According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?
What is a goal of the 'implement' step within the recommended risk management procedure?
Which role represents the stakeholders who will operate the project's products after the project is complete?
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?
Which process provides information for the project board to review a completed stage and confirm continued business justification?
How does the project board use the 'manage by stages' principle to control the project?
Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
Which process has the objective of confirming that acceptance criteria have been met?
Which action should the project manager take during the 'assessing issues' step?
According to PRINCE2, why might there be more than one business case for a project?
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?
Which are characteristics of stakeholders?
1. They are often affected by the project
2. They agree with every project objective
3. They are only/always external to the corporate organization
4. They typically interact with the project
What problem may occur if projects are not aligned with corporate business strategy?
Where should a team manager look for information about the quality required for a product?
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
Identify the missing word in the following sentence.
A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.
If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?
Which product describes the method the project will use to engage with corporate, programme management or the customer?
How does PRINCE2 ensure that the specific management needs of an organization are met?
As part of the 'business case management’ technique, how is the business case maintained during the project lifecycle?
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
Who should act as the communication channel between a project and corporate or programme management?
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
Which does the Executive need to ensure is in place before the project is initiated?
How should the Team Manager report that tolerances are forecast to be exceeded?
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
Identify the missing words in the following sentence.
The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.
Which management level should approve a course of action if project-level tolerance is exceeded?
Which management product is used to record relationships between specialist products?
What does the communication management approach define?
1. How versions of products will be described on information sent to interested parties
2. How information should be sent to interested parties
3. How often information should be sent to interested parties
4. How the PRINCE2 roles will be combined during the project
The project manager has created a list of tasks to produce the project's products.
Which step of the ‘organizational design and development’ technique should be informed ty this 1st?
The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.
Which element of effective business case management is the senior user applying?
When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?
Which management product Soul guide the Project management team on how to manage multiple aspects of the project?
How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?
The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
Identify the missing word in the following sentence.
[ ? ] is the measurable decline resulting from a negative outcome.
When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.
What statement describes how the project manager should ensure effective communication within a project?
According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?
What should be recorded in a quality register?
1. Activities to ensure the products are fit for purpose
2. Identified threats and opportunities
3. Problems and concerns to be managed informally
4. Roles responsible for reviewing the project's products
Which TWO are objectives of the 'closing a project’ process?
1. To confirm to the project board that each stage’s products are approved
2. To review whether the project was delivered within time and cost tolerances
3. To confirm whether operational staff are happy to take ownership of the products
4. To confirm that there is authority to close the project
Which member of the project management team should secure funding for the project before the project stars?
Identify the missing word(s) in the following sentence:
[ ? ] dependency is one between two products of a project, over which the project team has control.
Which should define how tools will be used to support the information needs of the project team?
In which process should the specified quality methods he used to/prove that a product meets its quality criteria?
Identify the missing word in the following sentence.
An (?) is the result of change, normally affecting real-world behavior and circumstances:
Which term is defined as a product that will not meet is quality specifications?
What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?
Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?
Which action contributes to achieving the ‘ensure continued business justification’ principle?
According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?
The project manager needs to understand what makes the outputs acceptable to the users.
In which step of the 'planning' technique should this occur?
Which plan is used to organize and control the work when executing a work package?
How should effective issue management be applied When changing management products?
Which TWO are objectives of the closing a project: process?
1. To ensure the benefit reviews enable the project benefits to the confirmed
2. To update the business case so that the project hoard can decide whether to continue with the project
3. To ensure that the project team deliver the products to quality expectations
4. To hand over any open threats to operations
Which TWO are objectives of the ‘starting up a project’ process?
1. To provide an interface between the corporate layer and the project
2. To provide the required authority to initiate the project
3. To plan the work required for project initiation
4. To provide business justification for initiating the project
The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual
products being worked on.
Which part of effective issue management is the project manager applying?
The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.
Which action should the project manager take when reviewing progress to assess the 'health' of a stage?
What statement describes how the project manager should ensure effective communication within a project?
What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?
Where should individual quality control activities, such as testing and reviews, be scheduled within a PRINCE2 project?
Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Which plan provides the Business Case with costs during the Initiating a Project process?