Special Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

CEM Certified Energy Manager (CEM) Questions and Answers

Questions 4

How much energy (kJ) is required to heat 2 kg of water from 25°C to 2 kg of water at 100°C? (The specific heat of water (C) is 4.2 kJ/kg-°C. Assume no system losses.)

Options:

A.

420 kJ

B.

510 kJ

C.

630 kJ

D.

840 kJ

Buy Now
Questions 5

Which of the following color temperatures looks more like daylight?

Options:

A.

2,500 K

B.

3,500 K

C.

4,500 K

D.

6,500 K

Buy Now
Questions 6

Which of the advantages listed below, makes an ice TES system more preferred over a water TES system, when a load shifting strategy is considered?

Options:

A.

Ice-storage systems operate with a higher coefficient of performance (COP)

B.

Ice-storage systems require smaller storage tanks since ice has a higher energy storage density

C.

Water-storage systems require smaller storage tanks since water has a higher density than ice

D.

Ice-storage systems require lower maintenance due to lower pumping volume

Buy Now
Questions 7

Calculate the monthly electric bill for a customer that used 400 kW and 75,000 kwh during one month. Use the following declining block structure for a monthly bill:

CEM Question 7

SELECT THE CORRECT ANSWER

Options:

A.

$3,280

B.

$4, 580

C.

$7,850

D.

$9,660

E.

$12,500

Buy Now
Questions 8

What does a manometer measure?

Options:

A.

Pressure

B.

Volume

C.

Distance

D.

Voltage

Buy Now
Questions 9

In a warehouse, lights are mounted 4 meters above the floor. This provides an average light level of 150 lux. To increase the light level without installing more lights or higher Wattage lights, you lower the light fixtures with pendants so that the lights are located 3.25 meters above the floor. Calculate the new average light level on the floor.

Options:

A.

150 lux

B.

166 lux

C.

176 lux

D.

227 lux

E.

276 lux

Buy Now
Questions 10

Which pump system listed below is most likely the best application for converting to variable-speed drive?

Options:

A.

Pump system with parallel rotary lobe pumps in a rebar quenching application with a static head of 80m

B.

Pump system with on-off control transferring liquid vertically from a low tank to a higher tank

C.

Pump system with bypass control transferring liquid from an intake dam to a process in production

D.

Pump system with throttle fully open circulating liquid in a closed loop cooling system

Buy Now
Questions 11

What is the main cause of low power factor?

Options:

A.

Harmonics

B.

Fluorescent lighting

C.

Solar flares

D.

Computers and electronic equipment

E.

Low-load induction motors

Buy Now
Questions 12

An outdoor parking area has 25 light poles. Each pole has a 420 Watt (ballast included) high-pressure sodium (HPS) luminaire. The parking area lights are illuminated 4,500 hours per year and the electricity cost is $0.08/kWh. What is the annual energy cost reduction if each luminaire is replaced with a 220-Watt (driver included) LED luminaire?

Options:

A.

$1,200/yr

B.

$1,500/yr

C.

$1,800/yr

D.

$2,200/yr

E.

$2,600/yr

Buy Now
Questions 13

What is a common cause of poor power quality?

Options:

A.

Natural gas turbine power generation by utilities

B.

Electronic equipment, such as personal computers

C.

Incandescent lighting

D.

Synchronous motors

E.

Partially loaded induction motors

Buy Now
Questions 14

A new lighting system costs $60,000. The new lighting system has a 15-year life and the minimum required rate of return (MARR) is 15%. How much must the new lighting system save to be life-cycle cost effective?

Options:

A.

$10,260/year

B.

$12,556/year

C.

$15,650/year

D.

$27,090/year

E.

$33,200/year

Buy Now
Questions 15

You are using a performance contract to finance the added cost of using more-efficient equipment in the construction of a new building. Which of the following International Performance Measurement and Verification Protocol (IPMVP) options would you use to verify annual energy savings?

Options:

A.

Option A - Retrofit isolation: key parameter measurement

B.

Option B - Retrofit isolation: all parameter measurement

C.

Option C - Whole facility measurement

D.

Option D - Calibrated simulation

E.

Option E - Stipulated savings

Buy Now
Questions 16

Which of the following statements best describe Demand Control Ventilation (DVC) in Building Automation Systems?

Options:

A.

