to present to the stakeholders. What is the purpose of presenting the package?
Several user groups are impacted by a proposed change to their daily work flow. How should the business analyst (BA) convey these changes so that the user groups understand the impact?
A business analyst (BA) is compiling information about different approaches that will meet solution
requirements in order to make a recommendation for solution design. To evaluate whether externally available solutions meet the requirements, which of the following will the BA create and distribute?
A business analyst (BA) is tasked with developing requirements that can be implemented by the development team iteratively. Which characteristic should the requirements exhibit?
The business analyst (BA) has completed the verification of a set of requirements, but a change in scope has materialized. Which technique should the BA use to obtain consensus and reach agreement among the stakeholders?
A project's business requirements require that the new solution reduce the labor costs currently attributed to performing end of month accounting procedures. Currently the company routinely must pay overtime to meet the deadline. The business analyst (BA) has been documenting the process and wants to ensure that the approach to the process design is feasible for the staff who perform the end of month procedures. Which of the following stakeholders will provide this verification?
A business analyst (BA) has been spending the majority of the past week cataloguing the new, removed, and modified components of an upcoming project. What is the main purpose of the BA performing this work?
A business analyst (BA) is identifying the functions and features required for a new enterprise software solution. The BA reviews historical documents about the current business processes and then interviews each stakeholder group, individually, asking Questions about current business processes. The BA compares the information obtained during the stakeholder interviews with the information gathered from the historical documents. Which activity is the BA performing with this approach?
A one-location restaurant has been a huge success and the owner wants to expand into more markets. The owner wants to ensure that the quality of the food and pleasing atmosphere is maintained without introducing new variables. Working with the key members of the organization, the owner determines that training and standard processes must be defined. The owner engages a business analyst (BA) to create training materials and operating procedures based on the existing processes at the original restaurant. During this documentation, the BA identifies some opportunities for improvement. How must the BA proceed?
Requirements have been prioritized in the product backlog for inclusion in the upcoming release. One of the project team members fears that at least one requirement from the prioritization list is not finalized and still requires further analysis. Which of the following factors describe the affected requirement?
A business analyst (BA) is working on a project to provide a temporary solution that will last for two months. The BA is feeling overwhelmed with the work needed to create the huge number of links to provide full traceability from solution requirements to design for this solution. How can the BA justify omitting all possible links?
A business analyst (BA) is preparing the elicitation activity plan for a project. How will understanding the elicitation scope assist the BA with the elicitation activity?
There are competing needs from the different business areas that will use a new system. The business analyst (BA) sets up a weekly meeting with a structured agenda to review the total effort, cost, business impact and risk of each requirement with the business leads to determine what is included in each release of the solution. What approach has the BA defined?
A client wants to rehire a business analysis consulting firm for another project. The assigned business analyst (BA) developed a good rapport with the stakeholders, but delivered documents that contained lots of technical jargon that the client could not fully understand. Based on the feedback, the consulting company should:
Kelly is the business analyst for her organization and she's identifying roles and responsibilities of the people involved in business analysis activities. Her manager has asked Kelly to create the RACI matrix to accomplish this task. What is the RACI matrix?
You are the business analyst for your organization and you're working with the key stakeholders to validate the requirements. In your review, you have determined the business value of each requirement and you've discovered three requirements that do not deliver direct or indirect value to the stakeholders. What should you do with these requirements?
Brian is the business analyst for his organization and he's hosting a brainstorming session. He is facilitating the session with eight stakeholders. Why is it important for Brian to not set a goal for the number of ideas the group should generate in the session?
You are the business analyst for your organization. On your current project you'll be using the change-driven approach for defining requirements and gathering feedback. Which of the following statements best describes the change-driven approach?
In order to assess the capability gaps of an organization, you'll need all of the following inputs except for which
one?
Your organization is using a plan-driven approach to business analysis. What must you do with all of the communication documents created as part of this high-priority project that you are serving as the business analyst for?
A business analyst (BA) is working to identity the business need, specifically the problems with the current state of a process. At which level of the enterprise can the BA identify problems with the current state?
The business analyst (BA) has scheduled an informal review of audit requirements with the compliance officer. The BA wants to demonstrate that the requirements collectively support one another so begins with reviewing the:
A business analyst (BA) must model information characteristics across multiple information systems for a project. What type of model captures this information?
A company is embarking on a software project in a heavily regulated domain. The client expects large upfront planning and detailed documentation for the project. The recommended approach for the project will be:
A lead business analyst (BA) analyzed the performance of all BA's within the organization. How should the BA approach communicating the results to stakeholders?
