Winter Special Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 713PS592

PSP Planning & Scheduling Professional (PSP) Exam Questions and Answers

Questions 4

Which of the following is NOT true?

Options:

A.

Remaining durations can exceed original durations.

B.

Constraints can interfere with the longest path calculation.

C.

Multiple calendars can affect the total float calculation.

D.

A network must contain only one Critical Path.

Buy Now
Questions 5

Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

PSP Question 5

Options:

A.

Predecessor is activity 5001, successor is activity 8001

B.

Predecessor is activity 4001, successor is activity 8001

C.

Predecessor is activity 9001, successor is activity 9002

D.

Predecessor is activity 5001, successor is activity 8002

Buy Now
Questions 6

Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

PSP Question 6

Options:

A.

After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

B.

After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

C.

After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

Buy Now
Questions 7

Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?

Options:

A.

19 Sep 2021

B.

08 Sep 2021

C.

09 Sep 2021

D.

27 Aug 2021

Buy Now
Questions 8

Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

PSP Question 8

Options:

A.

09-28-01.

B.

09-08-01.

C.

09-15-01.

D.

09-18-01.

Buy Now
Questions 9

Identify the late finish to develop plans and specs.

PSP Question 9

Options:

A.

9 months.

B.

10 months.

C.

8 months.

D.

7 months.

Buy Now
Questions 10

For which of these delays should an owner grant a time extension?

Options:

A.

Structural steel shop drawings.

B.

Shop drawings and centrifuge delay.

C.

Differing site conditions at parking structure.

D.

Differing site conditions and centrifuge delay.

Buy Now
Questions 11

Estimate to complete (ETC) is __________________.

Options:

A.

The expected remaining cost needed to complete an activity, group of activities or the project

B.

The costs actually incurred in accomplishing the work performed

C.

The expected total cost of an activity, group of activities or the project

D.

The value of the completed work expressed in terms of the budget assigned to that work

Buy Now
Questions 12

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

PSP Question 12

Options:

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

Buy Now
Questions 13

What was the original planned duration for Activity A through Activity G?

PSP Question 13

Options:

A.

26.

B.

28.

C.

24.

D.

25.

Buy Now
Questions 14

What project cost elements would NOT normally be reflected in the Activity 1000?

Options:

A.

Home office expenses

B.

CPM processing and updating

C.

Materials used in the construction

D.

Job site quality control

Buy Now
Questions 15

A driving relationship is _____________________.

Options:

A.

A critical relationship.

B.

A finish-to-start relationship.

C.

The link between two related activities.

D.

The link between a predecessor and the activity whose dates it controls.

Buy Now
Questions 16

Constraints control events or activities that __________________.

Options:

A.

Affect only the forward pass.

B.

Are not based on project relationships.

C.

Affect only the backward pass.

D.

May be over-ridden by activity logic.

Buy Now
Questions 17

Which of the following is NOT required when initially planning a project?

Options:

A.

Resource Identification and leveling.

B.

The duration of each task.

C.

A schedule that identifies tasks required on a project.

D.

Logical relationships between the tasks.

Buy Now
Questions 18

Determine the correct formula and date for the late finish for Activity 2001.

PSP Question 18

Options:

A.

LF.2001 - 1 day -> 08-28-01.

B.

LS.2002- 1 day-> 08-29-01.

C.

LS.2002 + 1 day -> 08-30-01.

D.

LS.2002 - 1 day -> 08-28-01.

Buy Now
Questions 19

These are the activities on the critical path:

PSP Question 19

Options:

A.

A, D, & I.

B.

A, C, E, & H.

C.

A, B, G, & H.

D.

A, B, F, & J

Buy Now
Questions 20

Project delays are best analyzed

Options:

A.

After either the contractor or the owner acknowledges ^responsibility for the delay.

B.

Contemporaneously with the delay.

C.

By an expert after the project is finished when complete records are available and the impact is known.

D.

Late in the project.

Buy Now
Questions 21

Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

PSP Question 21

Options:

A.

06-11-02.

B.

06-04-02.

C.

06-18-02.

D.

06-05-02.

Buy Now
Questions 22

The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it____________.

Options:

A.

uses arrows to signify logic in a network

B.

allows more than one critical path to be represented

C.

can be used to calculate the late start and late finish of all activities

D.

allows multiple relationship types to be associated with activities

Buy Now
Questions 23

What does the heavy, vertical line at "X" represent?

PSP Question 23

Options:

A.

Delay fault line.

B.

The status or data date.

C.

Change-over limits.

D.

International Date Line.

Buy Now
Questions 24

Under which circumstance should one perform resource-leveling calculations?

Options:

A.

When the contract contains a provision for float-banking.

B.

When you believe that known resource limitations may override schedule logic.

C.

Never, unless required by the contract.

D.

When the schedule is resource-loaded.

Buy Now
Questions 25

Which of the following is NOT input data to the construction planning process?

Options:

A.

Input from the owner

B.

The contract

C.

Bonding capacity of subcontractors

D.

Input from the contractor

Buy Now
Questions 26

If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?

Options:

A.

