An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.
What should the agile lead recommend?
At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.
How should this situation have been prevented?
The project team is ahead of schedule and beginning lo gold-plate the feature included in the current sprint. What should the agile project manager do?
After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.
If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?
A scrum master of a team that is new to Scrum wants to share the purpose of the daily coordination meeting. What should the scrum master tell the team?
Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.
What should the team have done to avoid this?
A project's first iteration contains item A and its second iteration contains item B The first iteration is behind schedule, which will impact the second iteration. Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?
An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables: however, issues arise when the deliverables are integrated. What should the agile practitioner do?
As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.
Which two actions should the scrum master take? (Choose two.)
The team is refining user stones during the backlog grooming session and confused on the acceptance criteria and level of details What should the agile practitioner do?
An agile team notices that the same problems continue to occur during multiple iterations Several team members have suggestions to fix the problem.
What is the proper agile approach to handle this?
Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date. What should the agile practitioner do?
An executive notices a kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do?
A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.
What steps should the project leader take to improve knowledge sharing?
The coach on a new agile team notices that one team member is influencing most of the team's decisions. What should the coach do?
A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations.
What should the team do to improve the accuracy of their estimates?
A company president is concerned about the impact of a natural disaster on the company. How should management identify areas to apply its resources and mitigate potential impacts?
A user interface (UI) developer has features for channels ready for review. During the team review, the architect is disappointed that Splunk software has not been implemented for better server and client logs. The architect insists on the implementation of Splunk software, which will impact the release date.
Which one of the following is the ideal option for the team to resolve this conflict?
During the project initiation stage, a team has estimated story points for all user stories. When the project team explained the minimum marketable feature (MMF), however, they were not confident that the solution would actually work.
What can the team do to better manage this situation?
What should a scrum master do when an agile team member is behind on their tasks?
An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the Scrum Master do?
During sprint planning the product owner wants the team to prioritize and deliver a number of features which have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.
What should the project leader do?
A project manager noticed that a team member had been a consistently high performer until a few months ago. Recently, the team member seems distracted and is not performing well.
How should the project manager handle a review with the team member?
A Scrum team is visualizing the blockers that arise when they work on their activities on the kanban board. The team decided to analyze why the blockers occur so they can take action to minimize their occurrence and reduce lead times.
Which practices should the team use?
An agile coach is assigned to help a project team that was recently co-located close to a very popular business Many team members visit this business during working hours which affects team performance.
What should the agile coach do to mitigate this issue?
A company is considering developing a new, complex application that will require a large initial investment However if successful the profit potential is high.
When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?
A team member has spent 5 days on a spike and the first set of experiments has not been successful. The issue is the development team member has determined a short-term rather than a long-term solution.
What should the project leader do?
During team meetings, the team often struggles with making decisions about their technical approach. What should be done to improve the quality and timeliness of decisions?
Stakeholders have conflicting requirements, and the product owner is struggling to decide which user stories to write. What should the product owner do?
A food company seeks additional business-to-business (B2B) revenues from some customers by
implementing purchase order (PO) functionality. To achieve this, the agile project team is exploring PO integration options (see item #3 in Exhibit A), as the product increment (PI) planning process is underway.
What should the project team do next?
An agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released.
What should the agile team do?
During the advanced stages of implementing a complex design, an agile practitioner realizes that the architecture is not scalable for user requirements. The architect suggests a workaround that is minimally adequate but may cause some performance issues.
What should the agile practitioner do?
An agile team is having difficulties in obtaining the participation of a true user to be a part of their team. In the absence of a true user, the development manager steps in to act as a proxy for the user.
What can the agile team do to improve value delivery in the absence of a true user?
A project team held a working session with a finance team to understand the procurement process. After the meeting, while the agile lead was facilitating the value stream mapping exercise, one of the team members asked: "When calculating the cycle time, which factors should be considered?"
How should the agile lead respond?
A software team is developing a product in an environment with increased uncertainty. Although there is a clear vision of the goals to be achieved, the product owner is not fully certain about how some of the product features should work.
How should the product owner address this situation?
During an iteration, an agile team discovers infrastructure requirements that were not initially considered. What should the team do to effectively manage this?
A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.
What should be done to resolve this challenge?
An agile coach is working with a team that serves clients making product requests by phone. During a daily commitment and replanning meeting, a team member states that they were unable to resolve a client request because they lacked sufficient product knowledge.
What should the agile coach do?
An agile project manager is leading an international project involving a global team consisting of members from very different cultures, countries, and time zones. The agile project manager is aware that similar projects with distributed teams have led to serious conflicts.
What should the agile project manager do to promote trust and collaboration?
A Talk with the human resources (HR) department to select team members with similar backgrounds to eliminate conflict
B. Collocate for team building to promote collaboration to build trust and improve communication.
C. Promote a project charter with the project vision and purpose to help align the team.
D Promote a team charter with a set of norms rules and agreements to facilitate the work
What is a specific development practice that has been effective in implementing disciplined DevOps?
During a review session, a customer representative is concerned that a story fails to satisfy the scope of work However the product owner declares that the scope of work is complete.
What should be done with this story?
