Pre-Summer Special Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 713PS592

PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Questions 4

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

Options:

A.

Use the Delphi technique involving experts who have identified opportunities in the past

B.

Interview more stakeholders who have a positive mindset

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

Buy Now
Questions 5

A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.

Which analytical tool should the risk manager use?

Options:

A.

Probability tree diagram

B.

Ishikawa diagram

C.

Decision tree analysis

D.

Monte Carlo simulation

Buy Now
Questions 6

While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?

Options:

A.

Present the complicated nature of the program risk responses to the sponsor for proper advice.

B.

Determine the workarounds for the program risks and allocate responsibilities to the team.

C.

Allow the most experienced program manager to handle the most critical program risks.

D.

Encourage the program team to assume risk ownership prior to delegation.

 

Buy Now
Questions 7

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board's response?

Options:

A.

Engaging the key stakeholders during the prioritization process

B.

Prioritizing the risks based on the project sponsor's risk appetite

C.

Engaging with the project sponsor before presenting to the board

D.

Working with an established industry standard prioritization method

Buy Now
Questions 8

A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.

Which type of analysis should the project manager use in this instance?

Options:

A.

Check list analysis

B.

Cause and effect

C.

Specialized meeting

D.

Quantitative analysis

Buy Now
Questions 9

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.

Reduce the probabilities of those risks on the risk register

B.

Transfer ownership of those risks to the customer

C.

Implement the risk handling strategies for those risks

D.

Request additional management reserve for those risks

Buy Now
Questions 10

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment

What should the risk manager do?

Options:

A.

Confirm the risk triggers are still valid.

B.

Ask the architect to develop acceptance criteria.

C.

Review the feature with the project team.

D.

Escalate the issue to the project board.

Buy Now
Questions 11

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

Options:

A.

Industrial studies

B.

Commercial risk databases

C.

Organizational process assets (OPAs)

D.

Enterprise environmental factors (EEFs)

Buy Now
Questions 12

A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule. One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.

What should the risk manager do to address this situation?

Options:

A.

Implement a disciplined tracking method and report to stakeholders accordingly.

B.

Call for a project team meeting to review risk strategies and make required adjustments.

C.

Escalate the staffing topic to the sponsor and request more budget for contingencies.

D.

Revisit the project charter for scope adjustments and sign them off with the customer.

Buy Now
Questions 13

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

Options:

A.

Assess the risk register to ensure the secondary risks are realistic.

B.

Assess the impact of residual and secondary risks on project objectives.

C.

Assess the change log to establish that changes were implemented.

D.

Assess the stakeholder register to determine the impact of initial risks.

 

Buy Now
Questions 14

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

Options:

A.

Reassess the design for the two pieces.

B.

Escalate the situation and request approval to move forward.

C.

Confirm the results through a second pilot.

D.

Update the assumptions log and assess the risk associated with it.

Buy Now
Questions 15

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:

A.

Avoid the risk

B.

Transfer the risk

C.

Ignore the risk

D.

Accept the risk

Buy Now
Questions 16

A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints

What should the project manager do next to determine risk impact of assumptions and constraints?

Options:

A.

Add all assumptions and constraints to the risk register.

B.

Add the risk impact of the assumptions in the risk register.

C.

Add the assumptions and constraints to the assumption log.

D.

Add the assumptions and constraints in the project charter.

Buy Now
Questions 17

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

Options:

A.

Risk mitigation

B.

Risk transfer

C.

Risk acceptance

D.

Risk avoidance

Buy Now
Questions 18

Business rhythm can fluctuate greatly between different industries and vary betweencompanies within the same industry. What should be used 10 determine how often a project's risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?

Options:

A.

The risk management plan

B.

The risk triggers

C.

The risk prioritization criteria

D.

The portfolio management plan

Buy Now
Questions 19

A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

Which kind of numerical analysis should be performed to understand the worst-case scenarios?

Options:

A.

Earned value analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Root cause analysis

Buy Now
Questions 20

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

What should the risk manager do with this risk?

Options:

A.

Put the risk on the watch list.

B.

Seek guidance from subject matter experts (SMEs).

C.

Ignore this risk as it is not critical.

D.

Inform the stakeholders about this risk.

Buy Now
Questions 21

When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

How does centralizing the risk management function help resolve the problem?

Options:

A.

Enhance the process of identification of different Individual project risks.

B.

Allows monitoring the impact against the overall project risk exposure.

C.

Establishes risk sources and ownership for trigger monitoring.

D.

Creates a single repository for all project risk documents.

Buy Now
Questions 22

The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

Options:

A.

The management team agreeing to include more resource for the digital signature initiative.

B.

The organization's professional engineers having reservations about possible information tampering.

C.

A growing number of competitors with digital signatures.

D.

An elimination of manual steps associated with recording wet signatures

E.

The growing adoption of mobile communications in the industry.

Buy Now
Questions 23

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.

How should the risk manager address this concern?

Options:

A.

Risks are documented to the practicable extent possible.

