Halloween Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

CDCS EXIN EPI Certified Data Centre Specialist Questions and Answers

Questions 4

You are working on the design of a new facility. The electrical riser of the building with high current power is located close to the area where sensitive IT equipment in the computer room will be located.

What should you recommend to reduce the amount of EMF coming from the electrical riser?

Options:

A.

Install single-phase power cabling

B.

Install three-phase power cabling based on three individual core wires

C.

Install bus bar trunking

D.

Install three-phase power cabling based on a combined cable (e.g. XLPE etc.)

Buy Now
Questions 5

What is a potential disadvantage of using a hypoxic-based fire suppression system as a fire extinguishing system?

Options:

A.

It can only be used in computer rooms which have sufficient air changes per hour.

B.

The gas containers need to be close to the hazard area.

C.

It can only be used in non-continuous occupied areas.

D.

It can only be used in computer rooms where you have sufficient positive pressure.

Buy Now
Questions 6

What is the minimum requirement for the power feeds to the building for a Rated-3 data center based on the ANSI/TIA-942 standard?

Options:

A.

Two feeds coming from two different substations, one power company is not acceptable

B.

Two feeds coming from two different substations, one power company is acceptable

C.

Two feeds entering the data center building from one substation

D.

One feed from one substation split over two separated distribution boards in separate rooms

Buy Now
Questions 7

In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?

Options:

A.

Security guards should perform regular inspections verifying the system works.

B.

The system should not be based on motion detection as the lights might suddenly switch off while staff is still at work.

C.

It is not advisable to use such a system since it will reduce the lifetime of LED lighting.

D.

At all times, the levels should allow for security cameras to function properly.

Buy Now
Questions 8

The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.

Taking energy efficiency as the highest priority, which cooling system should you recommend?

Options:

A.

Standard air conditioning units, as spares might not be readily available

B.

Any cooling system can be efficient because the outside air temperature will not influence the temperature of the air intake of the ICT equipment

C.

Waterside economizer

D.

Airside economizer

Buy Now
Questions 9

The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?

CDCS Question 9

Options:

A.

Rating - 4

B.

Rating - 3

C.

Rating - 2

D.

Rating - 1

Buy Now
Questions 10

Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:

•Rated power: 30 kVA

•Rectifier input voltage: 400 V/3 phase

•Rectifier input power factor: 0.8

•Battery rated voltage: 384 V

•Number of cells: 192

•End of discharge voltage: 308 V

•Inverter output voltage: 400 V/3 phase

•Inverter output power factor: 0.8

What information is missing to perform the battery calculation?

Options:

A.

UPS efficiency

B.

Inverter efficiency

C.

Load imbalance on the phases

D.

Available battery charging current

Buy Now
Questions 11

A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).

Will the network architecture be part of this audit?

Options:

A.

No, as concurrently maintainable only applies to electrical and mechanical (power and cooling).

B.

Yes, but only if the network administration does not comply with ANSI/TIA-606.

C.

Yes, amongst other aspects, the network architecture should be Rated-3 compliant with the requirements of ANSI/TIA-942.

D.

No, only the type of cabling used will be audited.

Buy Now
Questions 12

What is a potential disadvantage of using water mist as a fire extinguishing system?

Options:

A.

It only uses 10% of the water normally used in a water-based fire suppression, which might not be enough to suppress the fire

B.

It will rapidly increase the humidity level in the data center, which can cause a potential risk for the operation of the equipment

C.

It extracts oxygen from the air creating a potential risk for humans inside the computer room

D.

It has droplets that are too small (100-120 microns) so it can only be used for small fires

Buy Now
Questions 13

Is it allowed to make design changes during the implementation phase?

Options:

A.

No, after a design freeze no further changes are allowed.

B.

Any change is fine as long as it is within the scope of the project.

C.

Yes, but only when time to implement is not exceeded.

D.

Only when there is a strong business and/or technical justification.

Buy Now
Questions 14

The computer room has high levels of H2S gas contamination. What is the best option to resolve this issue?

Options:

A.

Vacuum the whole room using a HEPA/S-Class-based filter.

B.

Install air-scrubbers.

C.

Clean the room and racks with a damp/wet cloth.

D.

Provide more air changes per hour by adding more fresh air to the computer room.

Buy Now
Questions 15

The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.

To which feed will the output of the UPS be synchronized?

Options:

A.

The UPS will not synchronize to any of the feeds but use an internal clock to set the output voltage and frequency

B.

Depends on the setting of the UPS, as the UPS can normally be set to either feed

C.

Feed A

D.

Feed B

Buy Now
Questions 16

A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.

Are new floor loading calculations required?

Options:

A.

No, as long as the equipment is less than 700 kg/1,500 lbs it will be within the limits.

B.

No, specifications of equipment brought into the data center will already be known during the design of the data center, and therefore the floor will be able to handle it.

C.

Yes, additional floor loading calculations need to be done by the floor manager, which should be verified by the safety engineer.

D.

Yes, a structural engineer, approved/endorsed by the building owner, should carry out new floor loading calculations.

Buy Now
Questions 17

The noise levels in the data center are approximately 91 dB (A).

Do employers need to take precautions?

Options:

A.

No, anything less than 100 dB (A) is acceptable.

B.

There are no regulations regarding noise levels inside a building. Regulations only apply to noise pollution outside of the building.

C.

As long as the data is compliant to ISO/IEC 27001 it is acceptable.

D.

Yes, since it is mandated by regulations.

Buy Now
Questions 18

What indicates the breaking capacity of a fuse or breaker?

Options:

A.

Mechanical strength of the casing of a fuse or breaker.

B.

The maximum voltage, in case of an electrical surge, that the fuse or breaker can handle without being destroyed or causing an electric damaging arc.

C.

The current at which the device will trip.

D.

The current that a fuse or breaker is able to interrupt without being destroyed or causing an electric damaging arc.

Buy Now
Exam Code: CDCS
Exam Name: EXIN EPI Certified Data Centre Specialist
Last Update: Oct 9, 2024
Questions: 60

PDF + Testing Engine

$58.1  $165.99

Testing Engine

$40.25  $114.99
buy now CDCS testing engine

PDF (Q&A)

$36.75  $104.99
buy now CDCS pdf