CIS-SPM Certified Implementation Specialist - Strategic Portfolio Management Questions and Answers

Questions 4

What is the formula for Committed Utilization?

Options:

A.

Assigned Hours/Capacity

B.

(Allocated Hours + Confirmed Hours)/Capacity

C.

Confirmed Hours/Capacity

D.

Allocated Hours/Capacity

Buy Now
Questions 5

When creating a planning item, which fields are populated automatically with the Approved start date value and the Approved end date value respectively?

Choose 2 answers

Options:

A.

Actual start date

B.

Planned start date

C.

Planned end date

D.

Due date

Buy Now
Questions 6

Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?

Options:

A.

'Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change'.

B.

'Enable altering of planned date for task in WIP/Closed'.

C.

'Rollup project start date from tasks'.

D.

'Calculate ROI percentage based on a project's estimated cost and its net value'.

Buy Now
Questions 7

The Business Unit field on a Project or Demand form displays values from a specific table. What type of field is this?

Options:

A.

Journal.

B.

Reference.

C.

Conditions.

D.

List.

Buy Now
Questions 8

Which role is needed to group related projects and demands?

Options:

A.

it_program_manager

B.

it_project_manager

C.

it_demand_manager

D.

it_project_user

Buy Now
Questions 9

What can be used to derive date-effective, criteria-driven hourly rates for calculating planned and actual resource costs for a project or demand?

Options:

A.

A time card

B.

A rate model

C.

A resource assignment

D.

A rate type

Buy Now
Questions 10

Depending on the execution type selected for a particular project, one of these dashboards will also be available:

Options:

A.

Project Summary - Waterfall Dashboard

B.

Timecard Dashboard

C.

User Manager Dashboard

D.

PMO Dashboard

Buy Now
Questions 11

Which system property needs to be set to True to be able to allocate budgets in Project Workspace?

Options:

A.

sn_plng_att_core.default.expense_type

B.

sn_invst_pln.budget_allocation_attribute

C.

sn_invst_pln.enable_budget_allocation_v2

D.

com.snc.project.rollup.cost

Buy Now
Questions 12

What role must be assigned to users to be considered for resource planning?

Options:

A.

timecard_user

B.

pps.resource_resource_user

C.

resource_manager

D.

rate_model_user

Buy Now
Questions 13

Is resource capacity derived from FTE or schedules?

Options:

A.

Only Schedules.

B.

Both.

C.

Neither.

D.

Only FTE.

Buy Now
Questions 14

Which role should be assigned to a user so they can read and retrieve data from any table of the Release Management application to generate reports?

Options:

A.

Business stakeholder

B.

Project manager

C.

Release user

D.

Release admin

Buy Now
Questions 15

What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?

Options:

A.

Accrual

B.

Commitment

C.

Baseline

D.

Forecast

Buy Now
Questions 16

Which role does a group need for selection in a resource assignment?

Options:

A.

resource_manager

B.

pps_resource

C.

itil

D.

it_project_user

Buy Now
Questions 17

If a lens has four entities, which entity within the lens structure would not have a parent reference?

Options:

A.

Top-level entity

B.

Second-level entity

C.

Third-level entity

D.

Bottom entity

Buy Now
Questions 18

If a user creates a new demand from the demand workbench, what state will the system save the record in?

Options:

A.

approved

B.

open

C.

draft

D.

qualified

Buy Now
Questions 19

Which role can configure the parameters of the demand workbench that is provided with the base system?

Options:

A.

All roles.

B.

business_stakeholder.

C.

it_project_manager.

D.

it_pps_admin.

Buy Now
Questions 20

What information are users required to enter on a cost plan for a demand?

Options:

A.

Cost type

B.

Discount Rate %

C.

Total planned cost

D.

Functional currency

Buy Now
Questions 21

The combination of the user and the assigned portfolio must be unique when adding a user to which registry?

Options:

A.

Application Registry.

B.

Event Registry.

C.

UX Page Registry.

D.

Stakeholder Registry.

Buy Now
Questions 22

Which table would an admin modify in order to add extra columns to the side panel or remove default column choices on the Prioritization page within the Portfolio Planning Workspace?

Options:

A.

[sn_align_cmn_int_choice_map]

B.

[sn_align_ws_portfolio_plan]

C.

[sn_align_core_lens]

D.

[sn_align_core_planning_item]

Buy Now
Questions 23

To set up a group for selection in a resource plan, the group record needs to include which role?

Options:

A.

it_project_user

B.

pps_resource

C.

itil

D.

resource_manager

Buy Now
Questions 24

When creating a program, which of the following cannot be part of multiple programs? Select all that apply.

Choose 2 answers

Options:

A.

Project.

B.

Demand.

C.

Portfolio.

D.

Tasks.

Buy Now
Questions 25

If the 'Move project for WIP projects' property is enabled, project tasks associated with the project are also moved, except for tasks in which of

the following states?

Choose 2 answers

Options:

A.

Pending

B.

Work in Progress

C.

Closed

D.

Open

Buy Now
Questions 26

Why is it recommended to keep the value of the property 'com.snc.project.task.max_task_duration' to 2600 or under?

Options:

A.

To avoid application memory issues.

B.

The system is unable to handle more than 2600 tasks.

C.

Best practices states projects should be no longer than 5 years.

D.

Because projects longer than 2600 days will no longer load.

Buy Now
Questions 27

A project expense line is cost associated with a specific source, except for:

Options:

A.

Fixed Assets.

B.

Program.

C.

Resource.

D.

Software.

Buy Now
Questions 28

Which of the following is the default schedule for the Project Management application?

Options:

A.

Repeats every week on weekdays Monday through Friday from 8:00am to noon and 1:00-5:00pm.

B.

Repeats every week on weekdays Monday through Friday.

C.

Repeats every week on weekdays Monday through Friday from 9:00am to 5:00pm.

D.

Repeats every week on weekdays Monday through Friday. Includes the child schedule U.S. Holidays.

Buy Now
Questions 29

At a minimum, which role is required to update a project task in Project Workspace?

Options:

A.

it_project_user

B.

it_project_manager

C.

Itil

D.

it_portfolio_manager

Buy Now
Questions 30

What plugin must be installed to use Capacity Planning in a portfolio?

Options:

A.

Collaborative Work Management

B.

Portfolio Planning

C.

Skills Management

D.

Time Card Management

Buy Now
Questions 31

Can an it_project_manager convert a task to a milestone?

Options:

A.

No, this can only be done by a system admin.

B.

Yes, if the task is assigned to the project manager.

C.

Yes, by right-clicking on the task in the Planning Console.

D.

No, the PPS admin role is also required.

Buy Now
Questions 32

The RIDAC workflow can be modified by using which recommended feature?

Options:

A.

Workflow Editor

B.

Project Form

C.

Flow Designer

D.

Service Catalog

Buy Now
Questions 33

When a demand is converted to a project, the following fields retain the start and due date:

Choose 2 answers

Options:

A.

Approved end date

B.

Actual end date

C.

Approved start date

D.

Actual start date

Buy Now
Exam Code: CIS-SPM
Exam Name: Certified Implementation Specialist - Strategic Portfolio Management
Last Update: Sep 11, 2025
Questions: 112

PDF + Testing Engine

$72.6  $181.49

Testing Engine

$57.8  $144.49
buy now CIS-SPM testing engine

PDF (Q&A)

$49.8  $124.49
buy now CIS-SPM pdf