B.

Probability of the risk was very low. so the risk was not documented.

C.

Impact of the risk was assessed to be insignificant, so the risk was not documented.

D.

A similar risk never occurred in the past, so it was not considered.

 

Buy Now
Questions 24

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

Options:

A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk's response.

E.

Update and communicate assessments of the secondary risk's impact.

Buy Now
Questions 25

The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.

How should this documentation be utilized in the future?

Options:

A.

To return the remaining amount of the contingency reserve

B.

To ensure information is recorded for lessons learned

C.

To comply with the rules and regulations

D.

To hold those who created the risk accountable

Buy Now
Questions 26

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Options:

A.

Develop an affinity diagram

B.

Perform the analytical hierarchy process

C.

Perform a SWOT analysis

D.

Assign probability and impact

Buy Now
Questions 27

After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product's characteristics and quality. What should the risk manager propose to the project manager what to do?

Options:

A.

Use a predictive approach for the delivery.

B.

Use a hybrid approach for the delivery.

C.

Use an adaptive approach for the delivery.

D.

Use an agile approach for the delivery.

 

Buy Now
Questions 28

A risk manager for a hospital extension project is leading a project team in developing a risk management plan. One team member is responsible for conducting risk identification. The team member just joined the team and is struggling to ensure the coverage of all risks that might arise in this complex project.

How should the risk manager address this concern?

Options:

A.

Develop a risk breakdown structure {RBS) to identify possible risks.

B.

Develop a risk impact analysis to assess the consequences of possible risks

C.

Develop a probability and impact matrix to analyze possible risks.

D.

Create a risk register to capture and track possible risks.

 

Buy Now
Questions 29

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

Options:

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

C.

Close the risk's status on the risk register since the residual risk has now materialized.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register.

 

Buy Now
Questions 30

A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.

What should the risk manager advise the project team to do?

Options:

A.

Align the project risk thresholds with the risk appetite of a critical region.

B.

Align the project risk thresholds with the organizational risk appetite.

C.

Concentrate on the risk appetites of the influential stakeholders.

D.

Concentrate on the risk appetites of the vulnerable stakeholders.

 

Buy Now
Questions 31

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project

 

Buy Now
Questions 32

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

Options:

A.

Risk responses

B.

Risk triggers

C.

Risk registers

D.

Risk categories

Buy Now
Questions 33

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?

Options:

A.

Risk thresholds

B.

Risk response strategies

C.

Risk management reports

D.

Risk breakdown structure (RBS)

Buy Now
Questions 34

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.

What should the risk manager do next?

Options:

A.

Start a quantitative analysis to understand the impact.

B.

Crash the schedule to mitigate the risk consequences.

C.

Transfer the risk to the external team.

D.

Ask the risk owners to review the risk response plan.

Buy Now
Questions 35

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.

Advise the client that the project has exhausted contingency.

C.

Quantify the risk exposure that exceeds project contingency.

D.

Generate reports to assess and communicate the project risk level.

Buy Now
Questions 36

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.

Review potential next steps with the project team.

B.

Review the scope of work to determine the prescribed project methodology.

C.

Review the policies and practices that are outlined in the risk management plan.

D.

Review the contract and determine the resources and project funding.

Buy Now
Questions 37

An agile project manager has noticed their team's declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Introduce performance standards and evaluation methods.

B.

Clarify project goals and project contract constraints.

C.

Promote cross-training and mentoring among team members.

D.

Develop a reward system related to position and years of experience.

Buy Now
Questions 38

An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?

Options:

A.

Go for a low-risk threshold of ±5% around a cost objective.

B.

Confirm stakeholders risk thresholds based on risk appetites.

C.

Conduct risk identification to populate the risk register.

D.

Go for a high-risk threshold of ±10% around a cost objective.

 

Buy Now
Questions 39

A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

How should the project manager work with these risk handling strategies?

Options:

A.

Review and revise the strategies periodically.

B.

Implement the strategies after completing the risk analysis.

C.

Implement the strategies immediately.

D.

Ensure the strategies are approved by the stakeholders.

Buy Now
Questions 40

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

Options:

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

Buy Now
Questions 41

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Options:

A.

Issue log

B.

Change log

C.

Assumption log

D.

Risk-adjusted back log

Buy Now
Questions 42

A project manager wants to introduce a new technology to improve a project's performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.

What should the project manager do in this situation?

Options:

A.

Escalate this initiative to project decision makers and sponsors.

B.

Accept the fact that there is a risk associated with this new technology.

C.

Take advantage of this opportunity of Improving the project performance.

D.

Outsource the implementation of the new technology as soon as possible.

Buy Now
Questions 43

A stakeholder is asking a project team to hire an external vendor with more expertise and capacity to accelerate a delivery plan. The team has some concerns about this request. What should the risk manager do first?

Options:

A.

Conduct a strengths weakness, opportunities, and threats (SWOT) analysis.

B.

Create a contingency plan

C.

Start a vendor assessment

D.

