Halloween 2025 Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

ISTQB-CTFL ISTQB Certified Tester Foundation Level (CTFL v4.0) Questions and Answers

Questions 4

Which of the following statements about the shift-left approach is true?

Options:

A.

Shift-left in testing can be implemented only in Agile/DevOps frameworks, as it relies completely on automated testing activities performed within a continuous integration process

B.

Performance testing performed during component testing, is a form of shift-left in testing that avoids planning and executing costly end-to-end testing at the system test level in a production-like environment

C.

Shift-left in testing can be implemented in several ways to find functional defects early in the lifecycle, but it cannot be relied upon to find defects associated with non-functional characteristics

D.

Continuous integration supports shift-left in testing as it can reduce the time between the introduction of a defect and its detection, thereby reducing the cost to fix it

Buy Now
Questions 5

You are testing the download process of a mobile phone application.

For which to the following capabilities to the system you need to design a nonfunctional test?

Options:

A.

It was easy to locate, download and install the application

B.

The application was correctly downloaded

C.

The application created an installation log file in a given folder

D.

The application installed only after the user's approval

Buy Now
Questions 6

Which of the following about typical information found within a test plan is FALSE?

Options:

A.

The need to temporarily have additional test personnel available for specific test phases and/or test activities

B.

The conditions that must be met in order for the test execution activities to be considered completed.

C.

The list of the product risks which have not been fully mitigated at the end of test execution.

D.

The conditions that must be met for part of all the planned activities to be suspended and resumed.

Buy Now
Questions 7

Which of the following is NOT a typical debugging activity when a failure is triggered by dynamic testing?

Options:

A.

Fixing the cause

B.

Reproducing the failure

C.

Diagnosing the root cause

D.

Adding new test cases

Buy Now
Questions 8

The tests at the bottom layer of the test pyramid:

Options:

A.

run faster than the tests at the top layer of the pyramid

B.

cover larger pieces of functionalities than the tests at the top layer of the pyramid

C.

are defined as 'Ul Tests' or 'End-To-End tests' in the different models of the pyramid

D.

are unscripted tests produced by experience-based test techniques

Buy Now
Questions 9

A software company decides to invest in reviews of various types. The thought process they have is that each artifact needs to be reviewed using only one of the review methods depending on the criticality of the artifact.

Options:

A.

The thought process is incorrect. The whole company should adopt same standard for review of all artifacts.

B.

The thought process is correct. The whole company should decide or the review method based on their CMM level.

C.

The thought process is incorrect. Same artifact can be reviewed using different review methods

D.

The thought process is correct. It wastes time to review same artifact using efferent review methods

Buy Now
Questions 10

Following a risk-based testing approach you have designed 10 tests to cover a product risk with a high-risk level. You want to estimate, adopting the three-point test estimation technique, the test effort required to reduce the risk level to zero by executing those 10 tests. You made the following three initial estimates:

• most optimistic = 6 person hours

• most likely = 30 person hours

• most pessimistic = 54 person hours

Based only on the given information, which of the following answers about the three-point test estimation technique applied to this problem is true?

Options:

A.

The final estimate is between 22 person hours and 38 person hours

B.

The final estimate is exactly 30 person hours because the technique uses the initial most likely estimate as the final estimate

C.

The final estimate is between 6 person hours and 54 person hours

D.

The final estimate is exactly 30 person hours because the technique uses the arithmetic mean of the three initial estimates as the final estimate

Buy Now
Questions 11

A number of characteristics are given for impact of SDLC on the testing effort.

i. Finishing of requirements review leading to test analysis

ii. Both - static and dynamic testing performed at unit testing level

iii. Frequent regression testing may need to be performed

iv Extensive product documentation

v. More use of exploratory testing

Which of the following statements is MOST correct?

Options:

A.

i and iv are characteristics of sequential models; ii. iii and v are characteristics of iterative and incremental models

B.

ii and iv are characteristics of sequential models; i. iii and v are characteristics of iterative and incremental models

C.

iii and iv are characteristics of sequential models and i. ii and v are characteristics of iterative and incremental models

D.

ii and iii are characteristics of sequential models; iv and v are characteristics of iterative and incremental models

Buy Now
Questions 12

Which of the following statements does NOT describe good testing practice, regardless of the SDLC chosen?

Options:

A.

All development activities are subject to quality control.

B.

To avoid redundancy, different test levels have specific test objectives.

C.

To adhere to the principle of early testing, test analysis for a specific test level takes place during the corresponding phase of the SDLC.

D.

Testers are involved in the review of work results as soon as the documents have been approved by the stakeholders.

Buy Now
Questions 13

Which of the following characterizations applies to a test tool used for the analysis of a developer's code prior to its execution?

Options:

A.

Tool support for test design and implementation.

B.

Tool support for static testing.

C.

Tool support for test execution and logging.

D.

Tool support for performance measurement and dynamic analysis.

Buy Now
Questions 14

Which of the following statements best describes the difference between product risk and project risk in software testing?

Options:

A.

Product risk refers to the risk associated with the project's schedule, budget, and resources, while project risk refers to the risk associated with the quality and functionality of the software product.

B.

Product risk refers to the risk associated with issues such as delays in work product deliveries, inaccurate estimates, while project risk refers to the risk associated with the project's schedule, budget, and resources.

C.

Product risk and project risk are essentially the same and can be used interchangeably.

D.

Product risk refers to the risk associated with delays in elements such as work product deliveries and inaccurate estimates, while project risk refers to the risk associated with issues such as user dissatisfaction.

Buy Now
Questions 15

Testing Quadrants, as a model, is effective in aligning stakeholders within Agile teams.

Which of the following examples demonstrates this?

Options:

A.

Using Testing Quadrants, the test manager is able to measure and communicate test coverage to all stakeholders.

B.

Using Testing Quadrants, the test manager is able to communicate potential product risk to all stakeholders.

C.

Using Testing Quadrant, the test manager is able to prioritize defects by linking these to a specific type of test.

D.

Using Testing Quadrants, the test manager is able to differentiate and describe the types of tests to all stakeholders.

Buy Now
Questions 16

The following diagram displays the logical dependencies between requirements and the individual requirement priorities. For example, "R2->R3" means that R3 is dependent on R2. Priority is indicated by the number next to the letter ”P" i.e. P1 has a higher priority than P2.

Which one of the following options best describes the test execution sequence using both requirement dependency and priority

Options:

A.

R2. R1, R3. R4. R5, R6. R7, R8.

