A business analyst (BA) has developed requirements for a project containing sensitive information. The requirements were approved and the solution was implemented. What should the BA do to ensure these requirements are maintained for future reference?
After an initial project kick-off meeting, the business analyst (BA) determined that the project has a short deadline and a regulatory mandate with stiff penalties for non-compliance. The stakeholders do not want to risk missing the deadline, and management is willing to commit any amount of resources to meet the deadline. Which kind of approach is suitable for the initiative?
A business analyst (BA) is planning how to present a set of requirements for a project with financial constraints. Which requirements attribute should the BA assign to allow cost implications to be assessed?
A business analyst (BA) is facilitating a meeting with subject matter experts (SMEs) in which the SMEs are answering questions about the major business processes and associated activities the business performs. The BA will create a deliverable from this discussion that will assist in defining scope. What technique is the BA using?
A business analyst (BA) elicits requirements from end users for a new application, and then completes a set of use cases and use case scenarios. What should the BA do next?
The Chief Information Officer (CIO) of a large financial services firm with many technology applications was formally reviewing all ongoing projects and noticed that the requirements were complex and difficult to follow. The CIO asks the business analyst (6A) what would improve the stakeholder's ability to understand the requirements. Which of the following will improve the requirements quality?
A project team needs to maintain the traceability of requirements for a software system. Due to the large number of requirements, which of the following methods should the team use?
Market studies projected a 28% year over year growth for five (5) years for commercial vehicle loans. A company that provides lending for commercial vehicles wanted to keep up with industry demand; however, their applications were not capable of scaling to the increased demand for loan processing and billing. The company is deploying a new system to meet the demand. The project started five (5) years ago and cost S2 million USD. The project metrics are to be evaluated after five (5) years. The return on investment (ROI) for the project is calculated at 11%. The project sponsors are upset that the desired ROI for the project was not met. The actual demand for commercial vehicle loans for the past five (5) years is as follows:
Before selecting a design solution, a company wants to ensure that stakeholder, solution, and transition requirements align to the business requirements and also that the design satisfies the requirements. What process is the business analyst (BA) completing?
A business analyst (BA) conducted a requirements elicitation session with project stakeholders and communicated the results. The project sponsor expressed concern with certain requirements that address the federal government legislation. What must the BA do to address the concern of the project sponsor?
A business analyst (BA) is preparing an analysis approach to replace a 12-year-old air traffic control system. The BA aims to define the solution definition before implementation, capture the information in standardized templates, and ensure that all activities are identified first and then divided into tasks. Which approach provides the appropriate level of formality for this project?
During a senior management meeting about a project at the requirements analysis stage, a business analyst (BA) stated that there were a number of workarounds associated with the current application. The Chief Information Officer (CIO) was looking for ways to improve the situation and the BA suggests a solution. Which of the following can the BA suggest that the organization consider to increase efficiencies?
Stakeholders must be able to determine the audit and approval history of requirements and designs. Which of the following provides a means to document traceability and change?
The business analyst (BA) is helping the business stakeholders prioritize requirements for a new customer portal for managing orders, delivery, and payment information. A number of requirements address compliance with regulations regarding access for people with disabilities. What factor should the BA use to guide the stakeholders when assigning a priority for these specific requirements?
A business analyst (BA) plans to organize a focus group to bring all the interested parties together and discuss the issues and possible risks for the new initiative. Due to the geographical differences of each participant a videoconferencing service will be used to satisfy stakeholder preferences. Which approach is the BA defining?
A business owner has identified a high priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to perform an impact analysis of this change. Which factor will the BA need to consider?
A finance manager wants to begin a new project to replace the existing expenses processing system. The finance manager feels that the current expense submission-to-reimbursement process takes too long and is substantiated by 50% more complaints regarding incorrect reimbursement amounts than the same time last year. What should the business analyst (BA) investigate first?
Which of the following is a business management strategy originally developed by Motorola, USA in 1986?
A senior business analyst (BA) must review the requirements specification of a junior BA. The senior BA puts together a list of key evaluation criteria to guide the determination of a requirement's quality. Which of the criteria below is a characteristic of a quality requirement?
You are the business analyst for your organization and your requirements for the endeavor have recently been approved. Your organization creates a baseline for the requirements based on the approval of the requirements. What must happen in your business analysis activities if the requirements for your endeavor need to be changed?
You are the business analyst for your organization and you're working with the project manager to complete some business analysis activities. The project manager has the authority to approve the requirements based on the short iterations of business analysis activities.
