Prince2-Foundation PRINCE2 7 Foundation written Exam Questions and Answers

Questions 4

Which statement about the Directing a Project process is true?

Options:

A.

Provides a mechanism for the Project Board to assure that there is continued business justification

B.

Covers the day-to-day activities of the Project Manager

C.

Ensures there are regular progress meetings

D.

Begins on completion of the Initiating a Project process

Buy Now
Questions 5

How often should the 'controlling a stage' process be used during a project?

Options:

A.

Once, for the whole project

B.

For each delivery stage in the project

C.

Whenever the project board meets

D.

Twice, for initiation and for the rest of the project

Buy Now
Questions 6

Which statement defines a risk?

Options:

A.

A certain event occurring in the future that will have a negative impact on the project's objectives

B.

An event that has already occurred that the Project Manager must deal with immediately

C.

An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives

D.

An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response

Buy Now
Questions 7

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

Options:

A.

After the executive has been appointed

B.

When authorized by the corporate, programme management or the customer

C.

Before work to start the project commences

D.

When an organization produces its business plans

Buy Now
Questions 8

Which is a purpose of the quality theme?

Options:

A.

To check that the project is viable and achievable

B.

To ensure that the project outputs are agreed

C.

To ensure that formal issues are recorded

D.

To enable the project to be managed according to plan

Buy Now
Questions 9

What is a goal of the 'implement' step within the recommended risk management procedure?

Options:

A.

To prepare specific management responses to identified risks

B.

To monitor the effectiveness of actioned risk responses

C.

To estimate the risk to the project in terms of probability and impact

D.

To communicate information related to the risks faced by the project

Buy Now
Questions 10

Which role represents the stakeholders who will operate the project's products after the project is complete?

Options:

A.

Executive

B.

Senior user

C.

Senior supplier

D.

Project manager

Buy Now
Questions 11

Which should be provided by a project mandate?

Options:

A.

Terms of reference

B.

Detailed Business Case

C.

Stage tolerances

D.

Initiation Stage Plan

Buy Now
Questions 12

Which is a recommended quality review team role?

Options:

A.

Project Manager

B.

Assurance

C.

Chair

D.

Producer

Buy Now
Questions 13

Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?

Options:

A.

Manage by exception

B.

Learn from experience

C.

Tailor to suit the project environment

D.

Defined roles and responsibilities

Buy Now
Questions 14

Which is a purpose of the 'managing a stage boundary' process?

Options:

A.

To enable the project board to approve the continuation of the project

B.

To exercise overall control over the project while delegating day-to-day management

C.

To assign work to be controlled by the team manager

D.

To define the work that needs to be done to deliver the project product

Buy Now
Questions 15

Which process provides information for the project board to review a completed stage and confirm continued business justification?

Options:

A.

Controlling a stage

B.

Closing a project

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 16

Which statement about time-driven controls is CORRECT?

Options:

A.

Time-driven controls are used for monitoring the progress of work packages and management stages

B.

Time-driven controls take place when specific events happen

C.

Time-driven controls are produced at the end of a stage

D.

An exception report is a time-driven control

Buy Now
Questions 17

Which is a minimum requirement when applying the business case theme?

Options:

A.

To specify the solution to be used to deliver the business option selected

B.

To ensure the corporate business plan is updated with the project costs and benefits

C.

To define the management actions required to ensure the project's outcomes are achieved

D.

To integrate the benefits management approach with the project and stage plans

Buy Now
Questions 18

How does the project board use the 'manage by stages' principle to control the project?

Options:

A.

By approving the project management team

B.

By reviewing project viability at defined intervals

C.

By ensuring that the benefits are managed and controlled

D.

By reviewing previous project closure documentation

Buy Now
Questions 19

Which theme verifies that a project's products are fit for purpose?

Options:

A.

Business case

B.

Organization

C.

Quality

D.

Progress

Buy Now
Questions 20

Which is part of quality control?

Options:

A.

