Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Prince2-Foundation PRINCE2 7 Foundation written Exam Questions and Answers

Questions 4

Which is a responsibility of a risk owner?

Options:

A.

Identify risks to the project that might occur in their department

B.

Own and authorize the use of the risk budget to fund risk responses

C.

Manage, monitor and control all aspects of an assigned risk

D.

Determine project risk appetite

Buy Now
Questions 5

Which theme estimates the cost of delivering the project?

Options:

A.

Business case

B.

Change

C.

Plans

D.

PROGEESS

Buy Now
Questions 6

What information should be recorded in the quality register?

Options:

A.

Planned activities to determine whether the products are fit for purpose

B.

Potential threats to the project's objectives and how they will be managed

C.

Lessons that the project will capture and use during the project

D.

Off-specifications that will occur during the project

Buy Now
Questions 7

Which is a minimum requirement for applying the organization theme?

Options:

A.

To document the project management team structure

B.

To define the experience required for each project role

C.

To include external stakeholders on the project board

D.

To train project team members in the use of PRINCE2

Buy Now
Questions 8

How is the tailoring approach defined for a project?

Options:

A.

The project board approves the approach

B.

The project board documents the approach

C.

Project assurance approves the approach

D.

Project assurance documents the approach

Buy Now
Questions 9

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

Options:

A.

To identify responses to risks documented in the business case

B.

To identify information about the project environment and objectives

C.

To identify the roles to be involved in risk management activities

D.

To identify uncertainties that may impact on the delivery of the project objectives

Buy Now
Questions 10

According to the 'continued business justification' principle, what must project benefits be aligned to?

Options:

A.

Regular deliveries throughout the project

B.

The business objectives

C.

The direction of the project board

D.

The technology available

Buy Now
Questions 11

Which is a minimum requirement for applying the business case theme?

Options:

A.

To provide statements of actual benefits at benefits reviews

B.

To report on project performance at project closure

C.

To define the actions required to confirm the project's benefits are realized

D.

To monitor changes to the project plan to identify exceptions

Buy Now
Questions 12

To meet the minimum requirements for applying the progress theme, what must be considered?

Options:

A.

How lessons will be learned

B.

How time-driven reports will be produced

C.

Which management products will be baselined

D.

Who is responsible for reporting on progress

Buy Now
Questions 13

Which is a factor when deciding the duration of a management stage?

Options:

A.

The work packages to be delivered

B.

The level of risk in the project

C.

The cost of the stage

D.

The number of products to be produced in the project

Buy Now
Questions 14

What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

Options:

A.

The senior user's responsibilities for realizing benefits

B.

Statements of actual versus forecast benefits at reviews

C.

The management actions needed to ensure benefits are realized

D.

No specific documents related to benefits are necessary

Buy Now
Questions 15

Which is a minimum requirement for applying the change theme?

Options:

A.

To establish a change budget to fund changes in scope

B.

To appoint the project manager as part of the change authority

C.

To define the project's approach to baselining products

D.

To record every issue that is raised in the issue register

Buy Now
Questions 16

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

Options:

A.

Creating a product flow diagram

B.

Writing the product description

C.

Writing a project product description

D.

Documenting the plan

Buy Now
Questions 17

Which process provides information for the project board to review a completed stage and confirm continued business justification?

Options:

A.

Controlling a stage

B.

Closing a project

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 18

Identify the missing words in the following sentence.

The project manager [ ? ] for day-to-day management of the project.

Options:

A.

and the project board are responsible

B.

and the team manager(s) are accountable

C.

has responsibility

D.

decides who is responsible

Buy Now
Questions 19

Which product identifies how often stakeholders require information?

Options:

A.

Communication management approach

B.

Quality management approach

C.

Change control approach

D.

Risk management approach

Buy Now
Questions 20

Which is a purpose of a quality register?

Options:

A.

To record the quality management approach for a product

B.

To issue a unique reference number for each product

C.

To detail the number and type of quality activities to be conducted

D.

To identify corrective actions that are required after an audit by quality assurance

Buy Now
Questions 21

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

Options:

A.

End Stage Report

B.

Team Plan

C.

Work Package

D.

Project Plan

Buy Now
Questions 22

Which risk response is applied on a pain/gain basis?

Options:

A.

Share

B.

Accept

C.

Exploit

D.

