KCJ Ltd is a public sector organisation planning five projects for the next financial year. Each project has a distinct cost estimation method and source of power for the project leader.
Your task is to match the correct cost estimation method and source of power to each project.
Project Descriptions
Project 1
Description: Budget estimation is calculated using an algorithm.
Project Lead’s Power: Founder of the organisation.
Project 2
Description: The Head of R&D (PhD in Data Science) is using costing from similar past projects to determine the budget.
Project Lead’s Power: Expertise in Data Science.
Project 3
Description: The project is led by a key stakeholder and involves creating a Bill of Materials. Costs are worked out item by item.
Project Lead’s Power: Authority due to stakeholder influence.
Project 4
Description: The Project Leader has calculated the base cost, most likely cost, and worst-case scenario.
Project Lead’s Power: Has the authority to cancel the project at any time.
Project 5
Description: The project leader is a well-liked Board Member who has selected a team he is comfortable with. He determined the budget based on his own research.
Project Lead’s Power: Personal relationships with team members.
In a fixed lump sum contract, this pricing mechanism does not allow for any changes in price. Is this statement TRUE?
Fixed lump sum contracts are widely used in construction and infrastructure projects.
Answer Options:
Which project management methodology outlines a process for closing a project?
Answer Options:
Skipped
Which of the following statements is true of a business that operates in a 'low-context culture' country?
Spaceman Ltd’s R&D team has a strong relationship with its supplier of spaceship parts.
The space exploration industry is becoming highly competitive.
The team is looking for ways to enhance profits and market share.
Q: What strategy should Spaceman Ltd use?
Answer Options:
Jennifer is drafting a contract with a "termination for convenience" clause.
Q: What obligations should be included in this clause? (Select all that apply.)
✔ The return of any advance payments
✔ The destruction of confidential information
✔ The smooth transition of services to a new supplier
Why might a Public Sector Organisation use a PPP style of contract to build a new police station? Select ALL that apply.