What approach of business analysis are you using in this scenario?
When a business analyst completes the task of organizing requirements, he is completing two key objectives. What are the two objectives?
You are currently working on creating the activity list for an initiative in your organization. What characteristic must be assigned to each task in your task list?
You are the business analyst for your organization and you're creating the requirements package. In this documentation, to what level should you document the requirements for your stakeholders?
Which of the following is used as a means of validating a created, selected, or tailored business analysis approach?
You are the business analyst for your organization and you're performing the solution assessment process. When you assess a solution, what are you actually looking for?
A business analyst (BA) is working on a data-centric IT project. The business stakeholders develop the content but do not understand the technical aspects while the IT team believes that there is no need to understand the business issues. Which deliverable will facilitate understanding between IT and the business stakeholders?
A key stakeholder has requested an extensive range of performance measures for a replacement workflow system. A business analyst (BA) has decided to work closely with the stakeholder to validate the performance measures requested. The BA will be ensuring that the performance measures:
Jason is creating a business case for his organization and management has asked him to assess the appropriate risks in the business case regarding the solution. Which one of the following risks is not a concern for Jason when defining the business case and associated risks?
You are the business analyst for your organization and you're training Marcy, a new business analyst, on how requirements are defined. Which one of the following best describes how requirements are defined?
You are the business analyst for your organization and you're working with Nancy, the Sales Director. You've been identifying requirements for Nancy about the sales force and her desire to add a customer management solution to the sales process. Nancy believes that the software can help automate the sales process, keep things better organized than the current approach, and ultimately create more sales for the organization. As a business analyst, which one of the following should you advise Nancy about her need?
Billy is the business analyst for her organization and she's working with a team to select a model. Richard doesn't understand why a model is needed for the requirements. Which one of the following statements best describes the reason to use a model?
You are the business analyst for your organization. You've believed that your solution can actually be purchased from outside vendor rather than trying to create the solution internally. You decide to ask the vendor to provide a fee for their services based on the statement of work. What document will you give the vendor along with the statement of work?
What business analysis process is needed to define the solution scope and prepare the business plan for the endeavor?
In order to assess proposed solutions, business analysts will need three inputs. Which one of the following is not an input to the task of assessing proposed solutions?
A business analyst is studying the cost of the endeavor in relation to the projected income the endeavor will bring once the project is completed. What financial valuation technique can the business analyst use to determine the breakeven point for the project?
As a business analyst, you should be able to identify the characteristics of each business analysis task and domain area. Which one of the following statements best describes the characteristics of the business analysis knowledge area of requirements analysis?
Holly is the business analyst for her organization and she's leading a requirements workshop for a proposed solution. In this workshop, Holly is using a requirements tracing matrix to help prevent against scope creep. What is scope creep?
Which task in the requirements analysis knowledge area is best described as ensuring that the requirements specifications and models meet the necessary standard of quality to allow them to be used effectively to guide further work?
A business analyst has just completed an elicitation event. What stakeholder(s) is/are involved in the documentation of the elicitation results?
You are the business analyst for your organization and you are completing the manage requirements traceability process. You are tracking the requirements to determine how the requirements are interrelated with one another and with the actual delivery of the project scope.
There are actually three reasons why the business analyst should trace requirements. Which one of the following is not one of the three reasons why trace requirements are useful?
As a business analyst in your organization, you must understand the difference between operative rules and structural rules. What is the difference between structural rules and operative rules?
Enterprise analysis creates just five outputs. Which one of the following is an output of the enterprise analysis tasks?
A project to implement shared registration procedures across multiple jurisdictions has stalled several times. The new business analyst (BA) assigned to the project used a collaborative game to elicit requirements. What effect was the BA attempting to achieve?
You are the business analyst for your organization and you've been working with several stakeholders to
gather requirements for approval.
The requirements have been approved with the exception of a conflict on one requirement. What must you and the stakeholders do in regard to this conflict before the business analysis endeavor may continue?
You are the business analyst for your organization and you're creating a business analysis communication management plan. In your plan, you want to address the different locales and culture and the communication needs that may affect the business analysis approach. Which one of the following elements should not be included in the cultural analysis of the plan?
You are a business analyst for your organization. Your current business analysis endeavor includes working with stakeholders located in offices around the world. Because these stakeholders are dispersed, what is likely to increase in this endeavor as opposed to a collocated group of stakeholders?
