Questions 4

What steps should be taken to create a risk assessment and risk plan?

Options:

A.

Identify the risks. Determine the probability and severity of each risk. Develop contingencyplans to ameliorate each risk.

B.

Communicate the risks to stakeholders. Request additional funds to cover contingencies on the most important risks.

C.

Add additional days to activity durations to build in a cushion. Identify areas in the project that can be cut out, if necessary.

D.

Utilize project tools. PERT or Gantt charts, work breakdown structures to identify risk, track issues, and mitigation risks.

Buy Now
Questions 5

What is the best option to speed up the mail delivery process?

Options:

A.

Decrease mailroom staff and begin sorting and delivering mail every other business day.

B.

Keep current mailroom staff and change the mail code process to designate floors and provide employees mail slots.

C.

Increase mailroom staff to help speed up mail sorting and delivery.

D.

Keep current mailroom staff levels but implement overtime to speed up sorting and delivery.

Buy Now
Questions 6

What series of ISO standards defines the requirements of an environmental management system that can be used by the organization to measure and document the organization's environmental impact?

Options:

A.

ISO 14001

B.

ISO 14021

C.

ISO 14025

D.

ISO 14024

Buy Now
Questions 7

The building automation systems (BAS) experienced a power loss. The systems are now back online and are accessible by remote monitoring controls. From a remote login, you observe that the indoor air temperatures are warmer than the settings. What should you do?

Options:

A.

Lower the temperature set points to cool down the building faster.

B.

Call an onsite occupant to verify the office space temperatures.

C.

Dispatch staff to physically check all equipment for proper operations.

D.

Recommend to the owner to install a generator to minimize the impact of future outages.

Buy Now
Questions 8

What is a facilities register?

Options:

A.

A list of accounts representing the contracted services for a facility.

B.

A comprehensive list of the organization’s facility assets, including buildings, grounds, and infrastructure.

C.

An integrated work management system utilized in a facility to track preventative and on-demand work orders.

D.

A master list of emergency contacts for use in business continuity/emergency purposes.

Buy Now
Questions 9

An organization is considering relocating from leased building #1 into leased building #2. Leased building #1 is 55,000 sq. ft. costing $1,100,000 annually. Leased building #2 is 50,000 sq. ft. costing $1,100,000 annually. Building #1 can house 500 people and building #2 can house 580 people. The company's benchmark is $2,000.00 per person per year for leased space. What is the MOST important reason to know what the company's benchmarks are?

Options:

A.

It allows other organizations to measure against your results.

B.

It structures your recommendations in a method your managers require.

C.

It provides a quantitative measure to support your recommendations and decisions.

D.

It simplifies the budgeting process.

Buy Now
Questions 10

When referring to the off-gassing of materials used within a building, what does the acronym 'VOC' stand for?

Options:

A.

Versatile ongoing commissioning.

B.

Volatile organic compounds.

C.

Voracious odor composites.

D.

Variable offensive chemistry.

Buy Now
Questions 11

What is one of the perspectives used by an organization when developing a balanced scorecard?

Options:

A.

Financial

B.

Management style

C.

Market trends

D.

Real Estate strategic plan

Buy Now
Questions 12

What sustainability benefits can be attributed to the use of a fully implemented Geographic Information System (GIS)?

Options:

A.

Greenhouse Gas Reduction and Water Runoff

B.

Greenhouse Gas Reductions and Energy Conservation

C.

Water Runoff and Composting

D.

Water Runoff and Energy Conservation

Buy Now
Questions 13

You are tasked with building four conference rooms with standard conference features. The project scope and schedule are clearly defined. To minimize risk to the organization, what type of contract should be used to procure the needed services?

Options:

A.

Cost-Plus-Fee Contract

B.

Cost-Reimbursable Contract

C.

Fixed-Price Contract

D.

Time and Material Contract

Buy Now
Questions 14

What measures could you have taken to ensure your staff member focused on measurable priorities that you had established?

Options:

A.

You should have made it clear when hiring your Project Coordinator that it was his responsibility to ensure his projects were completed in a quality manner.

B.

The Project Coordinator should have set up regular appointments with you to demonstrate how he was completing his tasks according to the performance measures that he established.

C.

You should have hired a very experienced Project Coordinator to ensure that your priorities were met.

D.

You should have met with your Project Coordinator regularly to prioritize work, review assigned projects, and report on performance.