B.

R1, R2, R3, R4, R5, R6, R7, R8.

C.

R2, R4. R8, R5, R1, R6, R3, R7.

D.

. R2, R1,R3,R7,R6,R5,R4,R8.

Buy Now
Questions 17

Which of the following is the BEST reason for selecting a particular type of software development lifecycle model?

Options:

A.

The project manager's preference

B.

Tester skill level with the software development lifecycle model

C.

The project team's overall familiarity with the model

D.

The type of product being developed

Buy Now
Questions 18

Which of the following statements is LEAST likely to be describing component testing?

Options:

A.

It identifies defects in modules and classes.

B.

Simulators and stubs may be required.

C.

It mainly tests interfaces and interaction between components.

D.

It may be applied using a test-first approach.

Buy Now
Questions 19

What is typically NOT included in a test progress report?

Options:

A.

Information about test obstacles during a test period

B.

Statistics on the success of each tester in finding bugs

C.

Changed risks within the test period

D.

Test status in relation to defined test metrics (including exit criteria)

Buy Now
Questions 20

Which of the following is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development?

Options:

A.

Test-Driven Development (TDD)

B.

Acceptance Test-Driven Development (ATDD)

C.

Behavior-Driven Development (BDD)

D.

Domain-Driven Design (DDD)

Buy Now
Questions 21

You are an experienced tester on a project with incomplete requirements and under pressure to deploy.

What type of testing should you do?

Options:

A.

Decision-based testing.

B.

Checklist-based testing.

C.

Error guessing.

D.

Exploratory testing.

Buy Now
Questions 22

Which ONE of the following options corresponds to an activity in the testing process in which testable features are identified?

Options:

A.

Test design

B.

Test analysis

C.

Test implementation

D.

Test execution

Buy Now
Questions 23

Which of the following statements about white-box testing is FALSE?

Options:

A.

Static testing can benefit from using code-related white-box test techniques during code reviews.

B.

White-box testing allows suggesting test cases for increasing coverage levels which are based on objective measures

C.

Achieving full code coverage for a component or a system ensures that it has been fully tested

D.

Black-box testing can benefit from using code-related white-box test techniques to increase confidence in the code.

Buy Now
Questions 24

A requirement specifies that if the total amount of sales (TAS) made during the year by a corporate seller is 300,000€ or more, the bonus that must be paid to the seller is 100% of a certain amount agreed upon at the beginning of the year. The software contains a fault as it implements this requirement with the decision "IF (TAS = 300,000)" instead of "IF (TAS >= 300.000)". The application of the 3-value boundary value analysis to this problem consists of the following three test cases (TAS is an integer variable):

TC1 = 299,999 TC2=300,000 TC=300,001

Which of the following statements is TRUE?

Options:

A.

TC1 would highlight the fault

B.

TC2 would highlight the fault

C.

TC3 would highlight the fault

D.

None of the three test cases would highlight the fault.

Buy Now
Questions 25

Consider an estimation session in which a six-member Agile team (Memb1..... Memb6) uses the planning poker technique to estimate a user story (in story points). The team members will use a set of cards with the following values: 1,2, 3,5, 8,13,21. Below is the outcome of the first round of estimation for this session:

ISTQB-CTFL Question 25

Which of the following answers BEST describes how the estimation session should proceed?

Options:

A.

The final estimate of the user story in story points is determined by applying the three-point estimation technique with the following input values most optimistic estimate - 1, most likely estimate - 3, and most pessimistic estimate - 21

B.

Further estimation rounds should be performed until all team members will pick the card having the same value: this value will represent the final estimate of the user story in story points.

C.

The final estimate of the user story in story points is determined by calculating the average value between the most optimistic estimate of 21 story points (Memb4> and the most pessimistic estimate of 1 story point (Memb6)

D.

Memb6 and Memb4 which have produced the most pessimistic and the most optimistic estimates respectively, should explain the reasons of their choices to stimulate a discussion between all members before proceeding to another estimation round

Buy Now
Questions 26

Given the following user story for the development of an online shoe store:

"As a customer, I want to be able to filter shoes by color so that I see, for example, only red shoes in the selection."

Which of the following positive test cases BEST fits to the user story?

Options:

A.

Precondition: Home page of the shoe store is opened

Test steps to be performed:

Tick "red" in the color selection.

Click on the "Filter" button.

Expected result: Only red shoes are displayed.

B.

Precondition: Home page of the shoe store is opened

Test steps to be performed:

Tick "red" in the color selection.

Click on the "Filter" button.

Expected result: Within 2 seconds all red shoes are displayed, then the other colors.

C.

Precondition: Homepage of shoe store with shoes size 40 is opened

Test steps to be performed:

Tick "red" in the color selection.

Click on the "Filter" button.

Expected result: Only red shoes of size 40 are displayed.

D.

Precondition: Home page of the shoe store is opened

Test steps to be performed:

User logs in with his customer ID.

Tick "green" in the color selection.

Click on the "Filter" button.

Expected result: Only red shoes are displayed.

Buy Now
Questions 27

Which ONE of the following options BEST describes Behavior-Driven Development (BDD)?

Options:

A.

Expresses the desired behavior of an application with test cases written in a simple form of natural language that is easy to understand by stakeholders—usually using the Given/When/Then format. Test cases are then automatically translated into executable tests.

B.

Defines test cases at a low level, close to the implementation, using unit test frameworks.

C.

Is primarily focused on non-functional testing techniques to ensure system reliability and performance.

D.

Requires testing to be performed after development is completed to validate software functionality.

Buy Now
Questions 28

Which of the following exemplifies how a software bug can cause harm to a company?

Options:

A.

"Print" prints the last page twice for a file with 1000 pages

B.

The timeout on the login page of a web site is 9 minutes, while the requirement was for 10 minutes

C.

When uninstalling the application, the uninstall dialog has a spelling mistake

D.

When calculating the final price in a shopping list, the price of the last item is not added

Buy Now
Questions 29

For withdrawing money tram an Automated Teller Machine (ATM), the following conditions are required:

- The bank card is valid

- The PIN code is correct

- Money is available in the user's account

The following are some possible interactions between the user and the ATM:

- The entered card is invalid The card is rejected

- The PIN code is wrong The ATM asks for another PIN code

- The requested amount is more than available in the user's account: The ATM asks for another amount

- The requested amount is available in the user's account The ATM dispenses the money

Which test design technique should be used to cover all possible combinations of the in put conditions?

