Questions 4

Exhibit.

CFPE Question 4

The automatic fire sprinkler system remote area located on planF2.0 indicates that the fire sprinkler system has been designed to deliver

Options:

A.

20 gpm ( 76 L/mm) over 2 000 tt2 (186 m2)

B.

15 gpm ( 57 L/min) over 1 500 ft2 (139 m2)

C.

10 gpm ( 38 L/min) over 1 500 tt2 (139 m2)

D.

20 gpm ( 76 L/min) over 1 500 ft2 (139 m2)

Buy Now
Questions 5

How many fire hydrants are located on the project site on plan L2?

Options:

A.

Zero

B.

One

C.

Two

D.

Three

Buy Now
Questions 6

What is the minimum fire resistance rating for the enclosure of a floor opening in a new six-story building?

Options:

A.

1-hour

B.

2-hours

C.

3-hours

D.

4-hours

Buy Now
Questions 7

What is the minimum door opening width in a means of egress?

Options:

A.

28 in (711 mm)

B.

30 in (762 mm)

C.

32 in (810 mm)

D.

34 in (864 mm)

Buy Now
Questions 8

When does a new model code take effect within a jurisdiction?

Options:

A.

When it is adopted into law by a jurisdiction

B.

When it is voted into law by the people of a jurisdiction

C.

When it is published by the code-making body

D.

When it is approved by the voting members of the code-making body

Buy Now
Questions 9

Exhibit.

CFPE Question 9

What is the construction type specified for the new addition for plan set Tl?

Options:

A.

Type II (111

B.

Type II (000)

C.

Type (211)

D.

Type III (200)

Buy Now
Questions 10

The symbol above is a representation of which one of the following?

Options:

A.

Fire hydrant

B.

Riser

C.

Floor dram

D.

Utility meter

Buy Now
Questions 11

What is the classification for an area in a building with a permanent multi-level play structure?

Options:

A.

Special amusement

B.

Educational

C.

Class C mercantile

D.

Multipurpose assembly

Buy Now
Questions 12

On plan F0.1 the hydraulic calculations for the design were based on which of the following minimum flow criteria''

Options:

A.

740 gpm (2,800 lpm)

B.

840 gpm (3,180 lpm)

C.

1,040 gpm (3,937 ipm)

D.

1,500 gpm (5,6781pm)

Buy Now
Questions 13

Exhibit.

CFPE Question 13

CFPE Question 13

A code is generally considered as a document on what must be done, whereas a standard describes

Options:

A.

in less specificity what is required.

B.

the enforcing agencies requirements

C.

the goals and objectives ofa requirement

D.

in specific detail how it is to be done

Buy Now
Questions 14

Which one of the following is NOT a typical reason to require construction permits and the review of plans by local government?

Options:

A.

Community safety

B.

General traffic safety

C.

Emergency responder safety

D.

Property conservation

Buy Now
Questions 15

Exhibit.

CFPE Question 15

What is the occupancy classification of the conference rooms in the figure if they are used for meetings of less than 50 people?

Options:

A.

Assembly

B.

Business

C.

Mercantile

D.

Educational

Buy Now
Questions 16

Exhibit.

CFPE Question 16

CFPE Question 16

CFPE Question 16

Assuming all 6 classrooms m Wing C on plan A7 are the same size, what is their maximum occupant load?

Options:

A.

69 occupants

B.

138 occupants

C.

346 occupants

D.

460 occupants

Buy Now
Questions 17

A board of appeals is classified as what type of legal proceeding?

Options:

A.

Judicial

B.

Non-judicial

C.

Criminal

D.

Administrative

Buy Now
Questions 18

Exhibit.

CFPE Question 18

For the included figure, which dimension is the tread depth?

Options:

A.

A

B.

B

C.

C

D.

A+B

Buy Now
Questions 19

Exhibit.

CFPE Question 19

CFPE Question 19

What is the approximate maximum available water indicated on supply graph 2 on plan F0.2?

Options:

A.

980 gpm (3,709 Ipm)

B.

1,680 gpm (6,359 Ipm)

C.

1.980gpm (7,495 Ipm)

D.

3,980gpm(15,066lpm)

Buy Now
Questions 20

What is the minimum fire flow duration for a 21.000 ft2 (1.950 m2) building of type II (000) construction?

Options:

A.

1 hour

B.

2 hours

C.

3 hours

D.

4 hours

Buy Now
Questions 21

Exhibit.

CFPE Question 21

On plan A7, what is the corridor floor finish for the first floor plan wing C?

Options:

A.

Parinted concrete

B.

Ceramic tile

C.

NewVCT

D.

Carpel

Buy Now
Questions 22

Which of the following is an architectural drawing that shows the overall project layout of building areas, driveways, fences, fire hydrants, and landscape features?

Options:

A.

Landscape plan

B.

Construction plan

C.

Site plan

D.

Plot plan

Buy Now
Questions 23

Where field conditions necessitate a substantial change in the approved plans,

Options:

A.

revised drawings may be required by the AHJ.

B.

no action is necessary on the part of the applicant.

C.

revised drawings must be submitted to the applicant.

D.

no action is necessary on the part of the AHJ.

Buy Now
Questions 24

New manual fire alarm boxes must be within what distance from the door?

Options:

A.

60 in (1,524 mm)

B.

72 in (1,829 mm)

C.

34 in (2,133 mm)

D.

96 in (2,438 mm)

Buy Now
Questions 25

What is the occupancy classification of a restaurant, if it has an occupant load greater than 50 people?

Options:

A.

Business

B.

Kitchen

C.

Mercantile

D.

Assembly

Buy Now
Questions 26

Fire department access roads shall extend to within what distance of a single exterior door providing access to the interior of a building?

Options:

A.

20 ft (6 m)

B.

30 ft (9 m)

C.

40 ft (12 m)

D.

50 ft (15 m)

Buy Now
Questions 27

Exhibit.

CFPE Question 27

On plan C1 what is the widthof the fire department access driveway on the south facing side of the building wing closes! lo Bedford Street?

Options:

A.

16 ft (4.9 m)

B.

18 ft (5.5 m)

C.

20 ft (6.1 m)

D.

24 ft (7.3 m)

Buy Now
Questions 28

Exhibit.

CFPE Question 28

Using scale C, on the water supply graph 3 found on plan F0.2, what is the residual pressure availableflowing at 1 000 gpm (3,785 Lpm)?

Options:

A.

15 psi (1 bar)

B.

42 psi (2.9 bar>

C.

62 psi (4.2 ban

D.

75 psi (5.1 bar)

Buy Now
Questions 29

On plan set A5 what does the number 19 in the box within kindergarten #3 pertain to?

Options:

A.

Floor

B.

Base

C.

Walls

D.

Callings

Buy Now
Questions 30

What is the maximum common path of travel permitted in a sprinklered educational occupancy?

Options:

A.

20 ft (6 m)

B.

75 ft (23 m)

C.

100 ft (30 m)

D.

200 ft (61 m)

Buy Now
Exam Code: CFPE
Exam Name: Certified Fire Plan Examiner (CFPE)Exam
Last Update: Oct 21, 2024
Questions: 100

PDF + Testing Engine

$48  $159.99

Testing Engine

$36  $119.99
buy now CFPE testing engine

PDF (Q&A)

$30  $99.99
buy now CFPE pdf