SAFe-RTE SAFe Release Train Engineer (RTE) Questions and Answers

Questions 4

The Release Train Engineer (RTE) learns the teams feel the business value does not re-flect the effort and progress. What are two ways the RTE can provide a better under-standing of what the teams have created? (Choose two.)

Options:

A.

Educate teams that business value provides the Enterprise with a Metric of how fast the team executed work during the PI

B.

Coach the Business Owner's review of objectives to see that scoring is against the specific details negotiated with the team during PI Planning

C.

Illustrate the linkage between business values and the market communica-tions/release objectives tied to the three to six month Enterprise strategy

D.

Work with the team to ensure they are actively involved when the Business Own-ers score the business value achieved

Publish the team business values and coach teams that these values are for track-ing each Agile Release Train deliverable

Buy Now
Questions 5

Several Scrum Masters seem to be deadlocked in a disagreement on what to do about a shared issue. What is an appropriate coaching technique for the RTE to use?

Options:

A.

Driving an empirical assessment of the problem using metrics

B.

Asking powerful questions to invite creativity and new possibilities

C.

Being the final "decision making authority" once all views have been heard

D.

Bringing fresh emphasis to lean-agile's respect for people and culture

Buy Now
Questions 6

Which statement describes the three elements that the Innovation and Planning Iteration provides?

Options:

A.

Releasing, Continuous Integration, and planning

B.

Innovation, planning, and an estimating guard band

C.

Iteration Planning, User Story refinement and estimating

D.

Estimating techniques, training, and innovation

Buy Now
Questions 7

What are personas?

Options:

A.

Descriptions of actual target customers or users

B.

Key end-users the Product Owner leverages for managing the backlog

C.

Fictional representations of target customers or users

Buy Now
Questions 8

Which type of Enabler does a System Architect review during a System Demo?

Options:

A.

Enabler Epics

B.

Enabler Features

C.

Enabler Capabilities

D.

Enabler Stories

Buy Now
Questions 9

Which SAFe Core Competency incorporates guidance on coordinating trains and suppli-ers?

Options:

A.

Enterprise Solution Delivery

B.

Business Agility

C.

Measure and Grow

D.

Lean Portfolio Management

Buy Now
Questions 10

Which SAFe Core Competency requires exemplifying the principles and values of lean-agile?

Options:

A.

Continuous Learning Culture

B.

Agile Product Delivery

C.

Organizational Agility

D.

Lean-Agile Leadership

Buy Now
Questions 11

At which Tuckman stage would an ART be if it is improving engineering practices and fostering more effective communication?

Options:

A.

Storming

B.

Performing

C.

Forming

D.

Norming

Buy Now
Questions 12

Which two actions must the Release Train Engineer (RTE) take when facilitating the Pro-gram Increment (PI) Planning event? (Choose two.)

Options:

A.

Prioritize the Features

B.

Distribute the PI Planning agenda to the Agile Teams

C.

Purchase sugary snacks

D.

Ensure the facilities are set up appropriately

E.

Wear the RTE visor

Buy Now
Questions 13

Which statement is true about nonfunctional requirements?

Options:

A.

They stay in the Portfolio Backlog until implementation capacity is available

B.

They are split into Features and acceptance criteria is established

C.

They operate as constraints on the design of the system

Buy Now
Questions 14

Which of the following is true about the ART sync event?

Options:

A.

It is run after PO-sync and Scrum of Scrum events

B.

It is a combination of PO-sync and Scrum of Scrums events

C.

It occurs during the Innovation and Planning iteration

D.

Attendance by the entire ART is important

Buy Now
Questions 15

The Agile Release Train (ART) is near the end of the final Iteration of their first Program Increment. Integration into staging is more challenging than estimated. They add a week to the Innovation and Planning (IP) Iteration for integration and testing. Why is this a bad idea?

Options:

A.

Overall train velocity goes up and the time-to-market goes down

B.

It substantially decreases the predictability of the Solution Intent

C.