A scrum master assumes a project that is essential to organizational growth. The project is expected to be in production for three years. What should the scrum master do first?
In companies where decision making is driven by data analytics and unknown variables are addressed, what advantages does agile project execution offer over a predictive approach?
A team is preparing to demonstrate new product capabilities to a leadership team. The demonstration will show working software and a listing of the projected value of the capabilities.
What should the team do to ensure the demonstration is successful?
The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?
The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?
An agile practitioner wants to ensure that stakeholders have current information about a project's progress What should the agile practitioner do?
A project team is working with an enterprise agile center of excellence (CoE) to transition to a Scaled Agile Framework (SAFe). Many of the team members are not familiar with the new methodology and are worried that it will lead to more work and scrutiny.
What should the agile team lead do to help ensure a smooth transition?
What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?
The agile team has failed to meet their iteration goal, and contention has developed between members. The agile leader would like to determine how to improve the team's productivity and morale.
How should the agile leader address this?
A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?
A company is planning to launch a new service to improve the customer checkout experience. What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?
How can an agile team working on a new product ensure alignment with external stakeholders?
An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.
What should the agile coach do to address this requirement?
An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.
What should the agile coach do to address this requirement?
During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories. What should the team do?
During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.
What is an effective way to handle conflicting opinions in team meetings in an agile environment?
During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.
What is an effective way to handle conflicting opinions in team meetings in an agile environment?
An agile project leader notices that the team's velocity has decreased in examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses
What can happen as a result?
One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.
What should the agile practitioner do?
The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.
What should the agile practitioner do?
A team member starts discussing a project roadblock during a daily coordination meeting. The team discusses details of the impediment, which takes up most of the meeting time.
What should the agile facilitator do?
During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?
A scrum master wants to encourage better collaboration within a collocated team and is coming up with a visualization method for the project. How could the scrum master promote transparency?
A project manager is concerned that the team has misaligned expectations with some stakeholders, and that user stories were written only from a generic user's perspective. This may lead the team to miss stories for non-generic users.
What agile tools can help the team address these issues?
An agile learn has been in place (or five years and the customer is satisfied with the team's performance and deliverables. Now that the product is buill and delivered, the customer is considering the future role of the Scrum Master.
What should the customer do?
An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?
An agile practitioner notices that a project is increasing open defect counts after every subsequent iteration. What should the agile practitioner do?
A legal department representative contacts the scrum master because, while the project's budget has been maintained, it has exceeded its original contracted time and scope What should the scrum master do?
A member of a cross-functional project team is not able to attend regular status meetings and provide progress updates, which is impacting the productivity of the entire team. What should the product owner do to improve productivity?
A product owner obtains customer confirmation on product requirements and provides them to the team. After explaining the user stories, the product owner receives agreement for acceptance from the team. What should the team do next?
An event management team is following an agile approach to prepare for an upcoming conference. The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company's booth.
What should the team do?
During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.
What should the agile practitioner have done to avoid the situation?
A scrum master has a team of six members. The team complains they are losing time because they are attending meetings for which they see no value.
What should the scrum master do?
Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective.
What should the agile practitioner do?
A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?
During planning, a project team and sponsor created a visual representation of the high-level specifications of the features and user stories to be implemented in a product. Consensus was achieved on this high-level depiction of the product characteristics, but the sponsor is having difficulty understanding what to develop and when.
How should the project manager explain this to the customer and save time in the meeting?
Why should an agile coach model agile principles and behaviors, become self-aware, and be present?
Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.
What should the agile leader do next?
Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.
What should the agile leader do next?
A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.
What behavior would indicate the team is not working well together?
A development team determined the first release of a product should focus on delivering a minimally viable version of the solution. What is the most important reason the team decided to do this?
A product owner wants to create a release plan given the team is working in a chaotic environment. They want to set expectations about what is likely to be developed and in what timeframe for some of the stakeholders.
What should the product owner include in the release plan to achieve this?
An executive sponsor of a new scrum team actively attends scrum ceremonies How does this benefit the team?
A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.
What should the scrum master do?
An agile leader notices that a team member is becoming very quiet and disengaged in meetings. What should the agile leader do to identify team members' personalities and motivators?
How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?
New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities. How should the stakeholders ensure their objectives are met by product delivery?
During a daily stand up meeting, a developer expresses concerns that the selected technology limits the number of concurrent users. What should the agile team lead do?
An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.
What should the team member do?
An agile lead is working on a project to build a new product that will bring substantial business value to a company. Company executives want to present the first release at an important industry fair the following month. The agile lead started the project the previous month, and the team planned the release to take 8 iterations. For the past 4 iterations, work has been performed as planned and on time. In the current iteration, however, one team member will be out for the remainder of the project. Without this team member, velocity would drop 30%.
What should the agile lead do to ensure the release will be on time for the fair?
An agile team is building a training safety video based on current government regulations. The agile coach knows the regulations are likely to change before the release date.
How should the agile coach address this change?
An agile team is working on refining project requirements. Due to new dependencies uncovered in every working session, the team is unable to complete the detailed solution requirements. Instead of trying to complete requirements, what should the team do to work collaboratively to identify and prioritize the most important requirements and adapt to changes as needed?