Undertake quality reviews

B.

Write Product Descriptions

C.

Provide assurance that the project is being conducted properly

D.

Document the customer's quality expectations

Buy Now
Questions 21

Which of the following statements about stakeholders are true?

1. Someone who thinks they will be affected by a project is a stakeholder on that project.

2. Stakeholders may be internal or external to the corporate organization.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Questions 22

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

Options:

A.

Executive

B.

Senior User

C.

Senior Supplier

D.

Project Manager

Buy Now
Questions 23

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

Options:

A.

Project Brief

B.

Project Initiation Documentation

C.

Project mandate

D.

Benefits Review Plan

Buy Now
Questions 24

What is an advantage of applying the 'learn from experience' principle?

Options:

A.

It allows the project board to delegate cost tolerances to the project manager

B.

It allows the project team to fully understand their roles and responsibilities

C.

It allows the project manager to delegate time tolerances to the team managers

D.

It allows the project team to identify improvements to be made during the project

Buy Now
Questions 25

Which process has the objective of confirming that acceptance criteria have been met?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Managing product delivery

D.

Closing a project

Buy Now
Questions 26

Which action should the project manager take during the 'assessing issues' step?

Options:

A.

Create an exception plan tor project board approval

B.

Gain project board feedback on the Issue priority

C.

Consider the impact of alternative options for resolution

D.

Determine the initial priority of the issue that has been raised

Buy Now
Questions 27

According to PRINCE2, why might there be more than one business case for a project?

Options:

A.

There may be more than one management stage in the project

B.

The project may be in a commercial environment with a number of suppliers

C.

There may be more than one work package being delivered in the project

D.

The project may be in a programme environment

Buy Now
Questions 28

Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

Options:

A.

Continued business justification

B.

Defined roles and responsibilities

C.

Manage by exception

D.

Manage by stages

Buy Now
Questions 29

What may be funded from a risk budget?

Options:

A.

Corrections required due to off-specifications

B.

Impact analysis of requests for change

C.

Implementation of a fallback plan

D.

Preparation of the risk management approach

Buy Now
Questions 30

Who represents the three project interests on a project?

Options:

A.

Project manager

B.

Project support

C.

External project stakeholders

D.

Project board

Buy Now
Questions 31

Which are characteristics of stakeholders?

1. They are often affected by the project

2. They agree with every project objective

3. They are only/always external to the corporate organization

4. They typically interact with the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 32

Which describes risk probability?

Options:

A.

Level of risks which the project can tolerate before escalating to the Project Board

B.

Probable effect on the project delivering its objectives

C.

Timeframe within which the risk may occur

D.

A measure of the likelihood of the risk occurring

Buy Now
Questions 33

What problem may occur if projects are not aligned with corporate business strategy?

Options:

A.

The control of projects may be poor

B.

The outputs may be of poor quality

C.

The objectives of different projects may overlap

D.

The project management approaches used may differ

Buy Now
Questions 34

How does the project plan help to support the 'manage by stages' principle?

Options:

A.

By identifying the customer's quality expectations

B.

By defining products to ensure they are fit for purpose

C.

By identifying the major control points and milestones

D.

By estimating the timescales and costs of the project

Buy Now
Questions 35

What must a PRINCE2 project demonstrate?

Options:

A.

Application of PRINCE2 principles

B.

Application of proper leadership skills

C.

Application of the activities in each process

D.

Application of tools appropriate for the industry

Buy Now
Questions 36

Which is a responsibility of a risk owner?

Options:

A.

Identify risks to the project that might occur in their department

B.

Own and authorize the use of the risk budget to fund risk responses

C.

Manage, monitor and control all aspects of an assigned risk

D.

Determine project risk appetite

Buy Now
Questions 37

Where should a team manager look for information about the quality required for a product?

Options:

A.

Project initiation documentation

B.

Product description

C.

Team plan

D.

Quality management approach

Buy Now
Questions 38

Which activity takes place within the Managing a Stage Boundary process?