Buy Now
Questions 15

What are the environmental factors a facilities manager must consider before starting any renovation project to a circa-1960's manufacturing facility?

Options:

A.

Ensure that a licensed architect has reviewed plans and approved remodeling plans.

B.

Contract with a salvage company to remove questionable building materials.

C.

Precautions must be taken to ensure any hazardous materials are accounted for.

D.

Review water and sewer samples for contaminants to ensure code compliance.

Buy Now
Questions 16

To satisfy the needs of one of its largest customers, your company is opening a new facility about 1240 miles/2000 kilometers away from the corporate offices. Initially, the new operation will only support one customer. However, the company expects more customers will be added in the next three to five years. The plan is that the corporate office will support operations in the new facility. What is the best way to manage the facility requirements of this new operation?

Options:

A.

Use a temporary agency for facility services and manage everything from the corporate office.

B.

Hire a permanent staff of facility employees for the new operation.

C.

Contract with an outsource company to provide facility management services for the new operation.

D.

Relocate some existing facility employees to the new operation.

Buy Now
Questions 17

What is the FIRST priority when allocating facility management resources?

Options:

A.

Urgency

B.

Dollar value

C.

Customer satisfaction

D.

Criticality

Buy Now
Questions 18

When managing quality, what are Key Performance Indicators (KPIs) based on?

Options:

A.

What stakeholders feel is important

B.

What the facility manager feels is important

C.

What the facility management team feels is important

D.

What the CEO feels is important

Buy Now
Questions 19

What safety precautions are MOST important during a partial renovation of a building while keeping the existing business operating?

Options:

A.

Require the contractor to perform indoor air quality testing once a month to ensure staff safety and post results.

B.

Hearing protection and eye wash stations should be set up in designated locations within the construction area to minimize employee risk.

C.

Barriers must be set up to create a safe perimeter: all staff members should be moved outside of the area and it should be designated as an area where personal protective equipment must be worn.

D.

Staff should be required to wear safety footwear, hard hats, and a security checkpoint should be set up to ensure staff compliance.

Buy Now
Questions 20

How should the facility manager ensure the gym meets staff expectations?

Options:

A.

Solicit staff asking for suggestions on how to improve the gym.

B.

Poll in the industry and ask them how best to create and maintain a gym facility for staff use.

C.

Have the facility manager perform the monthly inspections.

D.

Hire a consultant to provide you with information regarding trends to keep a gym current.

Buy Now
Questions 21

How can the building information model (BIM) be used for emergency preparedness?

Options:

A.

It provides first responders with the names of all building occupants.

B.

It is not useful for emergency preparedness.

C.

It creates a virtual environment of the building for emergency personnel.

D.

It can help predict how an emergency will unfold.

Buy Now
Questions 22

Some new carpets can emit volatile organic compounds (VOCs) that can adversely affect occupants.

How can the facility manager avoid this problem when purchasing new carpeting?

Options:

A.

Research emissions data from carpet manufacturers.

B.

Increase the air flow in the space.

C.

Allow at least one month for off-gassing before occupancy.

D.

Treat carpeting during install.

Buy Now
Questions 23

During a large real estate project, what are the expenses of planning, design, construction, operation, maintenance, and disposition of a structure over time known as?

Options:

A.

Life-cycle costing.

B.

Investment analysis.

C.

Time value of money.

D.

Project classification.

Buy Now
Questions 24

What do as-built drawings document?

Options:

A.

Construction drawing bid set.

B.

Architectural drawings after design development.

C.

Field conditions after construction.

D.

Space program prior to design development.

Buy Now
Questions 25

In relation to establishing a level of acceptable risk, what should you include in your Business Continuity Plan (BCP) to help measure the plan's expected level of success against that level of risk?

Options:

A.

Contracted support

B.

Lessons learned

C.

Business analysis

D.

Performance metrics

Buy Now
Questions 26

You are a Facility Manager overseeing a proposed renovation of a floor to meet the needs of the business. What step should be taken first?

Options:

A.

Conduct space programming analysis.

B.

Perform a gap analysis.

C.

Engage an architect for scenario alternatives.

D.

Undergo a feasibility study.

Buy Now
Questions 27

What is the BEST term to indicate an asset can suffer a failure and yet still continue operations?

Options:

A.

Recoverable

B.

Continuity

C.

Dependable

D.

Resilience

Buy Now
Questions 28

What describes a facility condition assessment?