Options:

A.

Use case based testing

B.

Decision table

C.

Boundary value analysis

D.

Equivalence class partitioning

Buy Now
Questions 30

A test engineer finds a defect while testing. After the developer has fixed the defect, the test engineer decides to re-run a complete section of the tests. Which of the following is correct?

Options:

A.

The lest engineer should not re-run the tests, as they have already been run, and results recorded.

B.

The test engineer should not re-run the tests, they should be part of the developer tests.

C.

The test engineer should re-run the tests, in order to ensure that new defects have not been introduced by the fix.

D.

The test engineer should re-run the tests, because the defect shows that the test cases need to be updated.

Buy Now
Questions 31

A test manager has started a cycle of testing for an e-commerce application. The reason for testing is the change in the protocol for connecting to the payment gateway because of new regulations. Which of the following correctly names this type of testing?

Options:

A.

Beta testing

B.

Maintenance testing

C.

System integration testing

D.

Retirement testing

Buy Now
Questions 32

Which of the following is the main difference between quality assurance (QA) and quality control

Options:

A.

A is the responsibility of everyone on a project, while QC is the responsibility of a dedicated team.

B.

A is a process-oriented approach, while QC is a product-oriented approach.

C.

A is focused on implementation, while QC is focused on improvement.

D.

A is preventive, while QC is corrective.

Buy Now
Questions 33

Which of the following statements about white-box test techniques is true?

Options:

A.

Achieving full statement coverage and full branch coverage for a software product means that such software product has been fully tested and there are no remaining bugs within the code

B.

Code-related white-box test techniques are not required to measure the actual code coverage achieved by black-box testing, as code coverage can be measured using the coverage criteria associated with black-box test techniques

C.

Branch coverage is the most thorough code-related white-box test technique, and therefore applicable standards prescribe achieving full branch coverage at the highest safety levels for safety-critical systems

D.

Code-related white-box test techniques provide an objective measure of coverage and can be used to complement black-box test techniques to increase confidence in the code

Buy Now
Questions 34

Which are the MAIN goals of risk management in a software project?

Options:

A.

To increase the success probability for the project regardless of costs.

B.

To increase focus on preventative processes and to increase satisfaction for the testers.

C.

To control contractual problems and minimize the impacts of company policies.

D.

To reduce the probability of undesired situations and to reduce the effect of potential impact.

Buy Now
Questions 35

Which of the following statements is an example of testing contributing to higher quality?

Options:

A.

A test leader writes a test summary report

B.

A project manager asks to a test leader to estimate the test effort

C.

A tester installs a test ten in the lest environment

D.

A tester finds a bug which is resolved prior to release

Buy Now
Questions 36

The following 4 equivalence classes are given:

Which of the following alternatives includes correct test values for x. based on equivalence partitioning?

Options:

A.

-100; 100:1000; 1001

B.

-500; 0; 100; 1000

C.

-99; 99:101; 1001

D.

-1000; -100; 100; 1000

Buy Now
Questions 37

You are a test manager responsible for implementing risk-based testing in your organization which deals with software in the healthcare domain. You are writing a handbook of various product risk mitigation options. Which ONE of the following options correctly represent the correct mitigation options?

Options:

A.

Using a third party testing company to transfer the risk to that company

B.

Choosing a tool for automated unit testing to reduce the risks

C.

Increasing the number of testers to be able to take care of all the risks

D.

Selecting a tester with required knowledge related to compliance and standards

Buy Now
Questions 38

Consider the following iteration planning tasks where a tester can provide value:

    Break down user stories into tasks (particularly testing tasks)

    Estimate test effort for all testing tasks

    Identify and refine functional and non-functional aspects of the test object

Which ONE of the following tasks should be ADDED to the above list?

Options:

A.

Determining the test strategy

B.

Participating in the detailed risk analysis of user stories and determining their testability

C.

Planning the testing for the release

D.

Writing testable user stories and acceptance criteria

Buy Now
Questions 39

During which main group of test activity are the following tasks performed?

•Checking test results and logs against specified coverage criteria.

•Assessing the level of component or system quality based on test results and logs.

•Determining whether more tests are needed.

Select the correct answer:

Options:

A.

Test planning.

B.

Test analysis.

C.

Test design.

D.

Test monitoring and control.

Buy Now
Questions 40

Consider the following examples of risks identified in different software development projects:

[I]. The contrast color ratio for both normal text and large text of a website does not comply with the applicable accessibility guidelines, making it difficult for many users to read the content on the pages

[II]. A development vendor fails to deliver their software system on time, causing significant delays to system integration testing activities that have been planned as part of a development project for a system of systems

[III]. People in the test team do not have sufficient skills to automate tests at the test levels required by the test automation strategy which does not allow production of an effective regression test suite

[IV]. In a web application, data from untrusted sources is not subject to proper input validation, making the application vulnerable to several security attacks

Which of the following statements is true?

Options:

A.

[I] and [III] are product risks; [II] and [IV] are project risks

B.

[I] and [IV] are product risks. [II] and [III] are project risks

C.

[II], [III] and [IV] are product risks; [I] is a project risk

D.

[IV] is a product risk; [I]. [II] and [III] are project risks

Buy Now
Questions 41

An application is subjected to a constant load for an extended period of time as part of a performance test While running this test, the response time of the application steadily slows down, which results in a requirement not being met This slowdown is caused by a memory leak where the application code does not properly release some of the dynamically allocated memory when it is no longer needed. Which of the following statements is TRUE?

Options:

A.

The slowdown is a failure while the memory leak is a defect

B.

The slowdown is a defect while the memory leak is an error.

C.

The slowdown is an error; the memory leak is a defect.

D.

The slowdown is a defect; the memory leak is a failure.

Buy Now
Questions 42

Which of the following statements is NOT true about Configuration management and software testing?

Options:

A.

Configuration management helps maintain consistent versions of software artifacts.

B.

Configuration management supports the build process, which is essential for delivering a test release into the test environment.

C.

When testers report defects, they need to reference version-controlled items.

D.

Version controlled test ware increases the chances of finding defects in the software under test.

Buy Now
Questions 43

Use Scenario 1 “Happy Tomatoes” (from the previous question).

Using the Boundary Value Analysis (BVA) technique (in its two-point variant), identify the set of input values that provides the HIGHEST coverage.

Options:

A.

{7,8,21,22,29,30}

B.

{7,8,22,23,29,30}

C.

{6,7,8,21,22,29,31}

D.

