A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?
Who has the final decision about the order of items in the Product Backlog? (Choose the best answer.)
The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?
Which approach is best for Scrum Teams in order to produce valuable Increments? (Choose the best answer.)
Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?
What does it mean for a Scrum Team to be cross-functional?
(choose the best answer)
What is the function or purpose of management in Scrum?
(choose the best answer)
When a Development Team determines that it will not be able to finish the complete forecast, who has to be
present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
A Scrum Master is introducing Scrum to a new Development Team. The Development Team gas decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?
An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)
When multiple Scrum Teams are working on a single product, what best describes the
Definition of Done?
(choose the best answer)
How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning?
(choose the best answer)
What is the function or purpose of management in Scrum?
(choose the best answer)
Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?
You are the Scrum Master on a newly formed Scrum Team. Which three of the following activities would probably help the team in starting up? (Choose three.)
If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?
The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.
Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams? (Choose three.)
Who is accountable for tracking the remaining work toward the Sprint Goal? (Choose the best answer.)
When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?
Who is accountable for managing the progress ot work during a Sprint?
(choose the best answer)
True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders
A Scrum Team is a cohesive unit of professionals that consists of which of the following? (Choose all that
apply.)
What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement
about which agile practices to apply? (Choose the best two answers.)
Why does the Product Owner want the Development Team to adhere to its definition of “Done”?
Which answer best describes the topics covered in Sprint Planning? (Choose the best answer.)
Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)
What factor should be considered when establishing the Sprint length?
(choose the best answer)
True or False: A scrum Master Fulfills me same role as a traditional project Manager.
During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master? (Choose two.)
Who determines how many Product Backlog items the Developers select tor a sprint? (choose the best answer)
What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)
You are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the developers come to you complaining that work identified for the upcoming two Sprints will require full-time commitment from a technical specialist who is external to the teams. What are two key concerns for the Scrum Master to take into account in this situation? (Choose two.)
Which three questions might be answered by Development Team members at the Daily Scrum? (Choose three.)
What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)
When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
Which two things should the Development Team do during the first Sprint? (Choose two.)
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)
A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items “Done” by the end of the Sprint. Which three phrases best describe the purpose of a definition of “Done”? (Choose three.)
True or False A scrum Master fulfills the same role as a traditional Project Manager