Options:

A.

A report detailing the sustainability goals of an organization

B.

A five to ten-year facility plan incorporating owned and leased space

C.

An inspection and analysis of energy flows in a building with the objective of understanding energy efficiency

D.

A report of the current state of a building and component systems

Buy Now
Questions 29

What factors are included in the SMART approach to developing key performance indicators?

Options:

A.

Systematic, measurable, achievable, reliable, time-bound.

B.

Specific, measurable, achievable, rational, time-bound.

C.

Specific, measurable, achievable, relevant, time-bound.

D.

Systematic, measurable, achievable, related, time-bound.

Buy Now
Questions 30

A company has decided to establish a long-range strategic facility technology plan. What is the first step in determining the future technology needs of the company?

Options:

A.

Determine the level of employee technological skill requirements for the future.

B.

Review corporate plans for building renovations and lease negotiations.

C.

Research advances in technology.

D.

Conduct an assessment of existing technology.

Buy Now
Questions 31

Your company has been successful in obtaining business with a new client that has stores in malls and on campuses. You will be responsible for contracting and managing third-party services formerly managed by your new client's onsite managers at multiple retail locations. Your client has asked that, to the best of your ability, you retain current contractors and, more importantly, their staff members. The agreement between your company and the client requires that you reduce the client's expense for the contracted services by 6%. Who are the stakeholders in your newly obtained client?

Options:

A.

Other companies in the malls and campuses where your client has stores

B.

Client customers, internal stakeholders, indirect stakeholders, and service providers and partners

C.

Client staff and visitors at each store

D.

Managers within your company who manage comparable client services

Buy Now
Questions 32

What does the effectiveness of infrastructure resilience rely on?

Options:

A.

Finance, security, supply chain, communications.

B.

Robustness, resourcefulness, rapid recovery, redundancy.

C.

Back-up power, capital planning, supply chain, security.

D.

Written incident response plans, training, management participation, employee adaptability.

Buy Now
Questions 33

What does NOT contribute to your company's overall carbon footprint?

Options:

A.

Amount of kWh consumed by your facility

B.

Amount of solar energy generated by your facility

C.

Amount of fossil fuels consumed by your facility

D.

Amount of stormwater runoff created by your facility

Buy Now
Questions 34

What is the PRIMARY purpose of the Incident Command System (ICS)?

Options:

A.

Respond to large incidents.

B.

Avoid duplication of efforts in any incident.

C.

Effectively respond to any incident.

D.

Meet the needs of large operational staff.

Buy Now
Questions 35

What is the definition of "real property"?

Options:

A.

Things located within buildings such as furniture, accessories, appliances, etc.

B.

Property that has nothing artificial on it, only natural materials.

C.

Land, buildings, and machinery or equipment.

D.

Inventory and loose materials.

Buy Now
Questions 36

In planning your operating budget for the next fiscal year, what should NOT be included?

Options:

A.

Quarterly belt and filter changes

B.

Preventive maintenance during annual shutdown

C.

Electrical utility costs

D.

Allowance to overhaul the system’s motors that will soon be inoperative

Buy Now
Questions 37

You are planning a landscaping project in a densely populated area. What considerations are needed for the community outside your property?

Options:

A.

Choose alternative energy sources to power outdoor lighting and security stations, decrease costs to your facility, and provide energy back to the grid, which will bring energy costs down to the neighboring community.

B.

Ensure that lights and basic security sounds (e.g., beeping noises at an outdoor security station) are not intrusive on daily living, but that they may also be used to alert the neighborhood, when such alerts are appropriate and of value (e.g., in an emergency).

C.

Use the brightest possible lights and loudest sounds (e.g., sirens) to prevent security issues at night to support the community in decreasing crime in that area and announcing emergency situations.

D.

Provide security staff to walk the perimeter of your property, checking for damaged lights or other security issues while maintaining communication with a dispatcher for emergencies while keeping a low profile in the neighboring community.

Buy Now
Questions 38

Which task should occur during the first phase of sustainable plan development?

Options:

A.

Assign members to assist with developing a business case

B.

Review preliminary business cases

C.

Define what criteria will be used to consider and evaluate ideas

D.

Develop cash flow

Buy Now
Questions 39

What is the MOST effective tool in managing change?

Options:

A.

Managing resistance.

B.

Anticipating user denial.

C.

Using surveys.

D.

Communication.