{6,7,21,22,29,30}

Buy Now
Questions 44

Which one of the following statements correctly describes the term 'debugging'?

Options:

A.

There is no difference between debugging and testing.

B.

Debugging is a confirmation activity that checks whether fixes resolved defects.

C.

Debugging is the development activity that finds, analyses and fixes defects.

D.

Debugging is of no relevance in Agile development.

Buy Now
Questions 45

Consider a program that computes the factorial of a number (n). From the specifications you know that:

• I n < 0. a message "Value out of range" must be issued.

• If 0 < n < 100, the program calculates the factorial and returns the number

• If 100 < n < 200 message "Value out of range" must be issued

Options:

A.

There are 3 partitions - one for negative numbers, one for numbers up to 100 and the last one for numbers up to 200

B.

The equivalence partitions cannot be determined for this question because factorial of numbers close to 200 will be very large

C.

The equivalence partitions cannot be determined for this question because the error message for two partitions is exactly same

D.

The requirements are not correct because the partitions are overlapping

Buy Now
Questions 46

During iteration planning, a scrum team uses an estimation technique called planning poker to estimate the effort required to deliver a critical user story. In advance of the estimation session, the team agreed on some ground rules to limit the number of poker rounds and save time.

The team agreed on the following:

1. They will use the following progression for estimation: Extra-small, Small, Medium, Large, Extra-large, and Extra-extra-large.

2. If estimation values differ significantly, the highest score will be used for estimation purposes.

The result of the first round of planning poker:

Team MemberEstimation

BusinessLarge

DevelopmentExtra-extra-large

TestingExtra-extra-large

Which of the following options best represent the team’s next actions?

Options:

A.

The fact that all estimations are high indicate that the user story is not well understood or should be broken down into multiple smaller stories.

B.

The pre-agreed rules state that the highest score should be used for estimation, resulting in the user story being categorised as Extra-extra-large.

C.

Since the business representative is likely to have the most informed view of the requirement, the user story is categorised as a Large.

D.

the team discusses the differences in the estimates and repeats the poker round until an agreemet is reached.

Buy Now
Questions 47

How can testing contribute to higher quality?

Options:

A.

Testing help to measure the quality of software.

B.

Testing ensures that remaining defects are documented.

C.

Testing removes errors in the software.

D.

Testing eliminates the risk with software.

Buy Now
Questions 48

A team's test strategy was to invest equal effort in testing each of a system's modules. After running one test cycle, it turned out that most of the critical bugs were detected in one of the system's modules.

Which testing principal suggests a change to the current test strategy for the next test cycle?

Options:

A.

Pesticide Paradox

B.

Early testing

C.

Absence-of-errors fallacy

D.

Defect clustering

Buy Now
Questions 49

Which of the following is a good testing practice which is applicable INDEPENDENT of the software development lifecycle followed?

Options:

A.

Not all development activities should have corresponding test activities

B.

Each test level should have an appropriate test objective

C.

Large amount of redundancy between test levels is good because it prevents bug leakage

D.

Reviews should be done after the work products have been finalized

Buy Now
Questions 50

Which of the following statements is true?

Options:

A.

Functional testing focuses on what the system should do while non-functional testing on the internal structure of the system

B.

Non-functional testing includes testing of both technical and non-technical quality characteristics

C.

Testers who perform functional tests are generally expected to have more technical skills than testers who perform non-functional tests

D.

The test techniques that can be used to design white-box tests are described in the ISO/IEC 25010 standard

Buy Now
Questions 51

Which of the following statements about the value of maintaining traceability between the test basis and test work products is not true?

Options:

A.

Traceability can be useful for assessing the impact of a change to a test basis item on the corresponding tests

B.

Traceability can be useful for determining how many test basis items are covered by the corresponding tests

C.

Traceability can be useful for determining the most suitable test techniques to be used in a testing project

D.

Traceability can be useful to support the needs required by the auditing of testing

Buy Now
Questions 52

Which of the following is a typical potential risk of using test automation tools?

Options:

A.

Reduced feedback times regarding software quality compared to manual testing.

B.

Reduced test execution limes compared to manual testing.

C.

Reduced repeatability and consistency of tests compared to manual testing

D.

Underestimation of effort required to maintain test scripts.

Buy Now
Questions 53

Which ONE of the following work products TYPICALLY belongs to test execution?

Options:

A.

Test logs that document the results of test execution.

B.

Automated test scripts used for test execution.

C.

A test plan that describes the test strategy and test objectives.

D.

A list of test conditions prioritized during test analysis.

Buy Now
Questions 54

For the following pseudo-code determine number of tests required for 100% statement coverage

IF Gender = Boy

If Age > 3 AND Age < 5

Shoe Size = 1

ELSE IF Age >=5 AND Age < 7

Shoe Size = 2

ENDIF

ELSE

IF Age > 3 AND Age < 5

Shoe Size = 0

ELSE IF Age >=5 AND Age < 7

Shoe Size = 1

ENDIF

ENDIF

Options:

A.

6

B.

4

C.

2

D.

6

Buy Now
Questions 55

A company wants to reward each of its salespeople with an annual bonus that represents the sum of all the bonuses accumulated for every single sale made by that salesperson. The bonus for a single sale can take on the following four values: 3%, 5%, 7% and 10% (the percentage refers to the amount of the single sale). These values are determined on the basis of the type of customer (classified as "Basic" or "Premium") to which such sale was made, and on the amount of such sale classified into the following three groups G1, G2 and G3:

• [G1]: less than 300 euros

• [G2]: between 300 and 2000 euros

• [G3]: greater than 2000 euros

Which of the following is the minimum number of test cases needed to cover the full decision table associated with this scenario?

Options:

A.

12

B.

6

C.

4

D.

3

Buy Now
Questions 56

The following state transition diagram describes the functionality involved in a system using fingerprint and password authentication to log onto a system.

How many distinct states of the system are visible in the above diagram?

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Questions 57

Which of the following is NOT a common objective of testing?

Options:

A.

Finding defects in the software

B.

Preventing defects

C.

Debugging the software to find the reason for defects

D.

Providing information on the status of the system

Buy Now
Questions 58

Which of the following statements about the shift-left approach is FALSE?

Options:

A.

The shift-left approach can only be implemented with test automation

B.

The shift-left approach in testing is compatible with DevOps practices.

C.

The shift-left approach can involve security vulnerabilities

D.

The shift-left approach can be supported by static analysis tools.