Options:

A.

Produce Highlight Reports

B.

Take corrective action within the limits of a stage's tolerance

C.

Produce an Exception Plan

D.

Authorize a Stage Plan for the next stage

Buy Now
Questions 39

What is a supplier of a PRINCE2 project responsible for?

Options:

A.

Providing the project mandate

B.

Providing resources to deliver the project outputs

C.

Establishing the project's governance

D.

Realizing the benefits from the project

Buy Now
Questions 40

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

Options:

A.

Managing Product Delivery

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Starting up a Project

Buy Now
Questions 41

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

Options:

A.

change budget

B.

project budget

C.

project's cost tolerance

D.

project's risk tolerance

Buy Now
Questions 42

Which is an objective of the 'managing a product delivery' process?

Options:

A.

To ensure the business case is regularly reviewed

B.

To assess whether the stage products have been approved

C.

To deliver the planned specialist products within tolerance

D.

To request authorization to start the next stage

Buy Now
Questions 43

In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

Options:

A.

Directing a project

B.

Managing product delivery

C.

Managing a stage boundary

D.

Initiating a project

Buy Now
Questions 44

How is the tailoring approach defined for a project?

Options:

A.

The project board approves the approach

B.

The project board documents the approach

C.

Project assurance approves the approach

D.

Project assurance documents the approach

Buy Now
Questions 45

Which is an objective of the 'initiating a project' process?

Options:

A.

To ensure that baselines are established and controlled

B.

To ensure that the business case is kept under review

C.

To ensure that the planned products are delivered within tolerances

D.

To ensure that user acceptance of the products is confirmed

Buy Now
Questions 46

Identify the missing word in the following sentence.  

A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.

Options:

A.

benefits

B.

dis-benefits

C.

issues

D.

risks

Buy Now
Questions 47

Why is a project brief produced?

Options:

A.

To act as a trigger for the 'starting up a project' process

B.

To record the how the project will communicate with its stakeholders

C.

To provide a full and firm foundation for the initiation of a project

D.

To be used by the project board as a basis for reviewing the progress of a project

Buy Now
Questions 48

Which is part of quality control?

Options:

A.

Undertaking quality reviews

B.

Writing product descriptions

C.

Providing assurance that the project is being conducted properly

D.

Documenting the customer's quality expectations

Buy Now
Questions 49

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

Options:

A.

Appointing the project board and producing the project brief

B.

Planning the initiation stage and appointing the project manager

C.

Producing the additional role descriptions and validating the project product description

D.

Verifying the project approach and capturing previous lessons

Buy Now
Questions 50

Which product describes the method the project will use to engage with corporate, programme management or the customer?

Options:

A.

Quality management approach

B.

Communication management approach

C.

Change control approach

D.

Benefits management approach

Buy Now
Questions 51

When is a work breakdown structure MOST useful?

Options:

A.

When there are multiple work packages with a mix of internal and external resources

B.

in a simple project with one work package for the work of a small team

C.

When establishing a change authority aligned to project tolerances

D.

When assuring business, user and supplier aspects of project performance

Buy Now
Questions 52

How does PRINCE2 ensure that the specific management needs of an organization are met?

Options:

A.

By incorporating tailoring

B.

By mandating training

C.

By focusing on viability

D.

By representing best practice

Buy Now
Questions 53

In which process are the key decisions to control the project made?

Options:

A.

Directing a project

B.

Initiating a project

C.

Managing a stage boundary

D.

Controlling a stage

Buy Now
Questions 54

As part of the 'business case management’ technique, how is the business case maintained during the project lifecycle?

Options:

A.

By linking the outcomes and benefits to the business objectives included in the business case

B.

By updating the business case during each management stage, as actual costs are incurred

C.

By providing a robust justification for the entire project in a detailed business case

D.

By justifying to the project board that the project should be initiated

Buy Now
Questions 55

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

Options:

A.

Off-specifications

B.

