A component protect of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations
What should the program manager do next?
A program manager takes over a global program from another program manager. Upon arriving on-site, the program manager immediately sees that stakeholders are upset because of a lack of updates and communications about the program.
What should the program manager do first?
A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals A materials supplier informs the program manager that when this agreement is finalized, it will shorten the products delivery time.
What should the program manager update first?
During program execution, a program manager receives feedback from an executive sponsor (hat some program stakeholders may not understand the intended benefits of the program. Which will provide the greatest value to clarify stakeholder perceptions?
The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C.
Which of the following should the program manager do first?
When considering pathway types, the ICT distribution designer should consider the applicable MICE factors as defined in TIA 568 for structured cabling systems and components MICE 3 relates to
The MINIMUM required for backbone floor to floor pathways is five (5) sleeves each being 103 mm (four trade size) in diameter What increase in usable floor space should another 103 mm (four trade size) sleeve be added?
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program manager was asked to transition the program into operations.
At this stage, what is expected during the post-review session organized by the program manager?
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?
In an office area, a consultant needs to add the location of a fax machine to the plan. What is the approximated floor area that a fax machine occupies?
The program manager defines the program objectives, requirements and develops a high-level road map. To ensure program alignment with the enterprise strategic plan the program manager should work with which of the following?
A program has been established and preparation is complete. Component projects are planned as a part of which of the following?
An ICT distribution designer is estimating the installation of five units of 1.5 m (5 ft) tong channel basket trays connected together in the ceiling. The total length of the pathway needed is 7 5 m (25 ft). How many supports will be needed''
Which of the following statements Is CORRECT concerning best practice for horizontal cable management panels?
An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.
How should the junior project manager respond to this request?
A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program's benefits sustainment and transition plan What should the program manager do to create this plan?
A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.
What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?
An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts the program manager discovers the program may be shut down due to lack of funding.
To ensure continued funding for the program, what should the program manager do next?
When designing a video communications network, which type of video communication link is two-person videoconferencing?
The program manager takes over a poorly performing program After a review of the documentation and interviews with the program sponsor, stakeholders and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent protects and components to meet the program's needs
What action should the program manager take to realign the program?
What's the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)
In specifying labels and pruned tags that meet Underwriters Laboratories (UL) 969 Standard, marking and labeling systems are provided following the listed metrics. Which two of the following are REQUIRED for the UL standard? (Select two options.)
A two-year program is coming to an end Many of the initial governance board members have moved from their current posts or left the company Several new members have joined but have a shod association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.
How should the program manager handle this situation?
Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly. Which two of the following conditions could be caused by a poorly supported cabled (Select two options.)
A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?
While setting up a program's infrastructure and plan, a program management team develops documents and processes that provide commonality and consistency throughout the program's components. What should the team also prepare, if not already provided by the organization's assets?
What actions are taken in the process of developing and maintaining a program risk register?
Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?
Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance
To resolve this situation, which of the following must go through critical review and change"?
The program manager has a global program with live component projects. The program sponsor wants the management plans, processes/procedures and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six months into a three-year program.
What should the program manager do next?
You are designing distribution for a seven unit townhouse with in slab conduits. What is the MINIMUM number of 27 mm (1 in) rigid PVC Type 2 or metallic conduit that is required to satisfy distribution to each unit?
The program manager wants to increase the team's commitment to the program objectives. The program manager should do which of the following?
A program will generate revenue for several years after it ends. The program manager and the operations manager, who are accountable for managing the benefits after program closure, are in disagreement. The operations manager is concerned that information necessary for managing the processes and benefits after program closure will be unavailable. The program manager expresses that managing the benefits after program closure is not within the scope and must be managed through the scope management plan.
What should the program sponsor do?
Which requirement does the ICT distribution designer provide to the Mechanical Engineer in charge of the HVAC design for a Telecommunication Space?
The new performance financial system is delivered lo all business entities on time following a one-year implementation program After six months of utilization the global finance department one of the main beneficiaries of the program, determines that quality and level of granularity of the financial data is not sufficient for them to analyze the key performance indicators (KPIs) defined Additionally, the global finance department is missing the analytical tools required to understand the causes of discrepancies
To address these shortcomings the global finance department submits a request for a follow-up initiative through the process defined by which of the following documents?
For optical fiber cabling, which of the following test instruments is used to locate and identify any anomalies?
A new component project is approved by the program governance board. The funding for this component project will be provided by an organization different from the organization funding the program
Would this be an acceptable funding arrangement?
A program sponsor is concerned about the status of high-priority risks and budget variances. The program manager should refer lo which of the following?
During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers. The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?