You are the business analyst for your organization and are working on organizing the identified requirements for a new solution. Nancy, your assistant in this process, says that these requirements aren't very complex. You agree but add that it's this thing that makes the overall solution complex. What thing adds to the level of complexity among requirements?
What does the decomposition of activities and tasks based on the work breakdown structure create for the business analyst?
You are the business analyst for your organization. Management has asked that you create a method to store the project requirements including those under development, under review, and the requirements which have been approved. What is management asking you to create?
Which one of the following terms is not a business analysis planning and monitoring approach?
There are many stakeholders that need to be involved in the allocated requirements. One of the stakeholders in the task will be responsible for verifying released and solution components. Which stakeholder has this
responsibility?
The project plan called for deliverables to be handed over at the end of the project. Although the client's business team was satisfied, the client's technical team was extremely resistant to this approach. What could the business analyst (BA) do to mitigate the technical team’s resistance?
You are the business analyst in your organization and you're working to organize the requirements for the business units in your company. Which technique is best suited for structuring requirements around the needs of each stakeholder group?
You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system. You would like to plan the communications that need to be made during the project lifecycle. Which of the following would be a critical tool/technique to help in your communications planning?
As a business analyst, you must identify activities in your business analysis approach. Which one of the following is useful for identifying activities?
There are three business analysis planning techniques that a business analyst can use to help plan business analysis processes. Which one of the following is not one of the three techniques?
If you're a business analyst and using an event-based elicitation task, such as a requirements workshop, what can be considered as essential to establish with the participants?
Complete this sentence in regard to the level of abstraction. Requirements need to say needs to be done, not to do it.
Complete this sentence. If a requirement cannot be verified, it cannot be successfully .
Complete this statement. are longer-term, ongoing, and qualitative statements of a state or condition that the organization is seeking to establish and maintain.
There are four inputs to the plan business analysis activities. Which one of the following is not an input to the plan business analysis activities process?
There are three inputs needed to determine the solution approach process. What are these inputs?
When a business analyst is using alternative generation, what should she always include as an output?
A business analyst (BA) is assessing the completeness and coherence of the requirements. The BA has considered a variety of viewpoints and has a collection of views. What has the BA constructed?
A business analyst has determined that a project should be worth $2,750,000 in four years if her company decides to pursue the project. Assuming the rate of return on the investment is six percent, what is the minimum amount of funds the organization should invest in this project?
Which of the following defines all of the features and functions of the thing, solution, or service the project or organization will create?
Shelly is the business analyst for her organization and she's working with Thomas to review the business requirements. They are discussing the identified requirements, how the requirements will transition to the operations, and the longevity of the solution. Thomas is concerned that the identified requirements may not map to the desired future state of the organization. What business analysis task is Shelly facilitating in this scenario?
What condition of the requirements must be fulfilled in order to use the matrix documentation approach to specify and model requirements?
You are a business analyst for your organization and you're working with the stakeholders to identify the primary inputs to the business analysis approach. Which of the following will help determine whether a plan- driven or change-driven approach is appropriate?
Each correct answer represents a complete solution.
Kelly is the business analyst for her organization and she's identifying roles and responsibilities of the people involved in business analysis activities. Her manager has asked Kelly to create the RACI matrix to accomplish this task. What is the RACI matrix?
A project team member is confused about why a small change requires the team to look at the different enterprise-level business objectives when a desired state can be achieved easily without this analysis. What can the business analyst (6A) do to help the team member understand?
An organization is experiencing long contracting life cycles when establishing annual contracts with its customers. Upon initial investigation, the outdated application was thought to be the cause, however based on further analysis the business process is found to be flawed. The business analyst (BA) wants to model the people involved in the process. Which of the following techniques models the responsibilities of these stakeholders?
A business owner has marked certain requirements as high priority for the upcoming release. After performing some analysis, the project team concluded that some of these requirements are not actually high priority and can be implemented in later releases. How should the project team proceed with prioritizing requirements?
A business analyst (BA), analyzing requirements, has decomposed information into components. What is the purpose of this exercise?
The claims intake workflow of an insurance company is being standardized across all branch offices. The business analyst (BA) assigned to this project has interviewed users individually in all the offices and plans to schedule a workshop with all the users. What should the BA do to prepare for the workshop?
An organization has identified a market opportunity that could result in significant business gains. A business analyst (BA) is asked to assist in building the new business model. The BA begins by analyzing the current state. What input is critical to the current state analysis?
A company wants to launch a new product that will have similar features to an existing product. A business analyst (BA) working on the project has invited the product manager to explain the features and business rules of the new product. Which activity must the BA perform in preparation of the session?