Follow-on action recommendations

C.

Issue Register

D.

Risk Register

Buy Now
Questions 56

Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

Options:

A.

Stage Plan

B.

Communication Management Strategy

C.

Follow-on action recommendations

D.

Quality Management Strategy

Buy Now
Questions 57

Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Questions 58

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

Options:

A.

Benefits

B.

Quality

C.

Risk

D.

Scope

Buy Now
Questions 59

What is a purpose of the communication management approach?

Options:

A.

To document the target organizational state required for the project to meet its objectives

B.

To document how the project team should control its interaction with stakeholders

C.

To document how to use financial incentives to motivate project team members

D.

To document the responsibilities of project team members for testing whether products are acceptable to users

Buy Now
Questions 60

Which theme estimates the cost of delivering the project?

Options:

A.

Business case

B.

Change

C.

Plans

D.

PROGEESS

Buy Now
Questions 61

Who should act as the communication channel between a project and corporate or programme management?

Options:

A.

Project Board

B.

Project Assurance

C.

Project Manager

D.

Project Support

Buy Now
Questions 62

Which is a typical core activity within configuration management?

Options:

A.

Issue management

B.

Quality inspection

C.

Identification

D.

Preparation

Buy Now
Questions 63

Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

Options:

A.

a corporate

B.

a temporary

C.

an external

D.

a technical

Buy Now
Questions 64

How many management stages should a PRINCE2 project consist of?

Options:

A.

Start up stage, initiation stage and at least one other management stage to cover the remainder of the project

B.

Start up stage, at least one other management stage to cover the remainder of the project and a closing stage

C.

Initiation stage and at least one other management stage to cover the remainder of the project

D.

Start up stage, initiation stage and a closing stage

Buy Now
Questions 65

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

Options:

A.

Change

B.

Cross-functional

C.

Unique

D.

Risk

Buy Now
Questions 66

Which should be funded from a change budget?

Options:

A.

The Starting up a Project process

B.

A fallback plan

C.

An agreed change to the scope of a project

D.

A change to a plan, within allocated tolerances, due to poor estimating

Buy Now
Questions 67

Which does the Executive need to ensure is in place before the project is initiated?

Options:

A.

All Work Packages are authorized

B.

An understanding of how the project will contribute to corporate objectives

C.

The Project Plan has been approved

D.

The Project Initiation Documentation is complete

Buy Now
Questions 68

Which is a purpose of a Project Product Description?

Options:

A.

Records the costs and timescales for delivery of the project's final product

B.

Shows the dependencies between the project's products to aid planning

C.

Provides a list of all the products to be delivered by the project

D.

Defines what the project must deliver in order to gain acceptance

Buy Now
Questions 69

How should the Team Manager report that tolerances are forecast to be exceeded?

Options:

A.

Create an Exception Report

B.

Create a Highlight Report

C.

Raise an issue

D.

Grant a concession

Buy Now
Questions 70

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Questions 71

Identify the missing words in the following sentence.

The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

Options:

A.

project assurance

B.

the project board

C.

the corporate, programme management or the customer

D.

a team manager

Buy Now
Questions 72

Which is a minimum requirement for applying the change theme?

Options:

A.

To identify whether an issue affects the continuation of the project

B.

To ensure each change is managed as an exception

C.

To produce a breakdown of the products to be produced

D.

To tailor all changes to improve the quality of the project

Buy Now
Questions 73

Which management level should approve a course of action if project-level tolerance is exceeded?

Options:

A.

Corporate, programme management or the customer

B.

Project board

C.

Project manager

D.

Team manager

Buy Now
Questions 74

Which management product is used to record relationships between specialist products?

Options:

A.

Change control approach

B.

Configuration item record

C.

Issue register

D.

Product status account

Buy Now
Questions 75

Which is a minimum requirement for applying the 'change' theme?

Options:

A.

Specify in the change control approach the means by which project products will be protected

B.

Document the format and contents of the issue register

C.