Buy Now
Questions 59

A bank software has a feature of locking down accounts that have and overdraft higher than $10,000.

Due to a bug in the code, the system locks down accounts once they reached $1000 overdraft.

Based on this context, which of the following is correct statement

Options:

A.

It is an example of a defect that it goes undetected, will cause harm to the end customer and to the company (the bank)

B.

It is an example of a defect, that if goes undetected, will cause harm to the end customer but not to the company (the bank)

C.

It is an example of a defect that if goes undetected, will not cause harm to the end customer, but will cause harm to the company (the bank)

D.

It is an example of a defect that if goes undetected, will not cause any real harm to either the end customer or to the company (the bank)

Buy Now
Questions 60

Which of the following statements about traceability is FALSE?

Options:

A.

Traceability between test basis items and the test cases designed to cover them, makes it possible to determine which test basis items have been covered by the executed test cases.

B.

Traceability between test basis items and the test cases designed to cover them, enables experience-based test techniques to be applied

C.

Traceability between test basis items and the test cases designed to cover them, enables identification of which test cases will be affected by changes to the test basis items.

D.

Traceability can be established and maintained through all the test documentation for a given test level, such as from test conditions through test cases to test scripts.

Buy Now
Questions 61

Which of the following is a typical product risk?

Options:

A.

Poor usability of the software

B.

A problem in the code developed by a 3rd party

C.

Low quality of the configuration data, test data and tests

D.

Problem in defining the right requirements

Buy Now
Questions 62

Software was found lo take much more time than the stated requirement of less than one second to save a file. Upon investigation it was found that there was an unnecessary check inside a loop which was slowing down the file-save operation. The software not being able to meet the desired response time is an example of

Options:

A.

It is not a defect

B.

Defect

C.

Error

D.

Failure

Buy Now
Questions 63

A system has valid input numbers ranging between 1000 and 99999 (both inclusive). Which of the following inputs are a result of designing tests for all valid equivalence classes and their boundaries?

Options:

A.

999.1000.23232.99999.100000

B.

999.1000.50000.100000.100001

C.

999.100000

D.

1000,50000,99999

Buy Now
Questions 64

In a museum there are staggered entrance fees:

    Free admission: children under 14 years

    Reduced admission: young people aged 14 and under 18, retiree, students and welfare recipients

    Regular price: all other persons

Which of the following four options describes the minimum set of test data that reaches 100% coverage of all valid equivalence classes for the admission fees?

Options:

A.

Child (12 years), student (23 years), retiree (68 years)

B.

Youth (16 years), adult (35 years), adult (60 years)

C.

Child (12 years), welfare recipient (45 years), retiree (68 years)

D.

Child (12 years), adult (35 years), retiree (68 years)

Buy Now
Questions 65

What is test oracle?

Options:

A.

The source of lest objectives

B.

The source for the actual results

C.

The source of expected results

D.

The source of input conditions

Buy Now
Questions 66

Which of the following statements about static testing and dynamic testing is true?

Options:

A.

Unlike dynamic testing, which can be also performed manually, static testing cannot be performed without specialized tools

B.

Static testing is usually much less cost-effective than dynamic testing

C.

Unlike dynamic testing, which focuses on detecting potential defects, static testing focuses on detecting failures which may be due to actual defects

D.

Both static testing and dynamic testing can be used to highlight issues associated with non-functional characteristics

Buy Now
Questions 67

An Incident Management tool implements the following defect states; Open, Assigned, Solved,

Closed Consider the following defect report:

Id T000561

Test Object "Warehouse Management' application

Tester name; John Bishop

Date: 10th. April 2010

Test Case MRT558I

Status OPEN

Severity Serious

Priority

Problem- After inputting the Total Quantity item = 450 in the SV034 screen, the system shows an unexpected Error message=47

Correction:

Developer name:

Closing date:

Which of the following is a valid criticism of this report?

Options:

A.

The Priority, the Correction description and the Developer name are missing

B.

The version of the application is missing

C.

There is no link to the applicable requirement (traceability)

D.

The description is not highlighting the source of the problem

Buy Now
Questions 68

Which of the following software development models BEST exemplifies a model that does NOT support the principle of early testing?

Options:

A.

The iterative development model

B.

The V-model

C.

The Waterfall model

D.

The incremental development model

Buy Now
Questions 69

Which of the following is a task the Author is responsible for, as part of a typical formal review?

Options:

A.

Determining the people who will be involved in the review

B.

Recording the anomalies found during the review meeting

C.

Identifying potential anomalies in the work product under review

D.

Fixing the anomalies found in the work product under review

Buy Now
Questions 70

The acceptance criteria associated with a user story:

Options:

A.

are often written in a rule-oriented format using the template referred to as "Given/When/Then"

B.

are often documented following in rule-oriented format using the following template: "As a [role], I want [feature], so that I can [benefit]"

C.

can be written in different formats and represent an aspect of a user story referred to as confirmation' of the so called "3 C's"

D.

must be written in one of the two following formats: scenario-oriented or rule-oriented

Buy Now
Questions 71

Which ONE of the following roles is responsible for mediating, managing time, and generating a safe review environment in which everyone can speak freely?

Options:

A.

Manager

B.

Reviewer

C.

Review leader

D.

Moderator

Buy Now
Questions 72

What is 'Component Testing'?

Options:

A.

Integration Testing

B.

Functional testing

C.

Experience-based testing

D.

A test level

Buy Now
Questions 73

Which ONE of the following statements about acceptance testing is NOT correct?

Options:

A.

Testing of disaster recovery and backup/restore is usually NOT part of acceptance testing.

B.

The customers or system users are often responsible for the acceptance testing.

C.

The main goal of acceptance testing is to build confidence in the system, not find defects.

D.

Acceptance testing is the last level of testing performed prior to system release.

Buy Now
Questions 74

Which description reflects aspects of checklist-based testing?

Options:

A.

The checklist contains test cases that need to be executed in a certain order (e.g. defect-detecting test cases from previous projects).

B.

The checklist includes failure descriptions that have been found in the past which should be avoided.

C.

The checklist contains experience-based test conditions, mostly in the form of questions and based on causes of previous failures, which are used when creating the test.

D.

The checklist contains common testing techniques (e.g. equivalence class partitioning) and their uses to simplify the selection of the "appropriate" test techniques.

Buy Now
Questions 75

In Agile teams, testers closely collaborate with all other team members. This close collaboration could be problematic and result in testing-related organizational risks.

