You are working on the design of a new facility. The electrical riser of the building with high current power is located close to the area where sensitive IT equipment in the computer room will be located.
What should you recommend to reduce the amount of EMF coming from the electrical riser?
What is a potential disadvantage of using a hypoxic-based fire suppression system as a fire extinguishing system?
What is the minimum requirement for the power feeds to the building for a Rated-3 data center based on the ANSI/TIA-942 standard?
In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?
The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.
Taking energy efficiency as the highest priority, which cooling system should you recommend?
The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?
Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:
•Rated power: 30 kVA
•Rectifier input voltage: 400 V/3 phase
•Rectifier input power factor: 0.8
•Battery rated voltage: 384 V
•Number of cells: 192
•End of discharge voltage: 308 V
•Inverter output voltage: 400 V/3 phase
•Inverter output power factor: 0.8
What information is missing to perform the battery calculation?
A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).
Will the network architecture be part of this audit?
What is a potential disadvantage of using water mist as a fire extinguishing system?
The computer room has high levels of H2S gas contamination. What is the best option to resolve this issue?
The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.
To which feed will the output of the UPS be synchronized?
A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.
Are new floor loading calculations required?
The noise levels in the data center are approximately 91 dB (A).
Do employers need to take precautions?