Produce issue reports to document the impact assessment for requests for change

D.

Delegate the change authority to the senior supplier(s) for supplier off-specifications

Buy Now
Questions 76

What is a risk actionee responsible for?

Options:

A.

Identifying risks to the project that might occur in their department

B.

Owning and authorizing the use of the risk budget to fund risk responses

C.

Managing, monitoring and controlling of all aspects of an assigned risk

D.

Carrying out a risk response action to respond to a particular risk

Buy Now
Questions 77

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 78

The project manager has created a list of tasks to produce the project's products.

Which step of the ‘organizational design and development’ technique should be informed ty this 1st?

Options:

A.

Design the project ecosystem

B.

Understand the organizational ecosystem

C.

Manage the ongoing changes to the project ecosystem

D.

Develop the project ecosystem

Buy Now
Questions 79

Which is a feature of PRINCE2?

Options:

A.

It is naturally right=sized to the scale of every project

B.

It promotes improving processes for every project

C.

It replaces the need to apply specialist Industry-specific lifecycles

D.

It focuses on completing the project on time as its main objective

Buy Now
Questions 80

Which statement about capability and competency within a project is CORRECT?

Options:

A.

People who appear to have the same skills and experience will probably undertake the same tasks in different ways

B.

People within a team will perform equally when working with different people

C.

People who have participated in developing ways of working are more willing to be managed

D.

People working as team members often have conflicting priorities contrary to the project's needs

Buy Now
Questions 81

The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.

Which element of effective business case management is the senior user applying?

Options:

A.

Aligning products to business objectives and tolerances

B.

The business case lifecycle

C.

Establishing business justification

D.

Planning benefit reviews during the project

Buy Now
Questions 82

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

Options:

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority

Buy Now
Questions 83

Which management product Soul guide the Project management team on how to manage multiple aspects of the project?

Options:

A.

Project initiation documentation

B.

Project plan

C.

Business case

D.

Exception plan

Buy Now
Questions 84

Which is a feature of an effective project team?

Options:

A.

It should rely on the team sitting together in order to easily build effective working relationships

B.

It should consist of people with a wide range of skills, abilities and viewpoints

C.

It should plan and control effective communications with the project's stakeholders

D.

It should consist of full-time team members who can focus attention on the project's needs

Buy Now
Questions 85

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

Buy Now
Questions 86

What is the result of the change derived from using the project’s product?

Options:

A.

Benefit

B.

Dis-benefit

C.

Outcome

D.

Output

Buy Now
Questions 87

Which is an objective of the ‘directing a project’ process?

Options:

A.

To tailor the project’s products and roles so that the project suits the circumstances

B.

To respond to the project mandate by starting up a project

C.

To provide an interface between the project and corporate management

D.

To ensure the stage products are delivered to the stated quality standards

Buy Now
Questions 88

The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?

Options:

A.

Gathering user inputs

B.

Accepting products

C.

Describing the quality management approach

D.

controlling quality

Buy Now
Questions 89

Identify the missing words in the following sentence.

The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

Options:

A.

benefits, change, risk,

B.

benefits, quality, risk,

C.

change, quality, risk,

D.

benefits, change, quality,

Buy Now
Questions 90

Identify the missing word in the following sentence.

[ ? ] is the measurable decline resulting from a negative outcome.

Options:

A.

An exception

B.

A dis-benefit

C.

An off-specification

D.

A risk

Buy Now
Questions 91

Which statement about the length of management stages in a project is CORRECT?

Options:

A.

A higher level of major risk will require a stage to be longer

B.

Stage length is influenced by project board availability

C.

A higher level of major risk will require a stage to be shorter

D.

Use of management stages represents a time driven control

Buy Now
Questions 92

Why does the project board review the PID during an end stage assessment?

Options:

A.

To confirm that project controls are adequate for the remainder of the project

B.

To notify the commissioning organization that the project has been authorized

C.