Buy Now
Questions 40

Your company operates a Web-based CMMS but struggles with service quality across its facilities. What is the best way to address the issue?

Options:

A.

Select one facility for improvement and use this as the benchmark for all the other facilities.

B.

Use the CMMS data to identify those service delivery processes that need improvement.

C.

Retrain service delivery staff on the efficient use of the CMMS.

D.

Have each facility manager identify performance improvement initiatives for their respective facilities.

Buy Now
Questions 41

What is the most common method to accelerate the completion of a project?

Options:

A.

Outsourcing project work

B.

Reducing scope

C.

Adding resources

D.

Scheduling overtime

Buy Now
Questions 42

What is one of the MOST common reasons implementing a Computerized Maintenance Management System (CMMS) fails?

Options:

A.

Users are resistant to change.

B.

The board members are not interested in the system.

C.

The CMMS is home-grown.

D.

The building systems are not compatible with the CMMS.

Buy Now
Questions 43

What is the information gained from a risk assessment, business impact analysis, and a resource needs assessment used for?

Options:

A.

Business workflow plans.

B.

Property inspection and insurance assessments.

C.

Continuity and recovery plans.

D.

Risk management analyses.

Buy Now
Questions 44

Which problem should you address to convey the corporate value of “community pride" to the general public?

Options:

A.

The building does not have automated control systems to increase energy efficiency.

B.

The building does not have on-site overnight on-duty security guard services.

C.

The building manager's office has worn and outdated furnishings.

D.

The exterior perimeter wall has peeling and weathered paint.

Buy Now
Questions 45

What are the four methods a project manager should use to prove project requirements are met?

Options:

A.

Planning, specifying, negotiating, and payment

B.

Testing, analysis, inspection, and interpolation

C.

Interviewing, observing, inspecting, and reporting

D.

Analysis, reporting, measurement, and permit sign-off

Buy Now
Questions 46

What should the FM department do in the ongoing monitoring of a newly outsourced Property Management contract?

Options:

A.

Explain the evaluation methodology based on the identified Key Performance Indicators.

B.

Include opportunity for the Contractor to respond to non-compliances.

C.

Ensure that all codes and regulations are met.

D.

Create an incentive program for innovative work.

Buy Now
Questions 47

You manage a design-build project to renovate a new office space, including infrastructure upgrades. At the 60% design phase, the design-build contractor’s project estimate is over budget and contingency. What should be done first to address the issue?

Options:

A.

Investigate delaying a portion of the project until additional funding is available.

B.

Pursue a change order from the project sponsor for the difference.

C.

Remove the infrastructure upgrade items from the project scope.

D.

Investigate the reasons for being over budget.

Buy Now
Questions 48

You provide integrated facility services for a client with a single site, including janitorial services. The client’s site has been granted LEED certification, including points for implementing a green cleaning policy. What should you do to meet the client's need for a green cleaning policy?

Options:

A.

Contact professional organizations in the janitorial industry and Facility Managers at other LEED-certified sites for their recommendations.

B.

Review professional journals, identify green cleaning solutions, and prepare a policy and procedures based on those solutions.

C.

Review LEED standards applicable to the site, identify compliant equipment and supplies, and prepare a policy and procedures based on those standards.

D.

Meet with equipment and supplies vendors specializing in green cleaning and obtain their recommendations.

Buy Now
Questions 49

What is the BEST strategy to reduce waste in an organization?

Options:

A.

Reuse.

B.

Prevention.

C.

Recycling.

D.

Composting.

Buy Now
Questions 50

You work for a facilities management service provider that wants to improve its service delivery processes and has decided to analyze its performance data. What advice would you offer regarding the data analysis exercise?

Options:

A.

Have an independent consultant analyze the data.

B.

Only analyze data that relates to subpar performance.

C.

Only analyze data that is less than twelve months old.

D.

Use the data that is valid and relevant.

Buy Now
Questions 51

What is the most important factor to consider when upgrading the Building Management System(BMS)?

Options:

A.

The provider indicates the software version is obsolete

B.

Requirement to automate FM tasks

C.

An upgraded version is now available from the manufacturer

D.

Additional metrics are required for management reporting

Buy Now
Exam Code: CFM
Exam Name: Certified Facility Manager
Last Update: Feb 12, 2025
Questions: 180

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now CFM testing engine

PDF (Q&A)

$36.75  $104.99
buy now CFM pdf