Predecessor is Activity 4001. successor is Activity 9004

B.

Predecessor is Activity 8001, successor is Activity 5001

C.

Predecessor is Activity 5001, successor is Activity 8001

D.

Predecessor is Activity 4001, successor is Activity 9003

Buy Now
Questions 27

What is the cycle time?

PSP Question 27

Options:

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Buy Now
Questions 28

The data date or status date of a schedule represents the:

Options:

A.

date the monthly update is performed

B.

date the project manager turns in the schedule update

C.

system date when the software calculates the update

D.

date on which progress is based

Buy Now
Questions 29

Total float is defined as the amount of time an activity can be delayed without impacting

Options:

A.

The overall project completion

B.

The buoyancy of a successor activity

C.

The next activity

D.

The end of that activity

Buy Now
Questions 30

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Options:

A.

Projected crew size

B.

Estimated labor hours

C.

Hours in a standard work day

D.

Estimated cost

Buy Now
Questions 31

What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

Options:

A.

ADM is limited to finish-to-start logic relationships, while PDM is not.

B.

PDM is a bar chart with network logic, while ADM is a pure logic network.

C.

ADM is manual CPM calculations, while PDM is computerized.

D.

ADM uses arrows, while PDM uses boxes.

Buy Now
Questions 32

Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

PSP Question 32

Options:

A.

450 lifts

B.

300 lifts

C.

45 lifts

D.

150 lifts

Buy Now
Questions 33

How could the structural steel drawing delay have been prevented?

Options:

A.

Add a time buffer at the end of structural steel activities.

B.

Allow adequate time for review and resubmittal in the baseline schedule.

C.

Release the structural steel for fabrication concurrent with review of structural steel shop drawings.

D.

Switch to post-tensioned concrete construction.

Buy Now
Questions 34

Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

PSP Question 34

Options:

A.

8 work days

B.

18 work days

C.

7 work days

D.

15 workdays

Buy Now
Questions 35

What is the result of a forward pass calculation?

Options:

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

Buy Now
Questions 36

Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

Options:

A.

Estimating remaining durations of activities.

B.

The correct recording of actual start dates.

C.

Making "downstream" logic revisions as required.

D.

Entering the time impacts of delays and change orders.

Buy Now
Questions 37

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

Options:

A.

Finish-no-earlier constraint on the first activity

B.

Finish-no-earlier constraint on the last activity

C.

Finish-no-later constraint on the last activity

D.

Start-no-later constraint on the first activity

Buy Now
Questions 38

Which of the following phases does NOT describe the commonly accepted construction life cycle?

Options:

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.

Buy Now
Questions 39

In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

PSP Question 39

Options:

A.

2003 and 7001.

B.

2004.

C.

4001, 5001 and 6001.

D.

4001 and 5001.

Buy Now
Questions 40

For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

PSP Question 40

Options:

A.

LS.11001 + 25 days.

B.

02-19-04.

C.

EF.11001.

D.

EF.11001 + 1 day.

Buy Now
Questions 41

Determine the correct formula and date for the late finish for Activity 2002.

PSP Question 41

Options:

A.

LS.2003 - 1 day -> 11.06.01.

B.

LS.2003 - 1 day -> 10-06-01.

C.

LS.2003 + 1 day -> 10-07-01.

D.

LS.2003 - 1 day -> 10-05-01.

Buy Now
Questions 42

Background

Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.

It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.

You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.

With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.

In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.

1. Pull the project team together and ensure everyone understands which activities are on the critical path. Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.

2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.

3. Mandatory overtime for the project team - entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.

4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.

Assignment

Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:

a. the current problem and potential impact(s);

b. each course of action, stating advantages and disadvantages as appropriate;

c. your recommendations, properly supported.

Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).

While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.

Take time to read the problem and consider what you want Evan to say. Good luck!

Options:

Buy Now
Questions 43

If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

Options:

A.

8 days

B.

6 days

C.

4 days

D.

5 days

Buy Now
Questions 44

Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

PSP Question 44

Options:

A.

$271,000

B.

$299,000

C.

$139,000

D.

$289,000

Buy Now
Questions 45

Which of the following is NOT required when performing weekly or monthly schedule updates?

Options:

A.

Percent complete.

B.

Remaining duration of activities.

C.

Actual finish of activities.

D.

Original duration of activities.

Buy Now
Questions 46

What does the narrow band at "Y" represent?

PSP Question 46

Options:

A.

Resource limitation period.

B.

A rework period.

C.

Activity inactivity.

D.

You cannot tell with the information supplied.

Buy Now
Questions 47

Using the normal schedule, what is the owner's total cost of the project?

Options:

A.

S13.990.600

B.

S12.990.000

C.

S13.102.900

D.

S12.953.600

Buy Now
Questions 48

Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

PSP Question 48

Options:

A.

407 days

B.

362 days

C.

255 days

D.

267 days

Buy Now
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Feb 5, 2025
Questions: 163

PDF + Testing Engine

$66  $164.99

Testing Engine

$50  $124.99
buy now PSP testing engine

PDF (Q&A)

$42  $104.99
buy now PSP pdf