A business analyst (BA) is verifying requirements for a software solution. The BA needs to confirm that items determined to be important are included in the final requirements deliverable. Which of the following will help the BA complete this task?
A business analyst (BA) is working on a project that follows incremental and iterative approaches. The BA and the stakeholders have shortlisted several user stories to be considered in the project scope. Which of the following methods would enable them to arrive at a common understanding on delivering value in the product and ranking the stories?
A business analyst (BA) has discovered an old checklist prepared for another initiative, which includes the following characteristics: Complete, Feasible, Unambiguous, Testable. What is the purpose of this checklist?
A business analyst (BA) is structuring requirements to ensure they are cohesive and tell the full story. Which of the following requirements is consistent with a stakeholder's need: “As a Product Manager, I want to review my general insurance sales performance so I track my sales performance against my annual target”?
A business analyst (BA) is supporting an organization in its product launch. The BA wants to identify assumptions about the benefits resulting from the new product. What does identifying assumptions help the BA manage?
A company wants to increase its market share in the industry and its Board has prioritized capabilities that need to be implemented to achieve the goal. The business requirements for the top priority were signed off and the solution design has been completed. Due to technical constraints, it is not feasible to implement all the requirements at the same time. What must the business analyst (BA) do to deal with this situation?
A senior business analyst (BA) must review the requirements specification of a junior BA. The senior BA puts together a list of key evaluation criteria to guide the determination of a requirement’s quality. Which of the criteria below is a characteristic of a quality requirement?
A business analyst (BA) has recently joined a large consultancy firm where BAs are globally distributed on different assignments. Where would the BA find expectations for business analysis work as mandated by the consultancy firm?
A business analyst (BA) is examining the relationships between elicited requirements on a project. What quality criteria must be satisfied when the BA is defining requirements relationships?
Project work is taking place to evaluate whether a system's requirements can be met via creating internally, purchasing from others, or a combination of the two. What goal is addressed by this analysis?
A business analyst (BA) has spent the week conducting work sessions with key stakeholders. Together, they have been reviewing user requirements and high-level design flowcharts to ensure that they have been correctly defined and documented. Which of the following describes the purpose of their work?
A business owner has identified a high-priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to conduct an impact analysis of this change. Which factor will the BA need to consider?
A business analyst (BA) is logging end-user concerns and resolving these on a priority basis as mandated by the government. This project is a simple application, with no major strategic or financial impact on the organization. The BA strongly enforced end-to-end requirement traceability for this project. Why would the BA recommend this traceability approach?
Stakeholders must be able to determine the audit and approval history of requirements and designs. Which of the following provides a means to document traceability and change?
A business analyst (BA) conducted a requirements elicitation session with project stakeholders and communicated the results. The project sponsor expressed concern with certain requirements that address the federal government legislation. What must the BA do to address the concern of the project sponsor?
A project is being initiated to create new financial reports for the accounting department, and the accountants have a wide range of views as to what would serve them best. What should the business analyst (BA) do to develop the correct set of requirements?
A business analyst (BA) held a formal walkthrough of requirements developed on a project. Stakeholders expressed concerns because they had different interpretations of the requirements. What activity would help ensure a common understanding?
A business analyst (BA) is working on a data-centric IT project. The business stakeholders develop the content but do not understand the technical aspects, while the IT team believes that there is no need to understand the business issues. Which deliverable will facilitate understanding between IT and the business stakeholders?
A business analyst (BA) has just started a large project and is collaborating with stakeholders to define requirements. Another BA is joining soon to help with this initiative. What action should the BA take to ensure that the new BA understands the project?
A project manager asks a business analyst (BA) to conduct a meeting to walk the stakeholders through how requirements are structured. Which of the following requirement viewpoints will help the BA provide that information?
A business analyst (BA) has completed multiple workshops involving a number of stakeholders, including the project manager; however, the elicitation results are inconsistent between the stakeholders. How should the variation in results be resolved?
Which one of the following statements best describes a business analysis methodology?
As part of a strategic initiative, a bank decides to expand operations to a new country where the most commonly used language is Spanish. The bank's current mobile application only supports English. The organization initiates a project to provide local language support for the app. From which level did the business need originate?
A long-established company selling ice cream is entering its crucial sales period leading up to summer. Based on the company's risk tolerance, a business analyst (BA) has advised against replacing the most popular flavors with new untested flavors. What is the company's attitude toward risk, as assessed by the BA?
A business analyst (BA) has set up a number of elicitation workshops with key subject matter experts (SMEs) on a new project. All SMEs have accepted the workshop invitations except for the legal SME who has not responded to any invitations. The first workshop is scheduled for next week and the BA has tried unsuccessfully to reach the legal SME by phone. How should the BA proceed?