Which TWO of the following organization risks could be encountered?

I.Testers lose motivation and fail at their core tasks.

ii.Close interaction with developers causes a loss of the appropriate tester mindset.

iii.Testers are not able to keep pace with incoming changes in time-constrained iterations.

iv.Testers, once they have acquired technical development or business skills, leave the testing team.

Options:

A.

ii and iii

B.

i and iii

C.

i and ii

D.

ii and iv

Buy Now
Questions 76

Consider the following defect report for an Exam Booking System

Defect ID: ST1041 | Title: Unable to cancel an exam booking | Severity: Very High | Priority: Very High | Environment: Windows 10, Firefox

Description: When attempting to cancel an exam booking using the cancel exam feature, the system does not cancel the exam even though it shows a message that the exam has

been cancelled.

Which ONE of the following indicates the information that should be added to the description for reproducing the defect easily?

Options:

A.

Providing better severity and priority. It is not clear why this is a high severity problem as the exams can be booked without any problem.

B.

Providing exact steps that lead to this defect. It is not clear from the description if this is a problem for any scheduled exam or for a specific user.

C.

The defect Id used is alphanumeric in nature. It should be a number only.

D.

Repeating the test case with different browsers and logging a separate defect for each one of them

Buy Now
Questions 77

Which of the following is not an example of a typical content of a test completion report for a test project?

Options:

A.

The additional effort spent on test execution compared to what was planned

B.

The unexpected test environment downtime that resulted in slower test execution

C.

The residual risk level if a risk-based test approach was adopted

D.

The test procedures of all test cases that have been executed

Buy Now
Questions 78

Which of the following answers describes a reason for adopting experience-based testing techniques?

Options:

A.

Experience-based test techniques provide more systematic coverage cnteria than black-box and white-box test techniques

B.

Experience-based test techniques completely rely on the tester's past experience for designing test cases.

C.

Experience-based test techniques allow designing test cases that are usually easier to reproduce than those designed with black-box and white-box test techniques.

D.

Experience-based test techniques tend to find defects that may be difficult to find with black-box and white-box test techniques and are often useful to complement these more systematic techniques.

Buy Now
Questions 79

You are working on creating test cases for a user story -

As a customer, I want to be able to book an ISTQB exam for a particular date, so that I can find choose my time slot and pay the correct amount, including discounts, if any.

The acceptance criteria for this :

1. The dates shown should be from the current date to 2 years in future

2. Initially there should be 10 timeslots available for each day, 1 hour each, starting at 8 AM GMT

3. Maximum 5 persons should be able to select a time slot after which that time slot should become unavailable

4. First timeslot should have a 10% discount

Which of the following is the BEST example of a test case for this user story?

Options:

A.

Logon to the site. Book an exam for the current date. Expected result: timeslots should be shown. Change the time to any other date prior to the selected date. Expected result: New slot should become visible.

B.

Logon to the site. Expected result: Default 8 AM (GMT) timeslot should be selected Change the time to any other timeslot. Expected result: New slot should be booked

C.

Logon to the site. Book 5 exams for the current date. Expected result: Exams should be booked. Book 6th timeslot for the same date. Expected result: The exam should be booked but no discount should be given.

D.

Logon to the site and book an exam for the 8 AM (GMT) timeslot Expected result: You should get 10% discounted price. Change the time to any other timeslot. Expected result: Discount should be removed

Buy Now
Questions 80

Which of the following statements is TRUE'?

Options:

A.

Unlike functional testing, non-fundional testing can only be applied to conventional systems, not artificial intelligence-based system.

B.

Functional testing focuses on what the system is supposed to do, while white-box testing focuses on how well the system does what it is supposed to do

C.

Functional testing can be applied to all test levels, while non-functional testing can be applied only to system and acceptance test levels.

D.

Black-box test techniques and experience-based test techniques may be applicable to both functional testing and non-functional testing

Buy Now
Questions 81

Consider the following simplified version of a state transition diagram that specifies the behavior of a video poker game:

ISTQB-CTFL Question 81

What Is the minimum number of test cases needed to cover every unique sequence of up to 3 states/2 transitions starting In the "Start" state and ending In the "End" state?

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Questions 82

Which TWO of the following are benefits of continuous integration?

I. Allows earlier detection and easier root cause analysis of integration problems and conflicting changes.

II. Removes the need for manual test analysis, design and execution.

Hi. Removes the dependency on automated regression packs when integrating larger systems, or components.

iv. Gives the development team regular feedback on whether the code is working.

Select the correct answer:

Options:

A.

i and iv

B.

i and ii

C.

i and iii

D.

iii and iv

Buy Now
Questions 83

Which of the following statements about independent testing is WRONG?

Options:

A.

Independent testing is necessary because developers don't know any testing.

B.

Independent testing is best suited for the system test level.

C.

A certain degree of independence makes the tester more effective at finding defects.

D.

Independent test teams may find other types of detects than developers who are familiar with the system's structure.

Buy Now
Questions 84

Calculate the measurement error SD for the following estimates done using three point estimation technique-Most optimistic effort (a) -120 person days Most likely effort (m) -180 person days Most pessimistic effort (b) - 240 person days

Options:

A.

180

B.

120

C.

197

D.

20

Buy Now
Questions 85

Which of the following activities are part of test planning?

I) Setting the entry and exit criteria

II) Determining the validity of bug reports

III) Determining the number of resources required

IV) Determining the expected result for test cases

Options:

A.

I. IV

B.

I. III

C.

I, III, IV

D.

I, II, IV

Buy Now
Questions 86

Shripriya is defining the guidelines for the review process implementation in her company. Which of the following statements is LEAST likely to have been recommended by her?

Options:

A.

Independent of the size of the work products, planning for the review should be performed

B.

Defect reports should be created for every review found

C.

Large sized work products should be reviewed in one go because you will have to spend too much time if you split it into multiple reviews

D.

Review initiation is the stage when the review team starts the discussion on the review comments

Buy Now
Questions 87

Why is it important to select a test technique?

Options:

A.

There are usually loo many test cases that may be run on a system. Test techniques help reduce the number of tests.

B.

The only way to test a software application is by using well proven test techniques.

C.

Selecting the right test technique in a given situation Increases the effectiveness of the test process Oy creating tests with higher chance of finding bugs.

D.

Test techniques define the number of regression cycles, which in turn impact the project schedule.

Buy Now
Questions 88

Use Scenario 1 “Happy Tomatoes” (from the previous question).