To review summarized progress to date and decide what to do next with the project

D.

To ensure that post-project reviews of operational performance are planned

Buy Now
Questions 93

Which describes a time-driven control?

Options:

A.

The dates for the project's end stage assessment included in the project plan

B.

The expected frequency of progress reports specified in a work package

C.

The expected dates for planned checks of specialist products included in a stage plan

D.

The planned exception assessment meeting to authorize a requested exception plan

Buy Now
Questions 94

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

Options:

A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

Buy Now
Questions 95

What statement describes how the project manager should ensure effective communication within a project?

Options:

A.

Use a more structured approach to communication with co-located teams, then remote teams

B.

Rely on regular reporting by team managers to determine whether the work Is on track

C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication

D.

Focus on publishing standard messages to key influencers throughout the project

Buy Now
Questions 96

What 15the purpose of the ‘progress! practice?

Options:

A.

To review whether the use of the products is likely to lead to the expected benefits

B.

To define the roles and responsibilities for monitoring progress

C.

To measure actual achievements against the planned time and cost targets for the project

D.

To control events that could have a positive or negative effect on project objectives

Buy Now
Questions 97

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

Options:

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Buy Now
Questions 98

What is an advantage of dividing the project into stages?

Options:

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage

Buy Now
Questions 99

Which process is used by the project board to respond to on exception report?

Options:

A.

Controlling a stage

B.

Managing a stage boundary

C.

Managing product delivery

D.

Directing a project

Buy Now
Questions 100

What is the change authority role permitted to authorize?

Options:

A.

Risks to the project

B.

Adjustments to the limits on the change budget

C.

Changes to stage tolerance

D.

Changes to the project that do not exceed a defined budget

Buy Now
Questions 101

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 102

Which is a minimum requirement when applying the 'risk' theme?

Options:

A.

To identity and ring-fence an explicit risk budget within the project's budget

B.

To describe the probability impact grid in the risk management approach

C.

To appoint project assurance to maintain the risk register during initiation

D.

To assess if risks might have a material impact on business justification

Buy Now
Questions 103

What must be done for a project to be a PRINCE2 project?

Options:

A.

The project must form part of a programme or portfolio

B.

The project must meet the minimum requirements for applying the themes

C.

The project must use the recommended approach to planning

D.

The project roles must be combined wherever possible

Buy Now
Questions 104

Which is 3 purpose of the ‘plans! practice?

Options:

A.

To enable an event that requires project management consideration to be controlled

B.

To provide the standards against which the project products can be quality controlled

C.

To provide the basis of control against which a project's progress can be monitored

D.

To enable control of opportunities and threats, that could Impact on delivery of the business objectives

Buy Now
Questions 105

Which is a purpose of the quality theme?

Options:

A.

To establish how the project will ensure that all products created meet their requirements

B.

To establish baselines against which any changes to products can be assessed

C.

To identify all the products of the project to ensure the scope has been adequately defined

D.

To determine the communication needs of the organization’s quality assurance function

Buy Now
Questions 106

Which statement BEST describes how approved plans enable control?

Options:

A.

By defining the quality specifications of individual products in product descriptions

B.

By enabling the controlled consideration of business opportunities

C.

By defining the benefits that need to be realized through the benefits management approach

D.

By defining what is within the approved project scope to avoid scope creep

Buy Now
Questions 107

Which TWO are objectives of the 'closing a project’ process?

1. To confirm to the project board that each stage’s products are approved

2. To review whether the project was delivered within time and cost tolerances

3. To confirm whether operational staff are happy to take ownership of the products

4. To confirm that there is authority to close the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 108

Which member of the project management team should secure funding for the project before the project stars?

Options:

A.

Project executive

B.

Project manager

C.

Senior user

D.

senior supplier

Buy Now
Questions 109

Identify the missing word(s) in the following sentence:

[ ? ] dependency is one between two products of a project, over which the project team has control.

Options:

A.

An internal

B.

A schedule-driven

C.