A business analyst (BA) is working on an effort to upgrade a system to take advantage of new technology. Most of the end users with the business knowledge and IT staff with technical knowledge of the system are no longer with the company. What can the BA evaluate to better understand the extent of the effort?
Stakeholder requirements were approved for a business process reengineering initiative along with the creation of a roadmap.
Due to market conditions, the product roadmap is modified to move the default process to the next iteration. What should the business analyst (BA) modify in the stakeholder requirements?
Requirement attribute values
Requirement description
Requirement performance measures
An organization has identified a market opportunity that could result in significant business gains. A business analyst (BA) is asked to assist in building the new business model. The BA begins by analyzing the current state. What input is critical to the current state analysis?
A finance manager wants to begin a new project to replace the existing expenses processing system. The finance manager feels that the current expense submission-to-reimbursement process takes too long and is substantiated by 50% more complaints regarding incorrect reimbursement amounts than the same time last year. What should the business analyst (BA) investigate first?
A business analyst (BA) decided to capture requirements by inviting all the stakeholders to meet at an office location. After invitations were sent, it turned out that not everyone could attend this meeting because of their individual dispersed locations.
Which of the following does the BA need to adjust to handle this situation?
A change to support a regulatory requirement is proposed for inclusion in the scope of a project. A business analyst (BA) conducts an impact analysis to determine the extent of the change. What previous task could assist the BA in performing the impact analysis?
A business analyst (BA) has developed requirements for a project containing sensitive information. The requirements were approved and the solution was implemented. What should the BA do to ensure these requirements are maintained for future reference?
The human resources department of an organization needs a new report. The business analyst (BA) assigned to this effort has scheduled a requirements workshop with the users. Users from the legal department have also been invited to the workshop. As the BA sets up the workshop, what can be done in advance to ensure a productive and focused workshop?
The product backlog refinement meeting for a project is complete but two stakeholders do not agree on the priority of several product backlog items. What should the business analyst (BA) do to help move the project forward?
A business analyst (BA) is working on a data-centric IT project. The business stakeholders develop the content but do not understand the technical aspects while the IT team believes that there is no need to understand the business issues. Which deliverable will facilitate understanding between IT and the business stakeholders?
The project manager has tasked the business analyst (BA) to collect a performance measure on the solution implemented in the latest release. Which of the following considerations can help the BA obtain that information?
A recent survey shows that a newly implemented system has features that the users have never used. Upon reviewing the survey report, the Chief Executive Officer (CEO) highlighted that the company must avoid future implementations with functionality that does not provide any business value. What must the business analyst (BA) do to ensure future requirements meet a business need?
A business analyst (BA) is logging the end user concerns and resolves these on a priority basis as mandated by the government. This project is a simple application, with no major strategic or financial impact to the organization. The BA strongly enforced end-to-end requirement traceability for this project. Why would the BA recommend this traceability approach?
A business analyst (BA) elicits requirements from end users for a new application, and then completes a set of use cases and use case scenarios. What should the BA do next?
A lead business analyst (BA) has received negative feedback on the deliverables produced by BAs in the organization. A major concern was ambiguous requirements. What technique will help ensure business analysis information is clear and understandable?
A business analyst (BA) asked two stakeholders with approval authority to approve the requirements. The stakeholders are being asked to confirm that:
A business analyst (BA) is negotiating and resolving conflict with stakeholders to ensure they participate in the required BA activities. Which element of stakeholder management is the BA performing?
A stakeholder has requested an extremely detailed resolution to an issue during current state analysis that may consume about 20% of the estimated project effort. How should the business analyst (BA) handle the situation?
A business analyst (BA) spent three months eliciting, specifying, and modelling the detailed stakeholder and solution requirements. Right before requirement sign-off, the BA realized that the Vice President was unable to approve the requirements and the Chief Financial Officer should do so. What element of requirement approval did the BA miss?
Project work is taking place to evaluate whether a system's requirements can be met via creating internally, purchasing from others, or a combination of the two. What goal is addressed by this analysis?
You are the business analyst for your organization and working with the stakeholders to prioritize the requirements. The stakeholders are concerned about the financial impact of the requirements should some of them fail during the implementation. You would like to rank the risk tolerance of the stakeholders based on their comments about the solution and the requirements. The following are the three categories of risk tolerance associated with the stakeholders except for which one?
As a business analyst, you may be called upon to define the scope of work and to develop the estimates for the endeavor. Which one of the following is an important tool for this activity?