You want to use the Custom Code Migration Worklist via Remote Code analysis using the ABAP Test Cockpit (ATC). How can you get the latest content of the simplification database? Please choose the correct answer.
During an SAP S/4HANA conversion with DMO, which of the following actions take place during the business downtime of the SUM procedure?
There are 3 correct answers to this question.
Response:
You are performing an SAP S/4HANA conversion with DMO as an inplace migration. How does SUM transfer the data by default from the source database to the target database during the migration?
What do you need to consider when performing the SI checks for an SAP S'4I 1ANA conversion? Note There are 2 correct answers to this question.
You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime.
The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center you can see 40 Process Buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
Please choose the correct answer.
Response:
You are planning to upgrade your SAP ECC 6.07 system running on a single codepage (SCP) to SAP ECC 6.08. What is the recommended option to perform this upgrade?
Please choose the correct answer.
Response:
In which case can you use near-Zero Downtime Maintenance (nZDM)? Note: There are 2 correct answers to this question.
You are performing an upgrade with SUM. You are in the BIND_PATCH phase of the roadmap step "Configuration". For some software components you find entries in the "Calculated level" column.
What does the "Calculated level" indicate for those software components?
Please choose the correct answer.
Response:
You are performing an S/4HANA conversion of the development system. Which credentials do you use in which system to perform the adjustment of dictionary objects (SPDD)?
Please choose the correct answer.
Response:
During the configuration of the DMO for SUM, how does the tool behave if option "Do not compare table contents" is selected regarding table comparison?
Please choose the correct answer.
Response:
During the upgrade of your development system, you run into the adjustment of non-dictionary objects handled by transaction SPAU There you find programs that are shown in status "automatic adjustment (green traffic tight). What will happen with these programs when you continue with your upgrade without performing any other actions inside your SAP system?
In ICNV. How database operations synchronized between the source and the target table?
During the SUM procedure, the phase XPRAS_AIMMRG fails. Where can you most likely see the reason for the error?
There are 2 correct answers to this question.
Response:
You want to execute a Unicode Conversion only. Which approach do you need to follow?
Please choose the correct answer.
Response:
What is the main purpose of performing benchmark runs for an SAP S/4HANA conversion?
Which steps can SUM perform during an SAP S/4HANA conversion? Note; There are 2 correct answers to this question.
What can you achieve by setting the SUM parameter "migration_only" to 1 in parameter file SAPup_add.par?
Please choose the correct answer.
Response:
Which downtime optimization technique requires the minimized downtime service (MDS) from SAP?
You are performing an upgrade with SUM using DMO to an AS ABAP 7.50 based SAP system. You entered a specific number of R3Ioad processes during Roadmap step "Extraction".
Where can you change this during the migration via the Utilities option of the SUM UI?
There are 2 correct answers to this question
Response: