Winter Special Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 713PS592

PK0-005 CompTIA Project+ Certification (2024) Questions and Answers

Questions 4

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

Options:

A.

Change log

B.

Issue log

C.

Risk register

D.

Defect log

Buy Now
Questions 5

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

Options:

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Buy Now
Questions 6

Which of the following best represents the project impact to a company's brand value?

Options:

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.

The project meets the expected milestones and finishes on time and within budget.

Buy Now
Questions 7

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Options:

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Buy Now
Questions 8

Which of the following tools is best to use when conducting project meetings across time zones?

Options:

A.

Text

B.

Calendaring tools

C.

Videoconference

D.

Email

Buy Now
Questions 9

During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?

Options:

A.

Issue log

B.

Defect log

C.

Risk register

D.

Change log

Buy Now
Questions 10

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Buy Now
Questions 11

Which of the following activities are performed during the closing phase? (Select three).

Options:

A.

Requesting project charter sign-off

B.

Recognizing project team efforts and rewarding team members

C.

Working with the financial team to obtain return of investment

D.

Revoking resource credentials from the system

E.

Updating the risk register with new findings

F.

Informing the functional manager about the release of resources

G.

Monitoring project team performance

Buy Now
Questions 12

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

Options:

A.

Escalate the finding to the change control board.

B.

Add a risk to the risk register for validation.

C.

Consult the RACI matrix to identify ownership of the risk.

D.

Have a meeting with the project sponsor and main stakeholders.

Buy Now
Questions 13

Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?

Options:

A.

Percentage of controls with identified business owners

B.

Percentage of risk investments with defined business cases

C.

Ratio of control cost to operational budget

D.

Senior management satisfaction scores related to the security program

Buy Now
Questions 14

Given the following information:

PK0-005 Question 14

Which of the following represents the critical path of the project?

Options:

A.

A-C-F-I-J

B.

A-C-F-H-J

C.

A-B-D-G-J

D.

A-B-E-G-J

Buy Now
Questions 15

Which of the following tools is best to use for storing lessons learned?

Options:

A.

Whiteboard

B.

Wiki knowledge base

C.

Content management system

D.

Workflow platform

Buy Now
Questions 16

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

Options:

A.

Remove the team member's access.

B.

Release the project resources.

C.

Collect the stakeholders' feedback.

D.

Have the closeout report approved.

Buy Now
Questions 17

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options:

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Buy Now
Questions 18

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

Options:

A.

Define the WBS.

B.

Develop a RAM.

C.

Manage the vendors.

D.

Assess the resource pool.

Buy Now
Questions 19

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

Options:

A.

Hold a new backlog prioritization meeting.

B.

Add milestones to check the project's progress.

C.

Adjust the task relationship to complete coding in advance.

D.

Apply contingency buffers to the critical path.

Buy Now
Questions 20

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

Options:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Buy Now
Questions 21

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

Options:

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Buy Now
Questions 22

A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?

Options:

A.

Pareto

B.

Scatter

C.

Network

D.

Fishbone

Buy Now
Questions 23

Which of the following describes three-tier architecture?

Options:

A.

Conceptual, design, and implementation stages

B.

Presentation, application, and data processing

C.

Network, software, and security

D.

Development, testing, and production environment

Buy Now
Questions 24

Which of the following BEST describes how an organization should coordinate management of multiple related projects?

Options:

A.

Apply the SDLC process.

B.

Establish a program.

C.

Consult the CCB.

D.

Use different frameworks

Buy Now
Questions 25

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

Options:

A.

Assign more resources to complete similar stories in the future.

B.

Break the stories into workable items that can be completed within one sprint.

C.

Extend the sprint duration when required with the approval of the product owner.

D.

Release the current progress into production and carry over the rest of the code for the next sprint.

Buy Now
Questions 26

A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

Options:

A.

Project network diagram

B.

Gantt chart

C.

Issue log

D.

Risk report

Buy Now
Questions 27

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).

Options:

A.

Purchase the materials.

B.

Assign the resources.

C.

Accept delays in the work.

D.

Approve the deliverables.

E.

Monitor the performance.

F.

Negotiate with the vendors.

Buy Now
Questions 28

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

Options:

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Buy Now
Questions 29

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?

Options:

A.

Time to be fixed

B.

Impact to project

C.

Issue category

D.

Resource availability

Buy Now
Questions 30

Which of the following activities are important parts of the closing phase? (Select two).

Options:

A.

Releasing resources

B.

Locking risks

C.

Updating stakeholder register

D.

Closing contracts

E.

Completing the work breakdown structure

F.

Negotiating the next project

Buy Now
Questions 31

Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

Options:

A.

Concept of operations

B.

WBS

C.

Integrated master schedule

D.

RACI

Buy Now
Questions 32

Which of the following should be considered first when determining the privacy management for project data?

Options:

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Buy Now
Questions 33

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

Options:

A.

Memorandum of understanding

B.

Request for information

C.

Statement of work

D.

Non-disclosure agreement

Buy Now
Questions 34

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

Options:

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Buy Now
Questions 35

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

Options:

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Buy Now
Questions 36

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

PK0-005 Question 36

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Buy Now
Questions 37

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

Options:

A.

PRINCE2

B.

Scrum

C.

SAFe

D.

XP

Buy Now
Questions 38

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

Options:

A.

Development

B.

Production

C.

Testing

D.

QA

Buy Now
Questions 39

Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

Options:

A.

Telephone

B.

Videoconference

C.

Face-to-face

D.

Email

Buy Now
Questions 40

Which of the following PRINCE2 processes includes creating the project plan?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Managing product delivery

D.

Directing a project

Buy Now
Questions 41

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

Options:

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

Buy Now
Questions 42

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

Options:

A.

negotiating resources.

B.

assigning resources.

C.

assessing the resource pool.

D.

adding resources to the schedule.

Buy Now
Questions 43

A project team member wrote a user guide over the past ten days. Given the following scatter diagram.

PK0-005 Question 43

Which erf the following can be formally conducted?

Options:

A.

The team member prioritized other tasks over the completion of this task

B.

The learn member had performance issues over time.

C.

There is a negative correlation with 6me and output

D.

This is a display of units of outstanding work to predict completion

Buy Now
Questions 44

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Options:

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Buy Now
Questions 45

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

Options:

A.

Creating a backlog

B.

Managing the quality of deliverables

C.

Updating the issue log

D.

Performing a risk assessment

E.

Validating the deliverables

F.

Reconciling the project budget

Buy Now
Questions 46

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

Options:

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Buy Now
Questions 47

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

Options:

A.

Social engineering

B.

Phishing

C.

Spoofing

D.

Hacking

Buy Now
Questions 48

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

PK0-005 Question 48

B)

PK0-005 Question 48

C)

PK0-005 Question 48

D)

PK0-005 Question 48

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Questions 49

During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?

Options:

A.

Escalate the issue with the project sponsor and ask for assistance in managing the situation.

B.

Work with the vendor to achieve a compromise that benefits everyone.

C.

Approve the invoice to avoid damaging the relationship with the vendor.

D.

Schedule a call with the vendor PM and vendor executive to review the statement of work.

Buy Now
Questions 50

A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

Options:

A.

List both positively and negatively impacted stakeholders.

B.

Update the communication plan with the new findings.

C.

List the negatively impacted stakeholders only.

D.

List the positively impacted stakeholders only.

Buy Now
Questions 51

Which of the following is a quantitative key performance indicator?

Options:

A.

The project sponsor ranked the graphics of an application as four out of five.

B.

The project implements the application in ten different geographical regions.

C.

The workers complete tasks on average 25% faster using a new application.

D.

The use of a multimedia interface appeals more to users under the age of 21.

Buy Now
Questions 52

Which of the following best describes a benefit of the CI/CD process?

Options:

A.

Software delivery is sped up without compromising quality.

B.

Incremental changes are done at the end of the project.

C.

The software is integrated with other projects easily.

D.

Updates are released every sprint.

Buy Now
Questions 53

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Buy Now
Questions 54

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Buy Now
Questions 55

A system is scheduled to go live, and the client signed an SLA. Which of the following elements is part of the agreement?

Options:

A.

Resolution time

B.

Issue list

C.

Work breakdown structure

D.

Cost optimization

Buy Now
Questions 56

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?

Options:

A.

Enterprise resource planning and end user applications

B.

Electronic document and record management systems

C.

Customer relationship management and databases

D.

Content management and financial systems

Buy Now
Questions 57

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

Options:

A.

Application deployment

B.

Rollback plans

C.

Validation checks

D.

Maintenance window schedules

Buy Now
Questions 58

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

Options:

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Buy Now
Questions 59

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

Options:

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

Buy Now
Questions 60

A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?

Options:

A.

Planning

B.

Closure

C.

Initiation

D.

Execution

Buy Now
Questions 61

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

Options:

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps

Buy Now
Questions 62

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Buy Now
Questions 63

During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

Options:

A.

Status report

B.

Issue log

C.

Risk report

D.

Risk register

Buy Now
Questions 64

A project manager provided details regarding the completion of the following tasks:

Vendor selection took less time than planned.

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?

Options:

A.

Change log

B.

Project Gantt

C.

Issue log

D.

Requirements traceability matrix

Buy Now
Questions 65

Which of the following offers administrators more direct control over operating systems?

Options:

A.

Infrastructure as a service

B.

Software as a service

C.

Functions as a service

D.

Platform as a service

Buy Now
Questions 66

A team member identifies a critical issue in production. Which of the following should the project manager apply?

Options:

A.

Compliance check

B.

Release plan

C.

Rollback plan

D.

Validation check

Buy Now
Questions 67

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

Options:

A.

Evaluating the project

B.

Releasing the resources

C.

Closing the contracts

D.

Reconciling the budget

Buy Now
Questions 68

Which of the following software programs would be best to use to store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Buy Now
Questions 69

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

Options:

A.

Business collaboration tool

B.

Email

C.

Virtual meetings

D.

Enterprise CMS

Buy Now
Questions 70

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

Options:

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Buy Now
Questions 71

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

Options:

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.

Buy Now
Questions 72

Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

Options:

A.

Service-level agreement

B.

Functional testing

C.

Warranty period

D.

Audit

Buy Now
Questions 73

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

Options:

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

Buy Now
Questions 74

A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

Options:

A.

Scatter diagram

B.

Decision tree

C.

Pareto chart

D.

Histogram

Buy Now
Questions 75

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

Options:

A.

Mitigate

B.

Transfer

C.

Accept

D.

Share

Buy Now
Questions 76

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Options:

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

Buy Now
Questions 77

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

Options:

A.

Issue log

B.

Scope statement

C.

Risk report

D.

Change log

Buy Now
Questions 78

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Options:

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Buy Now
Questions 79

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

Options:

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

Buy Now
Questions 80

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

Options:

A.

Architect

B.

Project sponsor

C.

Scrum master

D.

Product owner

Buy Now
Questions 81

Which of the following BEST illustrates how team members with different roles should interact on the team?

Options:

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Buy Now
Questions 82

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

Options:

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

Buy Now
Questions 83

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

Options:

A.

Train users on the proper use of the system.

B.

Escalate the issue to the CCB

C.

Hold sessions to understand user challenges.

D.

Track system usage and report user activity.

E.

Log the issue in the project risk register.

F.

Create a memorandum of acceptable use.

Buy Now
Questions 84

Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?

Options:

A.

Storage project

B.

Computer services project

C.

Database project

D.

Multitiered architecture project

Buy Now
Questions 85

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Buy Now
Questions 86

Which of the following is the main reason for documenting artifacts?

Options:

A.

To provide a record of the project's progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

Buy Now
Questions 87

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

Options:

A.

Approving the change request

B.

Developing a rollback plan

C.

Gathering necessary resources

D.

Defining requirements

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2024)
Last Update: Nov 14, 2024
Questions: 291

PDF + Testing Engine

$64  $159.99

Testing Engine

$48  $119.99
buy now PK0-005 testing engine

PDF (Q&A)

$40  $99.99
buy now PK0-005 pdf