It reduces the overall predictability established through cadence and synchroniza-tion

D.

It decreases job satisfaction by removing autonomy and purpose

Buy Now
Questions 16

Which core competency helps foster faster lead time, faster recovery, fewer defects, and more frequent deployments?

Options:

A.

Lean-Agile Leadership

B.

Enterprise Solution Delivery

C.

Team and Technical Agility

D.

Agile Product Delivery

Buy Now
Questions 17

Which activity takes place during Team Breakout #2 on the second day of Program In-crement (PI) Planning?

Options:

A.

The RTE modifies the PI Iteration schedule, if needed, based on the scope of high priority Features

B.

Business Owners assign business value without team discussion so they can nor-malize business value across all teams on the Agile Release Train

C.

All Feature delivery and dependencies are visualized on the program board

D.

The Release Train Engineer (RTE) combines all Team PI Objectives into Program PI Objectives

Buy Now
Questions 18

What is one way to secure stakeholder commitment to the Agile Release Train?

Options:

A.

Provide them a planning schedule outlining a five-year plan for development

B.

Have them estimate User Stories for the teams

C.

Send them the Program Increment (PI) Objectives after each PI Planning event

D.

Have them attend the Program Increment (PI) Planning event

Buy Now
Questions 19

What is a characteristic of an effective Scrum Master?

Options:

A.

Gives open, honest opinions

B.

Removes all conflict

C.

As a technical expert

D.

Understands customer needs

Buy Now
Questions 20

What foundational issue most often leads to team dysfunction?

Options:

A.

Absence of trust

B.

Weak Lean-Agile leadership

C.

Fear of conflict

D.

Lack of commitment

Buy Now
Questions 21

After an Agile Release Train's first Program Increment (PI) Planning event, what action can the Release Train Engineer take to help optimize the Program Backlog readiness for the next PI?

Options:

A.

Ask Product Management and the System Architect what the new Program Back-log looks like just before the next Innovation and Planning (IP) Iteration, so social-ization can begin

B.

Compile all the teams' objectives from PI Planning and send out a summary report

C.

Coach Product Management and the System Architect to include Program Backlog refinement into their cadence-based approach

D.

Ask the Lean Portfolio Management function to hold regular Epic review meetings so new Epics will flow to the Agile Release Train

Buy Now
Questions 22

How can a Release Train Engineer support decentralized decision making?

Options:

A.

Update team Program Increment (PI) Objectives when shipping a time critical re-lease

B.

Empower knowledge workers to manage their dependencies with other teams

C.

Evaluate the strategy for the Value Stream

D.

Change the cadence of the Agile Release Train

Buy Now
Questions 23

An effective Scrum Master is a team-based servant leader who helps the team do what?

Options:

A.

Embrace relentless improvement through Iteration retrospectives

B.

Understand and operate within Lean Budgets

C.

Develop better and more specialized skill sets

D.

Manage the team's own backlog

Buy Now
Questions 24

What is one way Kanbans are used in SAFe?

Options:

A.

To manage queue length

B.

To manage runway cadence

C.

To manage Program Increment (Pl) Objectives

Buy Now
Questions 25

When is one time a Scrum Master may be a participant rather than a facilitator?

Options:

A.

If the entire team is present during the daily stand-up

B.

During team breakout sessions at Pl Planning

C.

When using ad hoc teams for Inspect and Adapt

D.

When the Agile Release Train does not require any team coordination

Buy Now
Questions 26

How are the 5 Whys used?

Options:

A.

To coach a team through powerful questions

B.

To brainstorm ideas

C.

To define acceptance criteria for a Story

D.

To identify a root cause(s) of a problem

Buy Now
Questions 27

Why do teams have an Iteration retrospective?

Options:

A.

To identify acceptance criteria

B.

To adjust and identify ways to improve

C.

To evaluate Metrics

D.

To iterate on Stories

Buy Now
Exam Code: SAFe-RTE
Exam Name: SAFe Release Train Engineer (RTE)
Last Update: Nov 23, 2024
Questions: 214