It satisfies indoor ventilation rates by preconditioning outdoor air with the exhaust air to decrease energy cost during cold, warm, or humid weather

B.

It's a prescriptive procedure in which outdoor air intake rates are calculated based on the energy cost method that compares a proposed building design to a base annual energy cost design

C.

It's a building standard for enclosed spaces in which biological, chemical, and physical contaminants are considered to meet thermal comfort requirements

D.

It's an active evaluation of outdoor and indoor space conditions to determine the amount of thermal, mechanical and natural conditioning that is required

Buy Now
Questions 17

A 25-kW motor, at full load, drives a centrifugal fan that produces 160,000 liters per second (l/s) of ventilation air. If the fan speed is reduced to a flow rate of 150,000 l/s, what is the new load on the motor?

Options:

A.

15.2 kW

B.

20.6 kW

C.

24.2 kW

D.

25.0 kW

E.

30.3 kW

Buy Now
Questions 18

In general, which of the following is the least expensive and easiest way to finance an energy project?

Options:

A.

Equity

B.

Debt

C.

Performance contract

Buy Now
Questions 19

An energy-saving project saves $30,000 per year. The project life is 10 years and the company minimum annual rate of return (MARR) is 15%. How much can the project cost and still be cost effective?

Options:

A.

$150,570

B.

$165,903

C.

$188,343

D.

$198,992

E.

$201,123

Buy Now
Questions 20

A compressed air system has a total volume of 247,500 liters. During a 30-minute break in production (air compressor system turned off and no production demand for compressed air), the system pressure drops from 7 bar, gauge (700 kPa, gauge) to 5 bar, gauge (500 kPa, gauge). Calculate the leakage rate in the compressed air system.

Options:

A.

8,250 liters/minute

B.

16,500 liters/minute

C.

22,750 liters/minute

D.

32,000 liters/minute

E.

48,250 liters/minute

Buy Now
Questions 21

A facility replaces a natural gas heating system rated at 10,000 kJ/h and 80% efficiency with an electric heat pump rated at 10,000 kJ/h and a coefficient of performance (COP) of 2.3. Will this project also reduce the annual energy utilization index (EUI) for the facility?

Options:

A.

Yes

B.

No

Buy Now
Questions 22

Which of the following is NOT a typical benefit of performance contracting from the building owner's perspective?

Options:

A.

Performance contracting is a simple and quick process

B.

Net cash flow can be neutral or positive for the owner

C.

The energy-service company can have a financial incentive to achieve projected savings

D.

Maintenance services provided by the performance contractor can add value to the overall savings achieved

E.

Performance contracting can provide access to external financing when the owner may not have sufficient equity for in-house financing for large projects

Buy Now
Questions 23

An energy-saving project costs $540,000. The project will have maintenance costs of $25,000 per year. The energy savings from the project are $160,000 per year. The project has a life of 10 years with no salvage value. The minimum attractive rate of return (MARR) is 10%. Using end-of-year cash flows, calculate the net-present value (NPV) of the project.

Options:

A.

$154,657

B.

$289,575

C.

$311,556

D.

$456,254

Buy Now
Questions 24

Which of the following is/are benefits of commissioning?

Options:

A.

Ensures a system is designed to operate as intended

B.

Ensures a system is installed to operate as intended

C.

Ensures staff know how to operate a system as intended

D.

Ensures staff know how to maintain a system as intended

E.

All of the above

Buy Now
Questions 25

Lighting systems operate with a certain recoverable light loss factor. Control systems with photocell sensor inputs combined with dimming ballasts can be used to regulate dimming levels to maintain a continuous light level in the work space. Which of the following best describes this type of control?

Options:

A.

Closed-loop controller

B.

Open-loop controller

C.

Demand-limiting controller

D.

Two-position controller

Buy Now
Questions 26

If installed without ancillary equipment, photovoltaic power cells generate what type of power?

Options:

A.

Sinusoidal alternating current

B.

Square-wave alternating current

C.

Direct current

Buy Now
Questions 27

A 7 bar (gauge pressure) compressed air system has 5 leaks that are 3 mm in diameter and 3 leaks that are 6 mm in diameter. The compressed-air system is pressurized 8,760 hours per year. Electricity cost is $0.10/kWh. What is the annual cost of the leaks in the compressed air system?

Options:

A.

$18,150/yr

B.

$25,220/yr

C.

$30,910/yr

D.