When running test case TC_59, the actual result for t = 35 degrees Celsius is OUTPUT = X instead of the expected output.

Which information should NOT be included in the defect report?

Options:

A.

Identification of the test object and test environment

B.

A concise title and a short summary of the defect being reported

C.

Description of the structure of the test team

D.

Expected results and actual results

Buy Now
Questions 89

What type of testing measures its effectiveness by tracking which lines of code were executed by the tests?

Options:

A.

Acceptance testing

B.

Structural testing

C.

Integration testing

D.

Exploratory testing

Buy Now
Questions 90

Which of the following statements about testware are correct?

I When closing the test activities, all the testware resources can be uninstalled and released

II All the testware should be subject to Configuration Management

III. The testware. at the end of the project, should be transferred to the organization responsible for maintenance

IV The developers are responsible for the correct installation of the testware

Options:

A.

II, Ill

B.

I, Ill

C.

I, IV

D.

II, IV

Buy Now
Questions 91

Which ONE of the following options is NOT a test objective?

Options:

A.

Verifying whether specified requirements have been fulfilled

B.

Triggering failures and finding defects

C.

Finding errors

D.

Validating whether the test object is complete and works as expected by the stakeholders

Buy Now
Questions 92

Which of the following is a key characteristic of informal reviews?

Options:

A.

Kick-off meeting

B.

Low cost

C.

Individual preparation

D.

Metrics analysis

Buy Now
Questions 93

Which of the following is a function of a dynamic analysis tool?

Options:

A.

Provide support for traceability of tests, test results and incidents to source documents

B.

Monitor the allocation, use and de-allocation of memory during run-time of a program

C.

Execute programs step-by-step in order to reproduce failures and find corresponding defects

D.

Provide support for release of baselines consisting of configuration items

Buy Now
Questions 94

The following table shows six test cases TC01 to TC06 with their priorities and dependencies.

ISTQB-CTFL Question 94

Schedule the test execution of the specified test case set according to the priorities and dependencies. Since the test time is very tight, the number of test cases should be minimized as much as possible, but all very important test cases must be included.

Which of the following statements is correct?

Options:

A.

TC04, TC05, and TC06 can be deleted.

B.

TC05 and TC06 can be deleted.

C.

TC04 and TC05 can be deleted.

D.

TC03, TC04 and TC05 can be deleted.

Buy Now
Questions 95

A possible risk of introducing test automation is:

Options:

A.

the tool may not be fit-for-purpose.

B.

the tool may create additional development dependencies.

C.

the tool may not be compatible with the development platform.

D.

the tool will be owned and maintained by developers and replace testers.

Buy Now
Questions 96

Which of the following correctly represents a test first approach?

Options:

A.

Code is refactored first then tests are written and run

B.

Application behaviour is written in Given/When/then format and tests are then written and run

C.

Tests are derived from acceptance criteria and run to check that the code passes these tests

D.

First the tests fail then the code is written to pass the tests and this is iterated

Buy Now
Questions 97

Which of the following statements about estimation of the test effort is WRONG?

Options:

A.

Once the test effort is estimated, resources can be identified and a schedule can be drawn up.

B.

Effort estimate can be inaccurate because the quality of the product under tests is not known.

C.

Effort estimate depends on the budget of the project.

D.

Experience based estimation is one of the estimation techniques.

Buy Now
Questions 98

For a given set of test-cases, which of the following is a benefit of running these tests with a test automation tool?

Options:

A.

Test coverage is increased

B.

The total cost of the test project always decreases

C.

The time spent on repetitive tasks is reduced

D.

The number of found bugs is reduced

Buy Now
Questions 99

Which ONE of the following options MOST ACCURATELY describes the activities of “testing” and “debugging”?

Options:

A.

Testing triggers a failure that is caused by a defect in the software, whereas debugging is concerned with finding the causes of this failure (defects), analyzing these causes, and eliminating them.

B.

Testing triggers a failure that is caused by a defect in the software, whereas debugging is concerned with finding the causes of this failure (defects), analyzing these causes, and reproducing them.

C.

Testing identifies a defect that is caused by an error in the software, whereas debugging is concerned with finding the causes of this defect, analyzing these causes, and eliminating them.

D.

Testing triggers a defect that is caused by an error in the software, whereas debugging is concerned with finding the causes of this defect, analyzing these causes, and eliminating them.

Buy Now
Questions 100

Who of the following has the best knowledge to decide what tests in a test project should be automated?

Options:

A.

The developer

B.

The customer

C.

The development manager

D.

The test leader

Buy Now
Questions 101

As a tester, as part of a V-model project, you are currently executing some tests aimed at verifying if a mobile app asks the user to grant the proper access permissions during the installation process and after the installation process. The requirements specification states that in both cases the app shall ask the user to grant access permissions only to the camera and photos stored on the device. However, you observe that the app also asks the user to grant access permission to all contacts on the device. Consider the following items:

[I]. Test environment

[ii]. Expected result

[iii]. Actual result.

[IV] Test level.

[V]. Root cause.

Based on only the given information, which of the items listed above, are you able to CORRECTLY specify in a defect report?

Options:

A.

[l] and [IV]

B.

[ii] and [III].

C.

[ii], [iii] and [v]

D.

[ii], [IV] and [V].

Buy Now
Questions 102

Which of the following tools is most likely to detect defects in functions or methods in source code?

Options:

A.

configuration management tool

B.

unit test framework tool

C.

test design tool

D.

monitoring tool

Buy Now
Questions 103

Consider the following table, which contains information about test cases from the test management system:

ISTQB-CTFL Question 103

Which ONE of the following options organizes the test cases based on the statement coverage strategy, while considering practical constraints?

Options:

A.

{TC 20; TC 30; TC 10; TC 40; TC 50; TC 70; TC 60; TC 80; TC 90}

B.

{TC 10; TC 30; TC 20; TC 60; TC 40; TC 80; TC 90; TC 50; TC 70}

C.

{TC 80; TC 70; TC 50; TC 60; TC 20; TC 30; TC 10; TC 40; TC 90}

D.

{TC 60; TC 80; TC 40; TC 90; TC 50; TC 10; TC 70; TC 30; TC 20}

Buy Now
Questions 104

Which of the following is MOST likely to be an example of a PROJECT risk?

Options:

A.

A computation is not always performed correctly in some situations

B.

A system architecture may not support some non-functional requirements

C.

Team members' skills may not be sufficient for the assigned work

D.