A business analyst (BA) is working on a project to improve product delivery. The issues arise during the latter stages of the delivery Freecycle and are due to poor communication of the business analysis information from the elicitation phase. As a result, a BA has ensured that the testing and training teams are identified as stakeholders on the RACI Matrix going forward. To which RAG designation should the training and testing teams be added?
Stakeholders initially agreed to an implementation schedule for a set of reports based on the value to business users. The development team provided a detailed estimate of the time required to develop each report based on the business requirements. What should the business analyst (BA) and the stakeholders do with the estimates?
The Chief Executive Officer (CEO) of a company presents a new corporate strategy that will introduce a new system to the organization. The CEO has expressed a concern about the impact to the staff once the strategy has been implemented. What must the business analyst (BA) do to address concerns of the CEO?
A business analyst (BA) has elicited the following requirement; "The solution must ensure the portal response times are under 2 seconds." What requirement classification schema does this requirement belong to?
A business analyst (BA) is managing stakeholder collaboration to ensure positive reactions are capitalized upon. There is uncertainty as to whether the correct stakeholders have been identified. Which technique can be used to correct this situation?
A business analyst (BA) is working on a project for a media company. The BA has verified, validated, and prioritized the requirements based on business benefits. During the development phase, the team discovered that the current viewer will no longer be supported by the provider. The technical team needs to either upgrade to the newer version with different technology or find an alternate viewer. Given this new information, what is the next step for the BA?
After a walk-through of the requirements specification with the business users, the group determines that five requirements are now mandatory due to new government regulations. What should the business analyst (BA) do following the meeting?
A project to replace a financial system uses a waterfall methodology. Initially, meetings with the project subject
matter experts (SMEs) were positive. As the project progressed through the requirements and design phases, the SMEs attended fewer meetings, resulting in a delay to the project build phase. What should the business analyst (BA) have done to prevent the delay?
After a number of requirements elicitation workshops, the business analyst (BA) notices that two business stakeholders did not speak up during any of the discussions. What should the BA do in the next workshop?
A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?
A business analyst (BA) is working on a project that has a number of stakeholder conflicts and issues. The BA is finding it difficult to resolve the conflicts and issues effectively. What should the BA do to prevent a similar situation in the future?
Stakeholder requirements where approved for a business process reengineering initiative along with the Creation of a | roadmap. Due to market conditions, the product roadmap is modified to move the default process to the next iteration. What should the business analyst (BA) modify in the stakeholder requirements?
The creative thinking process has three values to determine the effectiveness of the process. Which one of the following is not a measurement of effective creative thinking?
In order to plan the business analysis approach, the business analyst must understand the organizational process needs and what other thing?
What is the purpose of managing the solution scope and requirements from a business analyst's objective?
Which of the following documents graphically depicts the project team members and displays their interrelationship for a specific project?
A business analyst (BA) has determined that “Product Box”, a collaboration game, will provide a fun way to engage the stakeholders when working on prioritizing the list of features. What should the BA do?
You are the business analyst for your organization and you're working with Adam on business analysis processes. Adam allows the business analysis activities and resources to exist in support of the organization. Of the following, what type of business analysis stakeholder is Adam?
You are the business analyst for your organization and you're creating a data flow diagram to show how
information is input, processed, stored, and output from a system. Which element of a data flow diagram represents a process that transforms data by combining it with other data?
As a candidate for the CCBA exam, you should be able to recognize the activities associated with each knowledge area. All of the following are the business analysis planning & monitoring activities except for which one?
You are the business analyst for your organization and you're working with your stakeholders to assess the organization's readiness for the solution. As part of this assessment, you'll perform a cultural assessment. What is the purpose of this assessment?
According to the book 'A Guide to the Business Analysis Body of Knowledge', effective business analysis practices can do what to the amount of change to requirements in a stable business environment?
Which basis for prioritization allows the project team to work initially with lower-risk requirements first?
Wanda is the business analyst for her organization and she is currently working on the specify and model requirements process. One of the elements of this process is the documentation of the textual requirements. Wanda must describe the capabilities of the solution, any conditions that must exist for the requirements to operate, and what third component of the textual requirement?
You are the business analyst for your organization. You are currently writing the business goals and objectives as part of the elements for the define business process. Which one of the following statements best describes the business goals and objectives element?
What should an organization do if the business analyst has determined that the existing capabilities are inadequate to seize an opportunity?
Which of the following is the prime purpose of the Manage Stakeholders Expectations process?
