Eight months ago your company started developing a new product consisting ot several major components. You are the Scrum Master on the team building the "core" component of the product; your component also integrates all the other components.
The Scrum Teams work in monthly Sprints, and the team has forecast that it will deliver the integrated product in three Sprints. Recently the team's progress slowed because of changes to the other components that they integrate. The program manager is extremely upset when they find out that the team will need two more Sprints. The project managers of the other components confirm their adherence to the original forecast.
As a Scrum Master, what could you do to help the Product Owner?
(choose the best answer)
Your Scrum Team has been working together for over a dozen Sprints. The Scrum Team consists of 10 members. Each Sprint takes four weeks. As a Scrum Master, you observe that the Developers are hardly collaborating; during the Sprint, members are primarily working on their own items. You also notice that the items on the Sprint Backlog are mostly unrelated. You suspect that the lack of a Sprint Goal might be the cause.
Although you have encouraged the use of a Sprint Goal, both the Product Owner and the Developers have concluded that they are unable to create Sprint Goals based on the wide variety of items on their Product Backlog.
What might explain why this Scrum Team is struggling to craft a Sprint Goal?
(choose all that apply)
In the Sprint Retrospective, there is discussion that the quality of the Increment is not sufficient tor going to production In response, a Scrum Team member points out the high velocity reached by the team. What are the two best actions tor the Scrum Master to take?
(choose the best two answers)
Scrum Master is a management position because the Scrum Master is accountable for the following three management activities:
(choose the best three answers)
What are two signs that a Scrum Team is self-managing?
(choose the best two answers)
One Scrum Team is developing a product. They track how much software they produce as velocity. Their current velocity is 18 units of done work. A second team will be added to work on the same product. What is the most likely impact on the velocity of the original team?
(choose the best answer)
A Scrum Team selected a Product Backlog item during Sprint Planning. However, at the end of the Sprint the work does not meet the Definition of Done. What two things should happen with this incomplete Product Backlog item?
(choose the best two answers)
What are two ways in which technical debt relates to velocity?
(choose the best two answers)
What conditions are most likely occurring if you feel you need a "Quality Assurance and Release Readiness Sprint"?
(choose the best three answers)
Scrum requires a Definition of Done. Which phrases describe the purpose of the Definition of Done?
(choose the best three answers)
How should requirements be distributed when multiple Scrum Teams work on the same product?
(choose the best answer)
You have just been hired as a Scrum Master by a company new to Scrum. The company wants to use Scrum to build a new product that was conceived by the product management department. You will be the Scrum Master of two new teams that will build a first version of the product. The product management department assigns two new Product Owners, but wants more advice about the required participation with the new Scrum Teams. Which two suggestions would you offer?
(choose the best two answers)
During Sprint Planning, Developers work with the Product Owner to create a forecast for the Sprint. A forecast is a selection of Product Backlog items that the Developers believe are possible to get done by the end of the Sprint. Select two things that explain what done means.
(choose the best two answers)
Which two options describe how project budgeting and financial forecasting work in Scrum?
(choose the best two answers)