$48,480/yr

E.

$56,500/yr

Buy Now
Questions 28

If the initial design process includes group relamping, how can this reduce the number of lamps required to illuminate a space?

Options:

A.

Group relamping reduces factors that contribute to light loss, which means fewer lamps are required to illuminate a space

B.

Group relamping reduces the overall amount of lamp breakages, which means fewer lamps are required to illuminate a space.

C.

Group relamping requires using larger Wattage lamps, which means fewer lamps are required to illuminate a space

D.

Group relamping improves the room cavity ratio, which means fewer lamps are required to illuminate a space

E.

Group relamping cannot reduce the number of lamps required to illuminate a space

Buy Now
Questions 29

An energy-saving project costs $540,000. The project will have maintenance costs of $25,000 per year. The energy savings from the project are $160,000 per year. What is the simple payback of the project?

Options:

A.

2.0 years

B.

3.0 years

C.

4.0 years

D.

5.0 years

Buy Now
Questions 30

The set point for the chiller supply water temperature is varied as a function of the thermal demand for space cooling. What do you call this control strategy?

Options:

A.

Chilled-water temperature reset

B.

Condenser-water temperature reset

C.

Night setback

D.

Reheat coil reset

Buy Now
Questions 31

A fully-loaded heat pump unit delivers 36-kW thermal heating with a power draw of 12-kW electric. What is the coefficient of performance (COP) at full load?

Options:

A.

2.0

B.

3.0

C.

4.0

D.

5.0

E.

6.0

Buy Now
Questions 32

Which type of single-phase alternating-current motor has the highest efficiency?

Options:

A.

Electronic-commutated motor

B.

Shaded-pole motor

C.

Permanent split-capacitor motor

Buy Now
Questions 33

What is a common method to reduce the impact of voltage imbalance?

Options:

A.

Rebalance single-phase loads

B.

Install harmonic filters

C.

Install capacitors to improve power factor on three-phase loads

D.

Reverse phase connections on three-phase motors

Buy Now
Questions 34

How can you tell if steam traps in a steam distribution system may NOT be working correctly?

Options:

A.

Robust flash steam rising from condensate receiver tank vent pipes

B.

An increase in make-up water requirements relative to steam demand

C.

Rapid chattering of disk steam traps

D.

No sound from inverted bucket steam traps

E.

All of the above

Buy Now
Questions 35

An air-conditioning system at full load is rated at 70-kW (thermal cooling) and has a coefficient of performance (COP) of 4.1. What is the electrical load at full load?

Options:

A.

17.1 kW

B.

23.3 kW

C.

35.0 kW

D.

46.7 kW

E.

70.0 kW

Buy Now
Questions 36

When comparing two similar facilities, you see that the facility with newer, higher-efficiency equipment has a higher energy-use index [EUI] (kJ/m²-yr). What might be the cause?

Options:

A.

The facility with the higher EUI is in need of commissioning

B.

The facility with the lower EUI is in need of commissioning

C.

The facility with the lower EUI requires a performance contract

D.

The facility with the higher efficiency equipment should have a higher EUI

E.

The facility with the higher EUI requires a supervisory control and data acquisition (SCADA) system

Buy Now
Questions 37

What type of passive heat exchanger can wrap around an evaporator coil to precool entering air and reheat the air after the cooling coil without adding more moisture to the supply air stream?

Options:

A.

Desiccant heat wheel

B.

Plate and frame

C.

Heat pump

D.

Heat pipe

E.

Run-around coil

Buy Now
Questions 38

Which of the following is NOT a renewable-energy resource?

SELECT THE CORRECT ANSWER

Options:

A.

Saw grass

B.

Shale gas

C.

Geothermal heat

D.

Ocean waves

E.

Crop residue

Buy Now
Questions 39

Which of the following best describes a dead band in controls?

Options:

A.

A range around a set point with no change in state even though there is a change in sensor input

B.

A system which changes the output of a controller based on how fast a variable is moving from or to a set point

C.

The delay in response of a system to a controlled change

D.

A value that has been assigned to a controlled variable

E.

The difference between a sensor variable and its set point

Buy Now
Exam Code: CEM
Exam Name: Certified Energy Manager (CEM)
Last Update: Apr 2, 2025
Questions: 130

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now CEM testing engine

PDF (Q&A)

$36.75  $104.99
buy now CEM pdf