An external

D.

A resource-driven

Buy Now
Questions 110

Which should define how tools will be used to support the information needs of the project team?

Options:

A.

Digital and data management approach

B.

Quality management approach

C.

Issue management approach

D.

Commercial management approach

Buy Now
Questions 111

In which process should the specified quality methods he used to/prove that a product meets its quality criteria?

Options:

A.

Managing product delivery

B.

controlling a stage

C.

Managing a stage boundary

D.

closing a project

Buy Now
Questions 112

Identify the missing word in the following sentence.

An (?) is the result of change, normally affecting real-world behavior and circumstances:

Options:

A.

outcome

B.

exception

C.

output

D.

off-specification

Buy Now
Questions 113

Which term is defined as a product that will not meet is quality specifications?

Options:

A.

Off-specification

B.

Request for change

C.

Concern

D.

Problem

Buy Now
Questions 114

What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

Options:

A.

Benefits sustainability

B.

Product sustainability

C.

Delivery sustainability

D.

Quality sustainability

Buy Now
Questions 115

Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?

Options:

A.

Outcome

B.

Benefit

C.

output

D.

Request for change

Buy Now
Questions 116

Which action contributes to achieving the ‘ensure continued business justification’ principle?

Options:

A.

Producing separate business cases for each customer and supplier involved in the project

B.

Defining the products that the project must produce in order to control change effectively

C.

Establishing limits of authority on the project based on defined tolerances

D.

Adapting PRINCEZ to the scale of investment and the delivery approach

Buy Now
Questions 117

According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?

Options:

A.

Whenever authority is delegated to the project manager, the project board should set tolerances for the stage

B.

Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board

C.

Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting

D.

Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances

Buy Now
Questions 118

The project manager needs to understand what makes the outputs acceptable to the users.

In which step of the 'planning' technique should this occur?

Options:

A.

Defining and analysing the products

B.

Organizing work packages

C.

Preparing estimates

D.

Preparing a schedule

Buy Now
Questions 119

Which plan is used to organize and control the work when executing a work package?

Options:

A.

team plan

B.

A stage plan

C.

A project plan,

D.

An exception plan

Buy Now
Questions 120

How should effective issue management be applied When changing management products?

Options:

A.

By changing the issue management approach at the end of each stage to reflect lessons

B.

By creating new versions of a management product when a change is approved

C.

By Implementing a change budget to fund changes to the project product

D.

By recording the required change to a management product as an off-specification

Buy Now
Questions 121

Which TWO are objectives of the closing a project: process?

1. To ensure the benefit reviews enable the project benefits to the confirmed

2. To update the business case so that the project hoard can decide whether to continue with the project

3. To ensure that the project team deliver the products to quality expectations

4. To hand over any open threats to operations

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 122

Which is a definition of management?

Options:

A.

Directing the execution of project tasks as agreed for the project

B.

Away of working that characterises a group of people

C.

Being accountable to the business for the success of the project

D.

The party responsible for commissioning the project

Buy Now
Questions 123

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project

2. To provide the required authority to initiate the project

3. To plan the work required for project initiation

4. To provide business justification for initiating the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 124

The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual

products being worked on.

Which part of effective issue management is the project manager applying?

Options:

A.

Baselines

B.

Change budget

C.

Change control

D.

Issue resolution

Buy Now
Questions 125

The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.

Options:

A.

Benefits management approach

B.

Business case

C.

Quality management approach

D.

End project report

Buy Now
Questions 126

Which is definition of culture?

Options:

A.

The set of shared attitudes, values, goals, and ways of working that characterize a group of people

B.

The process when people from across the project ecosystem work together

C.

An essential aspect of project management that needs to be continually addressed

D.

The tailoring required to take into account the complexity or simplicity of a project

Buy Now
Questions 127

Which action should the project manager take when reviewing progress to assess the 'health' of a stage?

Options:

A.

Capture lessons that may assist in the monitoring and control of this project

B.