You work as a business analyst for u Certify Inc. You have been assigned the task to implement the job
shadowing process. Which of the following statements are true regarding the job shadowing process? Each correct answer represents a complete solution.
An organization has selected a solution for a business need and the business analyst has elected to use the time boxing/budgeting technique for requirements prioritization. What is the time boxing/budgeting technique?
John and Hanna are business analysts in their organization and they are completing the verification activities to check for completeness of the requirements. When should John and Hanna perform these verification activities?
Which technique in organizing requirements is best described as showing the concepts and relationships relevant to the solution or business domain?
Mark is a business analyst for his organization. A business need has been identified; therefore, Mark immediately sets out to identify the stakeholders. How long will stakeholder analysis need to continue?
A business analyst (BA) is tasked with developing requirements that can be implemented by the development team iteratively. Which characteristic should the requirements exhibit?
A business analyst (BA) has been spending the majority of the past week cataloguing the new, removed, and modified components of an upcoming project. What is the main purpose of the BA performing this work?
A survey on a new system was conducted after the chief executive officer (CEO), who is also the project sponsor, expressed concerns about the uptake of the new system. The CEO is neither sure that the concerns are valid nor whether the survey was conclusive about the success of the project. The business analyst (BA) has been tasked to address the concerns expressed by the CEO and evaluate the results of the survey. What must the BA do to determine that the system is performing as intended and address the concerns of the CEO?
A project's business requirements require that the new solution reduce the labor costs currently attributed to performing end of month accounting procedures. Currently the company routinely must pay overtime to meet the deadline. The business analyst (BA) has been documenting the process and wants to ensure that the approach to the process design is feasible for the staff who perform the end of month procedures. Which of the following stakeholders will provide this verification?
A business analyst (BA) is supporting an organization in its product launch. The BA wants to identify assumptions about the benefits resulting from the new product. What does identifying assumptions help the BA manage?
A business analyst (BA) is working on a project involving the purchase of a commercial off-the-shelf (COTS) product. All internal risks have been identified and assessed. What is the BA's next course of action?
Stakeholders need a financial report that can be published and distributed to multiple end users. They would also like the report to be developed within a specific time frame and within cost. What must the business analyst (BA) do to achieve this goal?
One of the tasks that the business analyst (BA) needs to complete is to maintain the requirements. As much as the BA values and sees the benefits of maintaining the requirements, the project manager (PM) does not see the same. In order to help the PM understand the value of this task, which following benefit of maintaining the requirements should the BA communicate to the PM?
A business analyst (BA) is determining the current state as part of a new project. What is an internal enterprise asset that the BA must include in the analysis?
A new regulation is introduced that the project must comply with to remain competitive and industry compliant. Management wants to understand the effect of this new requirement on the project. What will the business analyst (BA) use to evaluate the change?
A client wants to rehire a business analysis consulting firm for another project. The assigned business analyst (BA) developed a good rapport with the stakeholders, but delivered documents that contained lots of technical jargon that the client could not fully understand. Based on the feedback, the consulting company should:
A business analyst (BA) is in the process of eliciting requirements. It has been determined that not all requirements can be implemented by the project deadline due to complexity. What must the BA do to ensure maximum benefit for the stakeholders?
A business analyst (BA) is defining a stakeholder approval approach for the requirement deliverables. The project involves implementing new government regulatory requirements with significant risk to the organization in case of non-compliance. According to the BABOK ® GUIDE, what will the BA need to do?
A business analyst (BA) is preparing the elicitation activity plan for a project. How will understanding the elicitation scope assist the BA with the elicitation activity?
A business analyst (BA) is working on a set of tasks to establish a governance process for the project. The BA intends to identify who has authority and responsibility to propose changes, who should be involved in the change discussions, and how changes will be documented and communicated. Which of the following are the inputs that would help the BA complete the task?
A business analyst (BA) has been asked to develop a plan to complete the associated business analysis activities for a project in which an organization is switching from a manual to an automated process for receiving payments. As the final step in developing the plan, which technique will the BA use?
A business analyst (BA) is assessing risks on a project addressing the implementation of a new web portal. Which of the following would the BA classify as a project risk?
A one-location restaurant has been a huge success and the owner wants to expand into more markets. The owner wants to ensure that the quality of the food and pleasing atmosphere is maintained without introducing new variables. Working with the key members of the organization, the owner determines that training and standard processes must be defined. The owner engages a business analyst (BA) to create training materials and operating procedures based on the existing processes at the original restaurant. During this documentation, the BA identifies some opportunities for improvement. How must the BA proceed?