Specific modules do not adequately meet their intended functions according to the user

Buy Now
Questions 105

A typical objective of testing is to ensure that:

Options:

A.

testing is used to drive the development of a software

B.

a software has been tested using a combination of test techniques

C.

there are no defects in a software that is about to be released

D.

a software has been properly covered

Buy Now
Questions 106

Which of the following statements are true?

1. Early and frequent feedback helps to avoid requirements misunderstanding.

2. Early feedback allows teams to do more with less.

3. Early feedback allows the team to focus on the most Important features.

4. Early and frequent feedback clarifies customer feedback by applying static testing techniques

Select the correct answer:

Options:

A.

3

B.

2

C.

1

D.

4

Buy Now
Questions 107

Which of the following is a CORRECT statement about how a tester should communicate about defects, test results, and other test information?

Options:

A.

Testers should include personal opinions and judgements in defect reports and review findings

B.

Testers should emphasize the benefits of testing, such as increased quality and reduced risk

C.

Testers should reject all questions about their test findings and information

D.

Testers should take a command-and-control approach with the project team

Buy Now
Questions 108

Which of the types of test tools noted below BEST describes tools that support reviews?

Options:

A.

Tools to assess data quality

B.

Tools to support usability testing

C.

Tools to support specialized testing needs

D.

Tools to support static testing

Buy Now
Questions 109

The fact that defects are usually not evenly distributed among the various modules that make up a software application, but rather their distribution tend to reflect the Pareto principle:

Options:

A.

is a false myth

B.

is expressed by the testing principle referred to as Tests wear out'

C.

is expressed by the testing principle referred to as 'Defects cluster together'

D.

is expressed by the testing principle referred to as 'Bug prediction'

Buy Now
Questions 110

Which of the following statements is the BEST example of non-functional testing?

Options:

A.

Tests which capture the time it takes to save a file

B.

Tests which calculate overtime pay for those employees entitled to such

C.

Tests related to "what" the system should do

D.

Tests based on the internal structure of a component or system

Buy Now
Questions 111

Which of the following statements about retrospectives is TRUE?

Options:

A.

Only developers and testers should be involved in retrospectives, as involving people in other roles is very likely to prevent developers and testers from having open and constructive discussions that really help identify process improvements.

B.

Retrospectives can be very effective in identifying process improvements and can also be very efficient and cost-effective especially since, unlike reviews, they do not require any follow-up activities

C.

On Agile projects, well-conducted retrospectives at the end of each iteration can help the team reduce and sometimes even eliminate the need for dairy stand-up meetings.

D.

During retrospectives, in addition to identifying relevant process improvements, participants should also consider how to implement these improvements and retain them based on the context of the project, such as the software development lifecycle.

Buy Now
Questions 112

Which of the following statements best describes the objective of branch testing?

Options:

A.

Branch testing is used to verify the functionality of an application on all logical branches without knowledge of its internal workings.

B.

Branch testing is used to check the interactive reachable branches of the user interface of an application.

C.

Branch testing is used to verify the performance of an application on certain branches.

D.

Branch testing is used to execute some or all branches in the code of an application at least once.

Buy Now
Questions 113

Which of the following statements about branch coverage is true?

Options:

A.

The minimum number of test cases needed to achieve full branch coverage, is usually lower than that needed to achieve full statement coverage

B.

If full branch coverage has been achieved, then all unconditional branches within the code have surely been exercised

C.

If full branch coverage has been achieved, then all combinations of conditions in a decision table have surely been exercised

D.

Exercising at least one of the decision outcomes for all decisions within the code, ensures achieving full branch coverage

Buy Now
Questions 114

A software application incorrectly provided customers discounts of 50% off their total purchases if the purchases exceeded S100. It was discovered through an audit that the discount should have been only 5% off these purchases. A root cause analysis uncovered that the requirements Incorrectly stated 50% instead of 5% in this scenario.

Which of the following MOST accurately reflects this scenario?

Options:

A.

The audit finding Is the root cause, the incorrect calculation of 50% Is the defect, and the Incorrect requirement Is the effect

B.

The incorrect customer discount is the effect and the reason for the requirement error is the root cause

C.

The incorrect discount is the root cause, requiring a root cause analysis which led to investigating the software code, design, and requirements

D.

A defect in the code is determined to be the root cause of the incorrect calculation

Buy Now
Questions 115

Which ONE of the following options MOST ACCURATELY describes statement testing?

Options:

A.

In statement testing, the coverage items are control flow transfers between branches. The aim is to design test cases to exercise branches in the code until an acceptable level of coverage is achieved, expressed as a percentage.

B.

In statement testing, the coverage items are decisions and statements. The aim is to design test cases that exercise statements in the code until an acceptable level of coverage is achieved, expressed as a percentage.

C.

In statement testing, the coverage items are branches, and the aim is to design test cases to exercise branches in the code until an acceptable level of coverage is achieved, expressed as a percentage.

D.

In statement testing, the coverage items are executable statements. The aim is to design test cases that exercise statements in the code until an acceptable level of coverage is achieved, expressed as a percentage.

Buy Now
Questions 116

Given the following examples of entry and exit criteria:

1.A defined level of code coverage has been achieved

2.The test automation tool has been installed and properly configured

3.The number of unresolved defects is within the predefined limit

4.The performance test environment has been set-up and is available

5.The user stories have proper acceptance criteria defined

6.The testing budget has been spent and the project sponsor bears the risk of not testing any further

Which of the following BEST categorizes them as entry and exit criteria:

Options:

A.

Entry criteria - 2, 4, 5 Entry criteria -1, 3, 4

B.

Entry criteria - 2, 4 Entry criteria - 2, 4, 5, 6

C.

Exit criteria -1,3,6 Exit criteria - 2, 5. 6

D.

Exit criteria -1,3,56 Exit criteria -1,3

Buy Now
Questions 117

Why should you choose a test technique?

Options:

A.

Because you need to match the way you test to the content of the product under test

B.

Because of the time constraints that usually accompany a test project

C.

Because this way you cover the full scope of the product's functionality

D.

Because choosing a test technique is a common practice in software testing

Buy Now
Exam Code: ISTQB-CTFL
Exam Name: ISTQB Certified Tester Foundation Level (CTFL v4.0)
Last Update: Oct 21, 2025
Questions: 399

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now ISTQB-CTFL testing engine

PDF (Q&A)

$43.57  $124.49
buy now ISTQB-CTFL pdf