A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.
What should the project lead do to help the team?
A member of the development team is working on a prioritized non-functional requirement involving integrating with a 3rd party system. This integration has not been done before on the project.
What should the project leader suggest?
What should a product owner do when a new stakeholder is complaining that they are not receiving the relevant financial data regarding the project.
A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.
What should the scrum master do?
A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.
What should the scrum master do?
A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project
deliverables could not be completed on time.
How should the project team improve during their retrospective for future implementations?
During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.
How can the project team achieve this?
A healthcare agency has contracted a vendor to provide a financial accountability solution. During a daily coordination meeting, the lead developer reports they cannot complete the stories for this iteration because the project director requested a document detailing all testing planned for the solution. The team lead met with the project director to discuss alternatives but insists they need the detailed plan by the end of that week. The team lead advises the lead developer to continue coding.
What should the team lead do next?
An agile practitioner becomes a Scrum Master on an established Scrum team. After introductions, what should the agile practitioner do?
A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.
What should the project lead do to accommodate this request?
A product's scope and acceptance criteria have been defined, and the product is planned for release at the end of the next quarter. What should the project team do next?
Midway through an iteration an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?
Some members of an agile project team work remotely, so it is difficult to have regular face-to-face backlog grooming sessions. How should the agile practitioner ensure that the team is able to reduce miscommunication and rework in this environment?
As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met. How should the project management plan be adjusted?
A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories.
What should be proposed to the team?
A new CIO advocates an agile framework for new IT projects, but the team has reservations. How should the CIO ensure that the team will be aligned with this?
During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points. How should this be handled?
The product owner of an agile project is frustrated because the team is unable to deliver as many features as expected. The product owner asks the team to reduce test-automation levels, since the quality assurance team will test the product at project completion. The product owner expects that more features will be delivered in each iteration using this approach.
What should the agile practitioner do?
During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.
What should the project leader do?
The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.
What is the estimated project conclusion?
The product owner is very concerned about work not being completed and tested before a hard release date. What can the agile team do to mitigate this risk?
A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.
How should the team address this issue?
Agile team A struggles to deliver committed stories due to technical dependencies with team B. which continuously fails to meet its delivery commitments. What should the agile team lead do?
How can the scrum master respond to a stakeholder who suggests using velocity as a metric to measure team efficiency in an agile project?
A team is delivering work as per the sprint plan, and team velocity is stabilized. However, at the end of the release, the customer is dissatisfied with project quality. What should the agile project manager have done to avoid this?
An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?
Midway through a two-week sprint, an agile team realizes that the features cannot be delivered within the sprint. The team determines that another week will be required to complete all committed features.
What should the team do?
During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.
What should the product owner do to help the team?
One of the overseas stakeholders on an agile project has not been actively involved in the project's development. What would be the first step to reengage the stakeholder?
Unable to meet a sprint's committed velocity, an agile team approaches the agile coach to define the next sprint's velocity. What should the agile coach advise?
Toward the end of a project the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected What should the product owner do?
All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)
On a complex project with a large degree of uncertainty, the team’s velocity is declining. Upon testing, it is discovered that many of the work items reported as complete are not meeting the stakeholders requirements.
Which of the following could help resolve the incomplete work?
A product owner feels that the last sprint failed to sufficiently deliver what was valuable to their organization's overall project goals. What should the scrum master mention at the next retrospective?
To create the project vision, an agile team has scheduled an initial meeting with their customer representative. What should the team bring to this meeting?
Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.
How should the agile practitioner explain to senior management the benefits of this approach?
An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?
A backlog for a project has been prioritized and a sprint has begun. A security issue has been revealed that needs to be addressed or large security vulnerabilities will be exposed.
How should the project manager proceed?
A customer and a product delivery team meet to discuss a product's attributes, goals expectations. hypothesis1 and high-level needs. What is a benefit of this meeting?
After completing the release plan, the team realizes that the project is very likely to have a negative ROI What should the team do?
An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.
What should the team do next?
A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.
Which two actions should the scrum master take as priorities? (Choose two.)
A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.
Which two actions should the scrum master take as priorities? (Choose two.)
A project team for a local government is transitioning from a predictive development life cycle to an iterative development life cycle. The project sponsor has informed the team lead that the subject matter expert (SME) for the financial functions of the solution is overallocated, so the team needs to convert the previously gathered requirements into user stories.
What should the agile lead do?
During iteration planning, it was determined that an epic should be decomposed What was the determining factor?
An agile team has started to worry because lately they have seen an increase in the number of issues. There seems to be a large variance in the quality of the work items delivered. The team now realizes that a shared understanding of quality may not exist among team members.
What should the team do?
The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project.
What should the project manager do next?
Midway through a project the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project
What should the product owner do next?
A mobile application project is halfway through development. The team reaches a stabilized velocity after 8 iterations. The sprint duration is two weeks and requirements assigned by the product owner are not changing frequently.
What is the estimated time remaining for the project?
Midway through a sprint, a scrum team member advises the team of a new requirement that may change the initial scope. What should the team do?