Submit a change request

Buy Now
Questions 44

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

Options:

A.

Scenario-based risk analysis

B.

Quantitative risk analysis

C.

Qualitative risk analysis

D.

Monte Carlo analysis

 

Buy Now
Questions 45

During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?

Options:

A.

Contact the risk managers of the other projects and inform them

B.

Include an escalation process in the risk management plan

C.

Take note of the extensive impact of these risks in the risk register

D.

Address the unique characteristics of these risks on a case-by-case basis

Buy Now
Questions 46

What should the risk owner use as an effective information-gathering technique during the planning session?

Options:

A.

Monte Carlo analysis

B.

Update risk register

C.

Brainstorming

D.

Cost and time estimating

Buy Now
Questions 47

In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?

Options:

A.

Probabilistic and quantitative risk analyses to get the overall risk score

B.

Quantitative risk analysis to get the overall risk score

C.

Probabilistic risk analysis to get the overall risk score

D.

Qualitative risk analysis to get the overall risk score

 

Buy Now
Questions 48

A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?

Options:

A.

Earned value management (EVM) variance metrics

B.

A risk burndown chart showing remaining risks

C.

The format established in the risk management plan

D.

An itemized list of remaining risks and their scores

 

Buy Now
Questions 49

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

Options:

A.

Probability of a response triggering a secondary risk

B.

How the response will affect the quality of the components

C.

If the risk response is tied to an activity on the critical path

D.

Verify due dates for the actions have been identified

Buy Now
Questions 50

A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?

Options:

A.

Identify risks only at the project's midpoint for the stakeholders to review them

B.

Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

C.

Identify risks at the beginning of the project because the risk posture will not change

D.

Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

Buy Now
Questions 51

 

A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)

Options:

A.

Industry's standard procedures

B.

Current request for proposal (RFP)

C.

Company's historical financial reports

D.

IT infrastructure, networks, and data information

E.

Government laws and regulations

 

Buy Now
Questions 52

At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization's business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

How should the project manager handle this situation?

Options:

A.

Outsource conducting the risk response plan to risk consultants.

B.

Ask functional managers to improve their risk register and process.

C.

Adjust the risk response plans to effectively handle the identified risks.

D.

Coach the functional groups on how to properly conduct the process.

Buy Now
Questions 53

A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

Options:

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

Buy Now
Questions 54

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Options:

A.

Accept the response because there are no secondary risks were identified.

B.

The response plan should be discontinued and the risk should be accepted and dealt with if it occurs.

C.

Accept the residual risk as it is compatible with the organization's risk appetite.

D.

All identified risks must be addressed because they might significantly impact the project if they occur.

 

Buy Now
Questions 55

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis.

 

Buy Now
Questions 56

A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.

Which technique should the risk manager use?

Options:

A.

Political, economic, social, technological, legal, and environmental (PESTLE) analysis

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Decision tree analysis

D.

Cost-benefit analysis

Buy Now
Questions 57

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

Options:

A.

Residual risk

B.

Primary risk

C.

Secondary risk

D.

Normal risk

Buy Now
Questions 58

A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

Options:

A.

US$20.000 loss

B.

US$20,000 profit

C.

US$40,000 loss

D.

US$100,000 profit

Buy Now
Questions 59

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?

Options:

A.

Remove the activity padding.

B.

Review the risk response plan.

C.

Update the risk contingency plan.

D.

Update the schedule constraints.

 

Buy Now
Questions 60

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization

B.

The risk simulation

C.

The full risk description

D.

The risk response plan

Buy Now
Questions 61

A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.

What type of risk is being referred to here?

Options:

A.

Major risk

B.

Residual risk

C.

Secondary risk

D.

Environment risk

Buy Now
Questions 62

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Options:

A.

Reformed the risk monitoring and closing process properly.

B.

Created the project work plan and budget more accurately.

C.

Educated the project team on budget change requests.

D.

Communicated better with the organization's CEO.

Buy Now
Questions 63

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor's ask?

Options:

A.

Monte Carlo analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Quantitative risk analysis

Buy Now
Questions 64

 

One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.

Which risk response strategy is the program manager using in this scenario?

Options:

A.

Escalate

B.

Transfer

C.

Enhance

D.

Exploit

 

Buy Now
Questions 65

The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.

The project manager would like the risk manager to take full advantage of opportunities.

Which response should the risk manager take?

Options:

A.

Mitigate

B.

Accept

C.

Transfer

D.

Exploit

Buy Now
Questions 66

A project manager has requested the risk manager's support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.

What should the risk manager recommend?

Options:

A.

The new component should be purchased.

B.

Both options are losses to the project.

C.

Cost to expedite the execution is not worth the added risk.

D.

Perform a Monte Carlo simulation to quantify the impacts.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Apr 4, 2025
Questions: 221

PDF + Testing Engine

$66  $164.99

Testing Engine

$50  $124.99
buy now PMI-RMP testing engine

PDF (Q&A)

$42  $104.99
buy now PMI-RMP pdf