Enhance

Buy Now
Questions 23

As a minimum requirement for applying the risk theme, what must specifically be assessed?

Options:

A.

Whether a risk may cause the project to exceed its cost tolerance

B.

Whether a risk may affect the project-level quality tolerances

C.

Whether a risk may impact the underlying technical assumptions

D.

Whether a risk may alter the project's business justification

Buy Now
Questions 24

How does the use of product descriptions support the 'focus on products' principle?

Options:

A.

By documenting the scope tolerance for the project

B.

By documenting the quality expected by the customer

C.

By documenting the costs for the product

D.

By documenting the delivery date for the product

Buy Now
Questions 25

Which is a purpose of the 'initiating a project' process?

Options:

A.

To produce a stage plan for each stage of a multi-stage project

B.

To enable the project board to decide whether it is worthwhile to initiate a project

C.

To provide a fixed point at which acceptance for the project product is confirmed

D.

To enable an organization to understand the work needed to deliver the project's products

Buy Now
Questions 26

Which process is used to define how baselines will be established and controlled?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Initiating a project

D.

Starting up a project

Buy Now
Questions 27

Which statement describes the 'Implement' step within the recommended risk management procedure?

Options:

A.

Take planned action to respond to a risk

B.

Implement the responsibilities for risks defined in the Risk Management Strategy

C.

Assess the proximity of a risk

D.

Identify the level of risks that can be tolerated by the project

Buy Now
Questions 28

Which is a purpose of the Starting up a Project process?

Options:

A.

Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate

B.

Define the means of communication between the project and corporate or programme management

C.

Define the project controls

D.

Record any identified risks in the Risk Register

Buy Now
Questions 29

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

Options:

A.

Project mandate

B.

Initiation stage plan

C.

Project initiation documentation

D.

Project brief

Buy Now
Questions 30

Which theme verifies that a project's products are fit for purpose?

Options:

A.

Business case

B.

Organization

C.

Quality

D.

Progress

Buy Now
Questions 31

Which describes an off-specification?

Options:

A.

An interdependency between products that was previously unidentified

B.

The addition of an improvement to a product description

C.

A prototype demonstrating a possible design solution

D.

The production of more than the defined quantity of a specialist product

E.

That the right people are involved in appropriate roles

Buy Now
Questions 32

Which is part of quality control?

Options:

A.

Undertaking quality reviews

B.

Writing product descriptions

C.

Providing assurance that the project is being conducted properly

D.

Documenting the customer's quality expectations

Buy Now
Questions 33

Where should a team manager look for information about the quality required for a product?

Options:

A.

Project initiation documentation

B.

Product description

C.

Team plan

D.

Quality management approach

Buy Now
Questions 34

Which product documents the information needed to demonstrate continued business justification?

Options:

A.

Business Case

B.

Communication Management Strategy

C.

Project Product Description

D.

Quality Management Strategy

Buy Now
Questions 35

Which is an objective of the Directing a Project process?

Options:

A.

Create and authorize the project mandate

B.

Provide management control and direction

C.

Control the day-to-day running of the project

D.

Provide accurate progress information to the Project Manager

Buy Now
Questions 36

Why is it crucial that the Project Product Description clearly defines acceptance methods?

Options:

A.

Enables Project Assurance to authorize quality activities

B.

Defines how all project products will be reviewed and approved

C.

Defines how it will be proven that the completed project product meets the customer's expectations

D.

Provides confirmation that all project products have met their quality criteria

Buy Now
Questions 37

Which is a purpose of the Controlling a Stage process?

Options:

A.

Produce a Team Plan for the work to be assigned to a Team Manager

B.

Select and implement actions that will resolve deviations from a plan within tolerance

C.

Obtain approvals for products delivered in a Work Package

D.

Update a Project Plan to incorporate the actuals from a Stage Plan

Buy Now
Questions 38

What is the collective name for individuals or groups who may be affected by a project?

Options:

A.

Customers

B.

Project Support

C.

Stakeholders

D.

Team members

Buy Now
Questions 39

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

Options:

A.

Change

B.

Cross-functional

C.

Unique

D.

Risk

Buy Now
Questions 40

Which is a purpose of the Initiating a Project process?

Options:

A.

Decide if it is worthwhile to initiate a project

B.

Decide on the project approach

C.

Establish solid foundations for a project

D.

Identify the number of Work Packages required

Buy Now
Questions 41

Which is a true statement about acceptance criteria?

