You need to configure the two lift kit subassembly cost requirements for production.
Which methods should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure the production requirements for the QA team. What should you configure?
You need to configure the warehouse manager's ModelA subassembly production requirements. Which setting should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure the production requirements of the controller.
What should you configure? To answer, move the appropriate configurations to the correct requirements. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
You need to set up the state control for sales of motorcycles.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to modify the production order defaults for the manufacturing execution production order Start process.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure the system for plastic operations.
Which two parts should be manually reported as finished? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
A company plans to use master planning in Dynamics 365 Supply Chain Management. The company will sell items between legal entities.
The company has several facilities across legal entities that can manufacture the same products. Same products are produced only in some plants. To meet product demand, when one facility is over capacity, another facility is used to fulfill the downstream demand.
The organizational entities are:
• LegalEntityA: Plant 1.2, and 3
• LegalEntityB: Plant4and 5
• LegalEntityC: Plant 6. 7, and 8
The following plants must be planned together:
• Plant 1. Plant 3. and Plant 4
• Plant 2. Plant 6. and Plant 8
• Plant 5 and Plant 7
You need to configure master planning for the facilities.
Which configuration mechanism should you use?
A company implements Dynamics 365 Supply Chain Management.
You run a master plan each week.
You need to resolve the issue in the scenario.
What should you do? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
A customer produces light projection toys for holiday decorations throughout the year. The production process creates the projection toy at the following work cells: stands, main assembly, electric, visuals, and packaging.
Vendors must create templates for each toy they produce each season. They must manage the transfer of templates to the warehouse. Each transfer for each vendor must use the same purchase agreement.
You need to configure the subcontracted transfer activity.
What should you do?
A pharmaceutical company is implementing Dynamics 365 Supply Chain Management.
The formulas for medication include a single active ingredient. The active ingredient will be defined with a target level and specified deviation ranges from the target.
You need to set up the active ingredient items.
Which two actions must you perform? Each answer presents a partial solution.
NOTE: Each correct selection is worth one point.
You need to set up the metal production route and BOM.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to set up the correct production solution for the assembly area. Which solution should you implement?
NO: 3 HOTSPOT
You need to configure system attributes.
Which attribute types should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure scheduling for each production area.
Which scheduling options should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
You need to set up the system to calculate the overhead rates automatically for production.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
You need to implement the scheduled Kanban requirements.
Which rules should you use? To answer, drag the appropriate rules to the correct requirements. Each rule may be used once, more than once, or not at all. You may need to drag the spirt bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
You need to configure lot number control for inventory. Which option should you use?
A discrete manufacturer uses the time and attendance registration for production operations.
All employees register daily clock in and clock out times during a 40-hour. Monday through Friday workweek.
Pay periods are every two weeks. Workers are paid hourly.
The production manager will create work schedules with the following windows:
• Mandatory work hours
• Work hours during which employees can leave early without accruing absences
• Work hours during which employees can work extra time
If a junior production worker works over 90 hours in a pay period. the worker will receive lime and a half over 80 hours. If a senior production worker works over 90 hours in a pay period, the worker will receive double time over 80 hours.
Vou need to configure the system for these requirements.
Where should you configure this functionality? To answer, drag the appropriate forms to the correct requirements. Each form may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
You need to resolve the issue for UserB.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to configure the system to meet the requirements.
What should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
A company uses multiple Dynamics 365 applications to track and repair equipment.
The company wants to improve its repair order process. Repair technicians frequently encounter unexpected issues daily. The technicians must be empowered to address the issues and create new work orders by doing the following:
• Provide step-by-step, just-in-time training for work order completion in the field by using videos and text.
• Document work order creation in a single, printable document.
• Report on the use of hands-on training.
You need to implement a solution forth requirements.
Which solution should you implement for each requirement? To answer, drag the appropriate solutions to the correct requirements. Each solution may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
You need to resolve the production manager issue.
How should you configure manufacturing execution? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure the system to meet the order requirements for unscented cleaning solution. Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to configure production operations for the pine and orange scent solutions.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to resolve the shop supervisor’s issue.
Which options should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure costing for raw materials used to manufacture unscented cleaning solution.
Which form should you use?
You need to configure production control parameters for liquid cleaning solution manufacturing.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to resolve the issue for UserE.
Which configuration options should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to determine the batch values on the combined mix batches for OperatorA.
Which values should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to resolve the issue for UserG.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure the system to track the cost and delivery performance of VendorZ.
Which two actions should you perform? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to resolve the issue for UserC.
Which two options should you configure? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to set up the chocolate items.
Which values should you select? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to create the production orders for standard model bicycles.
Which method should you use?
You need to meet the substitution requirements for User4 and User5.
What must you configure? To answer, drag the appropriate configurations to the correct substitution requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
You need to enable the features and configuration keys for the firepits.
Which two features should you enable? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point
You must ensure that the firepit product is available for sale. How should the product be released?
You need to meet the needs for the large teakwood furniture order.
What must you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to address the ignition switch issue.
Which three actions should you perform? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to configure the requirements for metal fabrication equipment maintenance. What must you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure the controller's ModelB asset requirements for the off-season.
What should you do?
You need to resolve the ModelA charging issue.
Which two configurations should you set on the work order finite capacity? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.