Review the quality of the relationships in the organizational

C.

Increase the frequency of event-driven controls to monitor stage progress

D.

Identify whether issues are resolved in a timely manner or left unmanaged

Buy Now
Questions 128

What statement describes how the project manager should ensure effective communication within a project?

Options:

A.

Ensure all stakeholders receive the same project information to maintain alignment

B.

Rely on regular reporting by team managers to determine whether the work is on track

C.

Focus on publishing standard messages to key influencers throughout the project

D.

Ensure communication is tailored to meet the needs of different stakeholders

Buy Now
Questions 129

What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?

Options:

A.

A project

B.

A baselined product

C.

The project scope

D.

The business

Buy Now
Questions 130

Where should individual quality control activities, such as testing and reviews, be scheduled within a PRINCE2 project?

Options:

A.

As quality tolerances in product descriptions

B.

In the quality management approach to define quality standards

C.

As acceptance criteria in the project product description

D.

In stage or team plans to allow more accurate scheduling

Buy Now
Questions 131

Which is NOT a purpose of the Organization theme?

Options:

A.

Define a project management team structure

B.

Define the level of tolerance for each level of the project management team

C.

Define the Project Board's responsibility for directing the project

D.

Define which role is accountable for the project's success

Buy Now
Questions 132

Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.

Options:

A.

Management strategies

B.

Plan

C.

Stakeholder interests

D.

Time-driven controls

Buy Now
Questions 133

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:

A.

Progress

B.

Change

C.

Organization

D.

Quality

Buy Now
Questions 134

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

Options:

A.

Corporate group

B.

Project Board

C.

Project Assurance

D.

Executive

Buy Now
Questions 135

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

Options:

A.

Closing a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Buy Now
Questions 136

Which is a purpose of the Managing Product Delivery process?

Options:

A.

Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package

B.

Provide a controlled link between the Project Manager and the Team Manager(s)

C.

Enable the Project Board to request updates to the current Team Plan

D.

Establish solid foundations for the project

Buy Now
Questions 137

Which plan provides the Business Case with costs during the Initiating a Project process?

Options:

A.

Initiation Stage Plan

B.

Project Plan

C.

Stage Plan

D.

Team Plan

Buy Now
Questions 138

Which is a purpose of the Closing a Project process?

Options:

A.

Authorize the final stage of the project

B.

Confirm that all benefits defined in the Business Case have been achieved

C.

Recognize whether objectives set out in the original Project Initiation Documentation have been achieved

D.

Delegate day-to-day management of the end of the project to the Project Manager

Buy Now
Questions 139

Which is a purpose of the Controlling a Stage process?

Options:

A.

Produce a Team Plan for the work to be assigned to a Team Manager

B.

Select and implement actions that will resolve deviations from a plan within tolerance

C.

Obtain approvals for products delivered in a Work Package

D.

Update a Project Plan to incorporate the actuals from a Stage Plan

Buy Now
Questions 140

Which is a purpose of an End Project Report?

Options:

A.

Identify individuals or groups that need to be told that the project is coming to an end

B.

Review how well the project performed against the Project Initiation Documentation used to authorize it

C.

Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed

D.

Ensure that key project information is archived and made secure

Buy Now
Questions 141

Which is an objective of the Managing Product Delivery process?

Options:

A.

Sign-off completed Work Packages

B.

Ensure the Business Case is kept under review

C.

Report progress to the Project Board

D.

Ensure that work on products is authorized and agreed with the team

Buy Now
Questions 142

Which is a purpose of the Quality theme?

Options:

A.

Establish how the project will ensure that all products created meet their requirements

B.

Establish quality assurance to maintain the quality management system

C.

Identify all the products of the project to ensure the scope has been adequately defined

D.

Determine the communication needs of the organization's quality assurance function

Buy Now
Exam Code: Prince2-Foundation
Exam Name: PRINCE2 7 Foundation written Exam
Last Update: May 4, 2026