Options:

A.

Acceptance criteria are used to produce the customer's quality expectations

B.

Acceptance criteria are less specific and precise than customer's quality expectations

C.

Once agreed, acceptance criteria CANNOT be changed

D.

Acceptance criteria should be agreed between the customer and the supplier

Buy Now
Questions 42

Which is part of quality control?

Options:

A.

Document the project's acceptance criteria in the Project Product Description

B.

Define the quality responsibilities of those involved in the production of the products

C.

Produce quality records to show that the planned quality activities have been carried out

D.

Maintain the corporate organization's quality management system

Buy Now
Questions 43

Which of the following statements about quality assurance and Project Assurance is true?

Options:

A.

Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board

B.

Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager

C.

Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board

D.

Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Buy Now
Questions 44

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

Options:

A.

Create a separate Project Board to manage the supplier elements of the project

B.

Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.

C.

Create user and supplier groups

D.

Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board

Buy Now
Questions 45

Which is a true statement about PRINCE2 event-driven controls?

Options:

A.

Event-driven controls take place at predefined periodic intervals

B.

Event-driven controls are produced at the frequency defined in a Work Package

C.

Event-driven controls are used for decision making

D.

Checkpoint Reports are event-driven controls

Buy Now
Questions 46

What is the definition of a project outcome?

Options:

A.

A measurable improvement that is perceived as an advantage by one or more stakeholders

B.

The reason for the project

C.

The result of the change derived from using the project's outputs

D.

The project's specialist products.

Buy Now
Questions 47

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

Options:

A.

Product Description

B.

Team Plan

C.

Work Package

D.

Stage Plan

Buy Now
Questions 48

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

Options:

A.

Those with a financial interest in the project

B.

Those who will manage the project on a day-to-day basis

C.

Those who will specify the desired outputs of the project

D.

Those who will create the project's outputs

Buy Now
Questions 49

Which is a purpose of an End Project Report?

Options:

A.

Identify individuals or groups that need to be told that the project is coming to an end

B.

Review how well the project performed against the Project Initiation Documentation used to authorize it

C.

Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed

D.

Ensure that key project information is archived and made secure

Buy Now
Questions 50

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

Options:

A.

controls

B.

products

C.

project management team

D.

stages

Buy Now
Questions 51

What theme estimates the cost of delivering the project?

Options:

A.

Business Case

B.

Change

C.

Plans

D.

Progress

Buy Now
Questions 52

Which is a purpose of the Closing a Project process?

Options:

A.

Authorize the final stage of the project

B.

Confirm that all benefits defined in the Business Case have been achieved

C.

Recognize whether objectives set out in the original Project Initiation Documentation have been achieved

D.

Delegate day-to-day management of the end of the project to the Project Manager

Buy Now
Questions 53

What takes place during the Closing a Project process?

Options:

A.

The post-project benefits reviews are performed

B.

Ownership of the project's products is transferred to the customer

C.

An End Stage Report is prepared for the final stage

D.

The project closure notification is reviewed and approved

Buy Now
Questions 54

Which role is responsible for creating Checkpoint Reports?

Options:

A.

Senior Supplier

B.

Team Manager

C.

Change Authority

D.

Project Support

Buy Now
Questions 55

Which should be funded from a change budget?

Options:

A.

The Starting up a Project process

B.

A fallback plan

C.

An agreed change to the scope of a project

D.

A change to a plan, within allocated tolerances, due to poor estimating

Buy Now
Questions 56

What process aims to ensure accurate progress information is provided to the Project Manager?

Options:

A.

Starting up a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Buy Now
Questions 57

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Options:

A.

project cost tolerance

B.

stage cost tolerance

C.

Work Package cost tolerance

D.

product cost tolerance

Buy Now
Questions 58

Which product records any project outcomes perceived as negative by stakeholders?

Options:

A.

Business Case

B.

Project Plan

C.

Communication Management Strategy

D.

Project Product Description

Buy Now
Questions 59

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

Options:

A.

Raise a request for change

B.

Raise an off-specification

C.

Write an Exception Report

D.

Amend the Work Package

Buy Now
Questions 60

Which statement about the Directing a Project process is true?

Options:

A.

Provides a mechanism for the Project Board to assure that there is continued business justification

B.

Covers the day-to-day activities of the Project Manager

C.

Ensures there are regular progress meetings

D.

Begins on completion of the Initiating a Project process

Buy Now
Questions 61

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

Options:

A.

Checkpoint Report

B.

Highlight Report

C.

Issue Report

D.

Product Status Account

Buy Now
Questions 62

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

Options:

A.

Corporate group

B.

Project Board

C.

Project Assurance

D.

Executive

Buy Now
Questions 63

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

Options:

A.

Specify the desired result

B.

Provide the resources and skills to deliver the desired result

C.

Ensure the technical integrity of a project

D.

Develop a project's products

Buy Now
Questions 64

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Questions 65

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

Options:

A.

Executive

B.

Senior User

C.

Senior Supplier

D.

Project Manager

Buy Now
Questions 66

How should the Team Manager report that tolerances are forecast to be exceeded?

Options:

A.

Create an Exception Report

B.

Create a Highlight Report

C.

Raise an issue

D.

Grant a concession

Buy Now
Questions 67

Which is a recommended quality review team role?

Options:

A.

Project Manager

B.

Assurance

C.

Project Support

D.

Administrator

Buy Now
Questions 68

Which is a purpose of the Managing Product Delivery process?

Options:

A.

Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package

B.

Provide a controlled link between the Project Manager and the Team Manager(s)

C.

Enable the Project Board to request updates to the current Team Plan

D.

Establish solid foundations for the project

Buy Now
Questions 69

The senior user needs to understand how user assurance will support the senior user on the project.

Which management product should the senior user review?

Options:

A.

Project plan

B.

Project management team structure

C.

Role descriptions

D.

Project log

Buy Now
Questions 70

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project

2. To provide the required authority to initiate the project

3. To plan the work required for project initiation

4. To provide business justification for initiating the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 71

According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?

Options:

A.

Risk

B.

Scope

C.

Quality

D.

Cost

Buy Now
Questions 72

What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

Options:

A.

Benefits sustainability

B.

Product sustainability

C.

Delivery sustainability

D.

Quality sustainability

Buy Now
Questions 73

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a tear manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Buy Now
Questions 74

The project manager is acting as the team manager and needs to control the work of a team member who reports to them.

Which management product should the project manager use to control this work?

Options:

A.

A work package description

B.

The project management team structure

C.

A stage plan

D.

A work breakdown structure

Buy Now
Questions 75

The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual

products being worked on.

Which part of effective issue management is the project manager applying?

Options:

A.

Baselines

B.

Change budget

C.

Change control

D.

Issue resolution

Buy Now
Questions 76

Which term is defined as a product that will not meet is quality specifications?

Options:

A.

Off-specification

B.

Request for change

C.

Concern

D.

Problem

Buy Now
Questions 77

Which is a definition of management?

Options:

A.

Directing the execution of project tasks as agreed for the project

B.

Away of working that characterises a group of people

C.

Being accountable to the business for the success of the project

D.

The party responsible for commissioning the project

Buy Now
Questions 78

According to the guidance for effective quality management, when should the requirements for a product be captured?

Options:

A.

When the project team realizes that the product is needed

B.

When the project team needs to test the product

C.

When the project team needs to know whether the product has been approved

D.

When the project team needs to know how the product will be delivered

Buy Now
Questions 79

What is the BEST reason to perform the risk practice?

Options:

A.

To ensure risks are assigned to people who will own and action them satisfactorily

B.

To establish a supportive risk culture to enable decision-making

C.

To ensure stop-go decisions at stage boundaries are risk-informed

D.

To identiDfy and manage risks to project objectives

Buy Now
Questions 80

Which action contributes to achieving the ‘ensure continued business justification’ principle?

Options:

A.

Producing separate business cases for each customer and supplier involved in the project

B.

Defining the products that the project must produce in order to control change effectively

C.

Establishing limits of authority on the project based on defined tolerances

D.

Adapting PRINCEZ to the scale of investment and the delivery approach

Buy Now
Questions 81

The team manager has organized a workshop with project stakeholders to define the detailed requirements for a number of outputs.

Which principle is being applied by the team manager as part of the 'people’ element when holding this workshop?

Options:

A.

Focus on products

B.

Tailor to suit the project

C.

Define roles, responsibilities and relationships

D.

Ensure continued business justification

Buy Now
Questions 82

Which is definition of culture?

Options:

A.

The set of shared attitudes, values, goals, and ways of working that characterize a group of people

B.

The process when people from across the project ecosystem work together

C.

An essential aspect of project management that needs to be continually addressed

D.

The tailoring required to take into account the complexity or simplicity of a project

Buy Now
Questions 83

Identify the missing ward in the following sentence.

PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.

Options:

A.

project team

B.

project management team structure

C.

project bard

D.

project assurance

Buy Now
Questions 84

Which describes a management activity within a project?

Options:

A.

Encouraging a project team to continue working on a particularly challenging product

B.

Discussing project objectives with key stakeholders during a requirements gathering workshop

C.

Agreeing a work package with a team manager to deliver products within agreed tolerances

D.

Seeking feedback from team members to ensure they are still aligned to the project's objectives

Buy Now
Questions 85

According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?

Options:

A.

Whenever authority is delegated to the project manager, the project board should set tolerances for the stage

B.

Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board

C.

Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting

D.

Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances

Buy Now
Questions 86

When is a work breakdown structure MOST useful?

Options:

A.

When there are multiple work packages with a mix of internal and external resources

B.

in a simple project with one work package for the work of a small team

C.

When establishing a change authority aligned to project tolerances

D.

When assuring business, user and supplier aspects of project performance

Buy Now
Questions 87

What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?

Options:

A.

A project

B.

A baselined product

C.

The project scope

D.

The business

Buy Now
Questions 88

The project board needs to review whether the investment remains justified as the project progresses according to plan.

Which principle is being applied by the ‘business case' practice when the project board undertakes this review?

Options:

A.

Manage by exception

B.

Manage by stages

C.

Focus on products

D.

Tailor to suit the project

Buy Now
Questions 89

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

Options:

A.

Quality register

B.

Project plan

C.

Project product description

D.

Quality management approach

Buy Now
Questions 90

The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.

In which step of the ‘issue management technique should the change authority request this information?

Options:

A.

Deciding on changes

B.

Implementing changes

C.

Assessing issues

D.

Capturing issues

Buy Now
Questions 91

In which step of the Issue management’ technique should Superseded versions be archives?

Options:

A.

Implementing changes

B.

Assessing issues

C.

capturing issues

D.

Deciding on changes

Buy Now
Questions 92

Which TWO are objectives of the 'managing a stage boundary" process?

1. To confirm to the project board that there are no products outstanding for the stage

2. To ensure that expectations are managed via accurate reporting to the project manager during a stage

3. To ensure that the project management team is not distracted by delivering additional products during the stage

4. To request the project board to approve work to start on the next stage

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 93

Which team is defined as motivating people to achieve a project’s objectives?

Options:

A.

Leadership

B.

Management

C.

Quality assurance

D.

Co-creation

Buy Now
Questions 94

Which role is responsible for focusing on the safety and well-being of the project team?

Options:

A.

Project executive

B.

Project board

C.

Project manager

D.

Team manager

Buy Now
Questions 95

Which describes user's quality expectations?

Options:

A.

They are documented in the project product description

B.

They are documented in the quality management approach

C.

They are documented in the stage plan

D.

They are documented in the product descriptions

Buy Now
Questions 96

How is uncertainty identified, assessed and controlled?

Options:

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Buy Now
Questions 97

How is Uncertainty Identified, assessed and controlled?

Options:

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Buy Now
Questions 98

The project manager needs to document how risk management will be undertaken during the project.

In which step of the 'risk management’ technique should the project manager document this?

Options:

A.

Identify: define context and objectives

B.

Identify: identify threats and opportunities

C.

Assess: prioritize risks

D.

Assess: combine risk profile

Buy Now
Questions 99

The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

In which process should the project manager define this information?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 100

What is a purpose of the ‘organizing practice?

Options:

A.

To define who is responsible for which project activities

B.

To compare the team's actual achievements against the team plan

C.

Ta understand what the users require of the project

D.

To assess modifications raised by team members

Buy Now
Questions 101

What is a purpose of the ‘quality’ practice?

Options:

A.

To predict whether the project will deliver on time and to cost and whether the benefits will outweigh the costs

B.

To resolve off-specifications, that are Identified during the project, at the end of the project

C.

To plan the project so that there is time to deal with quality defects late in the project

D.

To identify the user's expectations and determine how the project will achieve them

Buy Now
Questions 102

How does product-based planning help to determine the project approach?

Options:

A.

By Identifying the outputs that the project trust deliver

B.

By planning in detail how to deliver the outputs over a more predictable time scale

C.

By managing constraints to the planned completion date for the project

D.

By dividing the delivery of the project's outputs into stages which do not overlap

Buy Now
Questions 103

What should the benefits management approach define?

Options:

A.

What actions will be taken to ensure the project's outcomes are achieved

B.

What will be used to record the effectiveness of the project's approaches

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Buy Now
Questions 104

Which should provide guidance on how and when prototyping is to be used?

Options:

A.

Product description

B.

Quality management approach

C.

Quality register

D.

Sustainability management approach

Buy Now
Questions 105

Which is a minimum requirement for applying the quality theme?

Options:

A.

To define the project’s approach to quality assurance

B.

To appoint external reviewers for quality reviews

C.

To define quality criteria in product descriptions

D.

To provide administrative support for quality controls

Buy Now
Questions 106

Which is a purpose of the quality theme?

Options:

A.

To establish how the project will ensure that all products created meet their requirements

B.

To establish baselines against which any changes to products can be assessed

C.

To identify all the products of the project to ensure the scope has been adequately defined

D.

To determine the communication needs of the organization’s quality assurance function

Buy Now
Questions 107

How does the ‘managing product delivery’ process achieve its purpose?

Options:

A.

By agreeing requirements for how project work should be undertaken

B.

By producing highlight reports to enable the project board to oversee the work

C.

By requiring the project manager to produce and monitor team plans

D.

By escalating issues and risks that cannot be resolved within stage tolerance

Buy Now
Questions 108

How can the risk culture of 3n organization make decision-making less effective?

Options:

A.

By using statistical modelling be understand the Impact of risks and their likelihood

B.

By establishing a risk budget to make funding risk responses actions easier

C.

By Individuals adopting an attitude that leads them to ignore threats to objectives

D.

By Involving stakeholders in assessing the likelihood and impact of each risk

Buy Now
Questions 109

What is an advantage of applying the 'learn from experience' principle?

Options:

A.

It allows the project board to delegate cost tolerances to the project manager

B.

It allows the project team to fully understand their roles and responsibilities

C.

It allows the project manager to delegate time tolerances to the team managers

D.

It allows the project team to identify improvements to be made during the project

Buy Now
Questions 110

Which process provides information for the project board to review an updated project plan?

Options:

A.

Initiating a project

B.

Controlling a stage

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 111

In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?

Options:

A.

Preparing estimates

B.

Defining and analyzing the products

C.

Organizing work packages

D.

Preparing a schedule

Buy Now
Questions 112

The project board Wants to consider whether td continue to operate in the same way, of Whether to change operations by means. of a project.

In which step of ‘business case management technique should this be considered?

Options:

A.

Develop

B.

Check

C.

Maintain

D.

Confirm

Buy Now
Questions 113

Which is a benefit of applying the ‘tailor to suit the project’ principle?

Options:

A.

Project management becomes less bureaucratic

B.

The capability of leadership is strengthened

C.

The project environment complexity is reduced

D.

The number of outputs is reduced

Buy Now
Questions 114

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 115

What is a purpose of the communication management approach?

Options:

A.

To define how the project team intends to obtain responses from stakeholders

B.

To describe the techniques required to make the project product acceptable to stakeholders

C.

To describe the target organizational state and how the business will move to that new state

D.

To describe the processes used to engage with stakeholders in identifying uncertainties

Buy Now
Questions 116

What must be produced to meet the minimum requirements when applying the change theme?

Options:

A.

A change budget for the analysis of change

B.

Records of the decisions made on all issues

C.

Documents recording the version of each product

D.

Status reports on all products being produced

Buy Now
Questions 117

According to the ‘exception management’ technique, when should the team manager raise an issue?

Options:

A.

When the team manager predicts that a product will cause a stage to exceed its time tolerance

B.

When the team manager identifies that a product is going to be delivered late

C.

when the team manager predicts that a product will cause a work package to exceed its time tolerance

D.

when the team manager identifies that the work package has already exceeded its time tolerance

Buy Now
Questions 118

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

Options:

A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

Buy Now
Questions 119

How often should the 'controlling a stage' process be used during a project?

Options:

A.

Once, for the whole project

B.

For each delivery stage in the project

C.

Whenever the project board meets

D.

Twice, for initiation and for the rest of the project

Buy Now
Questions 120

Which management product is used to record relationships between specialist products?

Options:

A.

Change control approach

B.

Configuration item record

C.

Issue register

D.

Product status account

Buy Now
Questions 121

Which is a benefit of using PRINCE2?

Options:

A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Buy Now
Questions 122

What is the change authority role permitted to authorize?

Options:

A.

Risks to the project

B.

Adjustments to the limits on the change budget

C.

Changes to stage tolerance

D.

Changes to the project that do not exceed a defined budget

Buy Now
Questions 123

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 124

Which describes a time-driven control?

Options:

A.

The dates for the project's end stage assessment included in the project plan

B.

The expected frequency of progress reports specified in a work package

C.

The expected dates for planned checks of specialist products included in a stage plan

D.

The planned exception assessment meeting to authorize a requested exception plan

Buy Now
Questions 125

In which process is the work to be done assigned to a team manager?

Options:

A.

Directing a project

B.

Managing a stage boundary

C.

Controlling a stage

D.

Managing product delivery

Buy Now
Questions 126

Which term is defined as the means by which an organization transitions from its current state to the target state?

Options:

A.

Change management

B.

change control

C.

Progress management

D.

Risk management

Buy Now
Questions 127

Which is a minimum requirement for applying the change theme?

Options:

A.

To identify whether an issue affects the continuation of the project

B.

To ensure each change is managed as an exception

C.

To produce a breakdown of the products to be produced

D.

To tailor all changes to improve the quality of the project

Buy Now
Questions 128

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 129

Which process is used by the project board to respond to on exception report?

Options:

A.

Controlling a stage

B.

Managing a stage boundary

C.

Managing product delivery

D.

Directing a project

Buy Now
Questions 130

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

Options:

A.

corporate, programme management or the customer

B.

the project board

C.

the project manager

D.

the change authority

Buy Now
Questions 131

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:

Which role should be accountable for approving these proposals?

Options:

A.

Project board

B.

Project manager

C.

Project assurance

D.

Business layer

Buy Now
Questions 132

What is a goal of the 'implement' step within the recommended risk management procedure?

Options:

A.

To prepare specific management responses to identified risks

B.

To monitor the effectiveness of actioned risk responses

C.

To estimate the risk to the project in terms of probability and impact

D.

To communicate information related to the risks faced by the project

Buy Now
Questions 133

Which is a minimum requirement for applying the organization theme?

Options:

A.

The project's approach to engaging with its stakeholders must be defined

B.

Roles must be combined to reduce the number of individuals needed on the project

C.

During a procurement the senior supplier must be appointed from the customer organization

D.

The project team must change at each end stage of the project life cycle

Buy Now
Questions 134

Who are considered as the stakeholders in a project?

Options:

A.

Only those benefitting the project

B.

Everyone in the corporate organization

C.

Everyone involved in or affected by the project

D.

Only those who are users of the products

Buy Now
Questions 135

Which process has the objective of confirming that acceptance criteria have been met?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Managing product delivery

D.

Closing a project

Buy Now
Questions 136

Which is a purpose of the 'initiating a project' process?

Options:

A.

To ensure the project has a sound basis before asking the project board to authorize the project

B.

To authorize the stage plan for the next management stage of the project

C.

To establish a contract between the project management team and the commissioning organization

D.

To ensure that prerequisites are in place before starting the project

Buy Now
Questions 137

What is the minimum number of management stages required by PRINCE2?

Options:

A.

Two stages: to initiate and to deliver the project

B.

One stage: to cover the whole project

C.

Three stages: to initiate, to deliver and to close the project

D.

Four stages: to start, to initiate, to deliver and to close the project

Buy Now
Questions 138

Which action should the project manager take during the 'assessing issues' step?

Options:

A.

Create an exception plan tor project board approval

B.

Gain project board feedback on the Issue priority

C.

Consider the impact of alternative options for resolution

D.

Determine the initial priority of the issue that has been raised

Buy Now
Exam Code: Prince2-Foundation
Exam Name: PRINCE2 7 Foundation written Exam
Last Update: Feb 17, 2025
Questions: 461

PDF + Testing Engine

$57.75  $164.99

Testing Engine

$43.75  $124.99
buy now Prince2-Foundation testing engine

PDF (Q&A)

$36.75  $104.99
buy now Prince2-Foundation pdf