The business analyst (BA) has prepared a requirements package and it is now ready to present to the stakeholders. What is the purpose of presenting the package?
Two business analysts (BAs) are working on a requirement elicitation activity. One BA comes across a checklist that contains stakeholder details such as who are involved, location, group dynamics that are to be considered before beginning the elicitation activity and seeks a clarification from the second BA. The other BA explains that these details, along with several other items mentioned in the checklist, are required to:
Due to a change in regulation, a solution being implemented has a new compliance requirement that must be evaluated. The requirements change strategy focuses on total cost of change as the primary driver for decisions. The business analyst (BA) compiled the following impact assessment of the proposed change based on the new compliance requirement.
What recommendation should the BA make to the stakeholders based on the above information?
A business analyst (BA) is currently verifying the accuracy and consistency of information obtained from the stakeholders. The BA needs to identify additional information. What should the BA do next?
An organization is engaged in an effort to streamline the online customer experience. The business analyst (BA) prepares a business analysis information package to discuss the changes the customer will experience. Which one of the following tools will assist the BA in this discussion?
A business analyst (BA) is identifying the functions and features required for a new enterprise software solution. The BA reviews historical documents about the current business processes and then interviews each stakeholder group, individually, asking Questions about current business processes. The BA compares the information obtained during the stakeholder interviews with the information gathered from the historical documents. Which activity is the BA performing with this approach?
A business analyst (BA) is creating a business process model (BPM) showing how the organization will handle errors reported on its website. The BA held a workshop with stakeholders about how the process might work. The BA was also given an instruction manual about a similar error-handling situation, but was advised that some minor aspects are not applicable to the new process. How can the BA use the manual?
A business analyst (BA) is reviewing the elicitation results of several workshops in order to decide which technique to use to model the requirements. The elicitation identified user roles needed in a future solution, the functionality needed by each of these roles, and how the desired interaction with the solution should look.
Which technique allows the BA to model this type of information?
A business analyst (BA) has identified the impacts and resolution for a proposed change. Based on the Responsible, Accountable, Consulted, informed (RACI) matrix, who must approve the change before it is implemented?
Several user groups are impacted by a proposed change to their daily work flow. How should the business analyst (BA) convey these changes so that the user groups understand the impact?
A global organization is implementing a new Knowledge Management System and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?
A lead business analyst (BA) analyzed the performance of all BA's within the organization. How should the BA approach communicating the results to stakeholders?
The business analyst (BA) assigned to support a legacy system has developed a customer survey to assess its usability. Before distributing the survey, what should the BA do?
Performance measures have been collected and analyzed by a business analyst (BA) to evaluate a solution that was launched a few years ago; however, the performance measures do not indicate whether or not the solution is contributing to the desired value. What is the recommended next step?
A business analyst (BA) is tasked with designing a method of ensuring that the requirements captured during the elicitation sessions satisfy the needs and expectations of the customer experience, within an initiative. The BA identifies a way that the stakeholder requirements can be structured to ensure realization of the desired customer experience. Which viewpoint describes the approach taken by the BA to structure the requirements?
The business analyst (BA) has traced the requirements for the interaction between a customer and the new online ordering system. Besides enabling the BA to ensure quality of the requirements to stakeholders, tracing the requirements will also enable the BA to:
A senior business analyst (BA) is tasked with verifying a set of requirements written by a junior BA for a
system. During this exercise, the junior BA will ensure that the requirements exhibit atomic characteristics. The senior BA will be verifying that the requirements:
A company wants to increase transaction service offerings using its on-line channels. The existing application already has some of the required functionality. A new project has been initiated to implement the additional capabilities but the company management is unsure of the complexity of the project. What exercise must be carried out to determine the changes needed in the new application?
A business analyst (BA) worked with two stakeholders to finalize the access rights related requirements for an internal software application. According to the first stakeholder “Comments, once entered in the application, should be stored for 365 days and should not allow the users to delete”. According to the second stakeholder, “The users with super administrator privileges should be able to add/delete/modify every page/section in the entire application.” Which characteristic does this pair of requirements fail to meet?
A business analyst (BA) identifies a design option that enhances the performance of the business by automating repetitive tasks that require multiple staff touchpoints to complete a single task. Which type of improvement opportunity is identified by the BA?
An organization prefers to execute projects using an adaptive approach. However, the new project is much more complex than previously executed projects. What will the business analyst (BA) recommend?